HHS0016943v2_Attach C_Project Special Conditions.pdf

PDF 174 KB Posted

Attached to
Water Improvements at El Paso Psychiatric Center
Solicitation number
HHS0016943v2
Issued by
El Paso County, Texas

About this file

This is a Project Special Conditions attachment document for a Texas Health and Human Services Commission (HHSC) construction contract, establishing supplementary requirements to the Texas Uniform General Conditions for Construction Contracts. The document outlines mandatory insurance and liquidated damages provisions applicable to the contractor performing work under this agreement. The contract requires contractors to achieve Substantial Completion in accordance with an approved work schedule, with the specific Substantial Completion date and Notice to Proceed to be issued by the Owner. The Owner retains the option to stage or "fast-track" portions of the work, with each stage receiving a separate Notice to Proceed and individual substantial completion date. The Construction Phase commences on the date specified in the Notice to Proceed, and contractors must achieve both Substantial Completion and Final Completion by the dates established in the Notice to Proceed and Contract, subject only to time extensions granted by Change Order.

The contract mandates Pollution Liability Insurance with minimum coverage limits of $1,000,000 per claim and $1,000,000 aggregate, with occurrence-based coverage required for all claims arising from pollution conditions related to contractor operations. The pollution liability policy must remain in force for ten years after project completion or contract termination, whichever occurs later, and must name the Owner Group as Additional Insureds. Contractors will face liquidated damages assessments of $150.00 per calendar day or part thereof for failure to meet the Substantial Completion date, with the Owner having sole discretion to assess damages. The Owner may withhold liquidated damages from contractor payments, demand payment within thirty days, or make claims against the performance bond. The Owner retains the right to assess liquidated damages regardless of whether prior notice of assessment was provided, and individual liquidated damages clauses remain enforceable even if other portions are deemed unenforceable.

View the file

Other files

File Type Posted
HHS0016943v2 PPW Attendance Roster.pdf PDF
HHS0016943v2 Attach H-3_Addendum 1 to Project Drawings and Project Specifications.pdf PDF
HS0016943v2 HSP Training.pdf PDF
ESBD_510337_1780518856960_RFP HHS0016943v2_Addendum 2.pdf PDF
HHS0016943v2 Site Visit Sign in Sheet.pdf PDF
HHS0016943v2 Addendum 2 PCS 121.pdf PDF
HHS0016943v2 Responses to Questions.pdf PDF
HHS0016943v2 Addendum 1 PCS 121.pdf PDF
HHS0016943v2_Attach F_Signed Pricing Proposal.pdf PDF
HHS0016943v2_Attach D_Facility Specific Policies and Procedures.pdf PDF
HHS0016943v2_Attach B_Texas UGCs (Version 2.2).pdf PDF
HHS0016943v2_Attach H-1_Project Drawings.pdf PDF
HHS0016943v2_Exhibit B_HUB Requirements.pdf PDF
HHS0016943v2_Attach H-2_Project Specifications.pdf PDF
HHS0016943v2_Attach G_HSP.pdf PDF
HHS0016943v2_Exhibit F_Respondent's Pricing Proposal Form.pdf PDF
HHS0016943v2_Exhibit G_Evaluation Tool.pdf PDF
HHS0016943v2_Exhibit A_Affs_and_Solicitation_Acceptance.pdf PDF
ESBD_510337_1777054076977_RFP HHS0016943v2.pdf PDF
HHS0016943v2_Exhibit D_Exceptions Form.pdf PDF
HHS0016943v2_Attach J_HHS UTCs - Vendor v 3.4 Nov 2023.pdf PDF
HHS0016943v2_Exhibit H_Site Visit Location.pdf PDF
HHS0016943v2_Exhibit E_Respondent's Information, Disclosures, and Financial Form.pdf PDF
HHS0016943v2_Attach A_Contract_Affs.pdf PDF
HHS0016943v2_Exhibit C_Draft General Construction Services Contract.pdf PDF
HHS0016943v2_Attach E_Prevailing Wage Rates.pdf PDF
HHS0016943v2_Attach I_Negotiated Modifications to the Proposal.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Template Updated: September 2025

Attachment C

Project Special Conditions

Attachment C

Project Special Conditions

Article I. INSURANCE

1.1 Subsection 5.2.6.1.2 of the Texas Uniform General Conditions for Construction Contracts with

HHSC Supplementary General Conditions, Version 2.2, is hereby deleted in its entirety and replaced with the following:

1.2 Subsection 5.2.6.1 of the Texas Uniform General Conditions for Construction Contracts with

HHSC Supplementary General Conditions, Version 2.2, is hereby amended by adding a new Subsection as follows:

5.2.6.1.9 Contractor’s Pollution Liability Insurance. Contractor’s Pollution Liability

Insurance, with minimum limits of coverage not less than shown below, providing occurrence based coverage for all claims, liabilities, damages, costs, fees, and expenses, including but not limited to claims for bodily injury or death, property damage, environmental or natural resource damage, and any civil fines, fees, civil assessments or civil penalties or punitive, exemplary or multiplied damages assessed by any governmental department, agency. commission or court, arising out of any Pollution Condition(s) (as defined below) that is in any way related to Contractor’s or Contractor’s Personnel’s operations, actions or inactions or completed operations associated with any Work performed by Contractor or Contractor personnel. If coverage is written on a Claims Made and Reported Policy form, the policy retroactive date for prior acts coverage shall be no later than the Contract Effective Date. The pollution liability policy shall be continuously maintained for a period of 10 years after completion of the project or termination of the Contract, whichever occurs later; the Contractor’ purchase of an extended discovery period or an extended reporting period will not be sufficient to comply with Contractor’s obligations hereunder. Such insurance shall name the Owner Group as Additional Insureds. The Pollution Liability policy shall provide coverage for "sudden & accidental and gradual occurrences arising from the work performed under this Contract. The Business Automobile Liability policy shall either be endorsed to provide coverage under the ISO CA9948 endorsement (Broadened Pollution Liability Coverage) and Motor Carrier Endorsement (MCS-90), or the Contractor‘s Pollution Liability policy shall be endorsed to provide transportation coverage beyond the boundaries of the job site, if Contractor activities involve hauling excavated spoil. The Contractor's Pollution Liability policy shall also include coverage for: (i) the full scope of the Contractor’s operations (on-going and completed), as described in the Contract; (ii) losses arising from pollutants, including but not limited to fungus, bacteria, biological substances, mold, microbial matter, asbestos, lead, silica and contaminated drywall; (iii) third party liability for bodily injury, property damage. clean up expenses, and defense costs arising from the Contractor’s operations; (iv) diminution of value and natural resources damages;

(v) contractual liability; (vi) claims arising from Contractor’s use of any owned or non-owned disposal sites arising out of Contractor’ activities in connection with the Contract; (vii) bodily injury to include physical injury, sickness, disease, death, mental anguish, medical monitoring and emotional distress sustained by any person; and (viii) all costs that are related to or that arise out of or the investigation or adjustment of any claim or in connection with any court, arbitration, mediation, state administrative hearing, or other proceeding of any kind, including attorney's fees, expert witness fees, costs, charges and expenses that arise out of or that are related to a Pollution Condition(s). Coverage under this policy shall include a 7-day minimum occurrence period for emergency response costs. The Pollution Liability insurance policy shall not include any type of exclusion or limitation of coverage applicable to claims arising from:

5.2.6.1.9.1 Insured vs. insured actions (however, an exclusion for claims made between insureds within the same economic family is acceptable).

5.2.6.1.9.2 Impaired property that has not been physically injured.

5.2.6.1.9.3. Materials supplied or handled by the named insured; any exclusionary language pertaining to materials supplied by the insured is subject to the Owner's review and approval.

5.2.6.1.9.4 Property damage to the work performed by a contractor.

5.2.6.1.9.5 Faulty workmanship as it relates to clean up costs.

5.2.6.1.9.6. Punitive, exemplary or multiplied damages.

5.2.6.1.9.7. Work performed by subcontractors.

5.2.6.1.9.8. Contractual liability incurred as a result of an injury to an employee of the insured.

“Pollution Condition(s)” means the discharge, dispersal, release or escape of any solid, liquid, gaseous or thermal irritant or contaminant, including, but not limited to, smoke, sewage, vapors, soot, fumes, acids, alkalis, toxic chemicals, medical waste, mold, silt, sedimentation, low level radioactive material and waste materials into or upon land, the atmosphere or any watercourse or body of water, including groundwater, provided such conditions are not naturally present in the environment in the amounts or concentrations discovered.

Pollution Liability Insurance $1,000,000.00 Each Claim / $1,000,000.00 Aggregate

Article II. LIQUIDATED DAMAGES

2.1 Subsection 9.11 of the Texas Uniform General Conditions for Construction Contracts with

HHSC Supplementary General Conditions, Version 2.2, is hereby amended by adding new Subsections as follows:

9.11.1 Owner is entitled to full and beneficial occupancy and use of the completed Work. If

Contractor fails to meet Substantial Completion of any portion of the Work in accordance with the approved Work schedule, Owner will sustain actual damages as a result of such failure.

9.11.2 Contractor agrees that:

(1) establishing the precise measure of damages in the event of default by the

Contractor may be (i) costly, (ii) time consuming, or (iii) difficult or impossible to calculate;

(2) the liquidated damage assessments in this section represent a good faith effort to quantify the damages that could reasonably be anticipated at the time of execution of the Contract;

(3) the liquidated damages in this section are just and reasonable and are not a penalty;

(4) nothing contained in this section shall be construed as relieving the Contractor from performing all Contract requirements whether or not said requirements are set forth herein; and

(5) All assessments of damages shall be within the sole discretion of the Owner.

9.11.3 Liquidated Damages Assessment. Once the Owner has determined that liquidated damages are to be assessed, the Owner shall notify the Contractor of the assessment(s). Failure to notify does not impact the Owner’s assessment of damage and is not a condition precedent thereto. The Owner will withhold liquidated damages from payments to the Contractor, or, if no payments have been made, the Owner will make demand of payment of liquidated damages. The Contractor must make payment within 30 days of the Owner’s demand. In the event the Contractor fails to pay within the 30 day period, the Owner may make a claim for payment against the performance bond, with or without notice to the Contractor. In the alternative and at Owner’s sole discretion, the Owner may deduct liquidated damages from the Contract Sum payable to Contractor as stated in the UGCs, Standard Construction Terms and Conditions, or Project Special Conditions.

9.11.4 Failure to Assess Liquidated Damages. The failure of the Owner to assess liquidated damages in any instance where the Owner is entitled to liquidated damages pursuant to the terms of this Contract shall not constitute waiver in any fashion of the Owner’s rights to assessment of liquidated damages.

9.11.5 Severability of Individual Liquidated Damages Clauses. If any portion of Section

9.11 is determined to be unenforceable, the other portions of Section 9.11 will remain in full force and effect.

9.11.6 Failure to Meet Substantial Completion Date. The failure of the Contractor to meet the Substantial Completion date for any portion of the Work in accordance with the approved Work schedule under Article 9, Construction Schedules, Texas Uniform General Conditions for Construction Contracts with HHSC Supplementary General Conditions, Versions, 2.2, may result in the assessment of liquidated damages in the sum of $150.00 for each calendar day, or part of a day, after the Substantial Completion Date that the Work remains incomplete. This sum is not construed in any sense as a penalty

9.11.7 Time of Completion

9.11.7.1 The date for achieving Substantial Completion of the Project shall be set forth within the Owner’s Notice to Proceed.

9.11.7.2 The Construction Phase will be deemed to commence on the date specified in a Notice to Proceed issued by Owner.

9.11.7.3 Contractor will achieve Substantial Completion of the Work and Final

Completion of the Work on or before the dates set forth within the Notice to Proceed and the Contract, subject to time extensions granted by Change Order.

9.11.7.4 The times set forth for completion of the Work in the Notice to Proceed with

Construction are an essential element of the Contract. Owner may elect, at its option, to stage or “fast-track” portions of the Work. Owner will issue a separate Notice to Proceed or Change Order for each such stage and each such stage will have a separate substantial completion date.

(The Remainder of this Page is Intentionally Left Blank)