HDEC03‐11‐R‐0001 – Section J Attachment 18 5 Aug 2011
DESIGN-BUILD REQUEST FOR PROPOSAL
for
Architectural and Refrigeration Upgrade to Commissary
MCGUIRE AFB, NEW JERSEY
DeCA Project Number EA10MI09
July 31, 2011
The following shall be included as additional Design-Build requirements for this project:
1. The entire existing 4-ply asphalt roof system shall be removed and replaced with a new black Ethylene-Propylene-Diene-Monomer Roofing (EPDM) system. The work shall include the complete removal of the existing roof system including roof membrane, flashing, counter-flashing, insulation, crickets, gravel guard, parapet coping, fascia, roof drain assemblies, and roof hatches.
2. Include provisions for the repair and/or replacement of up to 3000 s.f. of existing damaged or deteriorated metal roof decking uncovered during demolition of the existing roof system.
3. Comply with DeCA Design Criteria and Guide Specifications.
4. Coordinate the roof system replacement with all Architectural, Structural, Plumbing, Mechanical, Electrical and Refrigeration requirements.
5. The attached Infrared Moisture Survey prepared by Roof Consulting Service, Inc., dated 4/7/2011 is provided for information only. Paragraph 1.8 of Section 01000, Scope of Work applies to the information provided in this survey.
End