FASPP_Q A__6.pdf

PDF 29 KB Posted

Attached to
Federal Aggregated Solar Procurement Project (Photovoltaic installatioins)
Solicitation number
GS-09P-15-KS-C-7000
Issued by

About this file

Questions and answers 6

View the file

Other files

File Type Posted
SF1449-GS-09P-15-KS-C-7000.pdf PDF
FASPP_Q A__5.pdf PDF
C.5.2_System_Minimum_and_Maximum_Capacity_Requirements_Amendment_13_.pdf PDF
Forest_Service_Site_SOW_08202015_(Amendment_13).pdf PDF
Price_Schedule_-_Amendment_13.xlsx XLSX spreadsheet
GS-09P-KS-15-C-7000_SF_30_Amendment_13.pdf PDF
FASPP_SOL_PART_4_SECTIONS__K-M_AMENDMENT_12.pdf PDF
GSA_FASPP_SOL_PART_1_SECTION_C__AMENDMENT13.pdf PDF
GSA_FASPP_SOL_PART_1_SECTION_A B D-H__AMENDMENT_13.pdf PDF
FASPP_Q A__4.pdf PDF
FASPP_2nd_round_site_visits_sign-in_sheets.ZIP ZIP file
GSA_FASPP_SOL_PART_1_SECTION_C__AMENDMENT12.pdf PDF
Forest_Service_Site_Markup_08042015.pdf PDF
GS-09P-KS-15-C-7000_SF_30_Am_12.pdf PDF
GSA_FASPP_SOL_PART_1_SECTION_A B D-H__AMENDMENT_12.pdf PDF
Site_Statements_of_Work_Amendment_12.pdf PDF
Price_Schedule_-_Amendment_12.xlsx XLSX spreadsheet
Peckham_Overall_Roof_Plan.pdf PDF
FASPP_SOL_PART_4_SECTIONS__K-M_AMENDMENT_12.pdf PDF
C.5.2_System_Minimum_and_Maximum_Capacity_Requirements_Amendment_12_.pdf PDF
Forest_Service_Site_Scope_of_Work_08072015.pdf PDF
GS-09P-KS-15-C-7000_SF_30_Amendment_11.pdf PDF
FASPP_SOL_PART_4_SECTIONS__K-M_AMENDMENT_11.pdf PDF
FASPP_SOL_PART_4_SECTIONS__K-M_AMENDMENT_10.pdf PDF
GS-09P-KS-15-C-7000_SF_30_Amendment_10.pdf PDF
FASPP_SOL_PART_4_SECTIONS__K-M_AMENDMENT_9.pdf PDF
Amendment_9_SF_30.pdf PDF
GS-09P-KS-15-C-7000_SF_30_Amendment_8_(corrected_copy).pdf PDF
FASPP_Q A__3.pdf PDF
FASPP_SOL_PART_4_SECTIONS__K-M_AMENDMENT_8.pdf PDF
GSA_FASPP_SOL_PART_1_SECTION__I___Amendment_8.pdf PDF
GS-09P-KS-15-C-7000_SF_30_Amendment_8.pdf PDF
Price_Schedule_-_Amendment_8.xlsx XLSX spreadsheet
FASPP_SOL_PART_4_SECTIONS__K-M_AMENDMENT_7.pdf PDF
GS-09P-KS-15-C-7000_SF30_Amendment_7.pdf PDF
Price_Schedule_-_Amendment_6.xlsx XLSX spreadsheet
C.5.2_System_Minimum_and_Maximum_Capacity_Requirements_Amendment_6_.pdf PDF
GSA_FASPP_SOL_PART_1_SECTION__I___Amendment_6.pdf PDF
GS-09P-KS-15-C-7000_Amendment_6_SF_30.pdf PDF
GSA_FASPP_SOL_PART_1_SECTION_A B D-H__AMENDMENT_6.pdf PDF
Forest_Service_documents.zip ZIP file
Site_Statements_of_Work_Amendment_6.pdf PDF
GSA_FASPP_SOL_PART_1_SECTION_C__AMENDMENT_6.pdf PDF
FASPP_SOL_PART_4_SECTIONS__K-M_AMENDMENT_5_REVISIONS_6-2-15.pdf PDF
GS09P15KSC7000_SF_30_Amendment_5.pdf PDF
GS-09P-KS-15-C-7000_SF_30_AMENDMENT_4.pdf PDF
FASPP_SOL_PART_4_SECTIONS__K-M_AMENDMENT_4_REVISIONS_5-22-15.pdf PDF
FASPP_site_visit_sign-in_sheets _5-11_to_5-15-15.pdf PDF
FASPP_Q A__2.pdf PDF
FASPP_site_visit_powerpoint_presentation_-_11-11_May_2015.pdf PDF
Show 40 more

Latest 50 of 67 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FASPP – QUESTIONS & ANSWERS #6

QUESTION: Can you please confirm that the Government will use the “Expected Production (kWh/year)” (Column 4) provided by each offeror in the file “Price_Schedule_-_Amendment_13.xlsx” as the basis for calculating the Weighted Average Price to Beat for that offeror?

ANSWER: The Government will use the “Warranted Minimum PV Energy Delivered” in the Price Schedule. The Price to Beat constitutes the baseline for calculating the net present value.

QUESTION: Will it be acceptable to trim the trees to the height of the building at the Shea site? Because of shading, we are struggling to meet even the revised Minimum Warranted Production requirement for this site using industry leading solar PV equipment without placing panels in highly shaded areas. Placing panels in shaded areas significantly drives up the cost per kilowatt-hour of energy produced by the panels (and thus drives up the price we can offer to the Government) because shaded panels are underutilized.

The Shea Building itself, which is to the South and East of the parking lot, shades the parking lot, so we have found through our shading analysis that the parking lot location is not suitable for solar PV. If tree trimming to the height of the building is not allowed at this site, we ask that you reduce the Warranted Minimum PV Energy Delivered requirement for this site to 22,000 kWh per year.

ANSWER: Trees may not be trimmed at the Shea FB. We will not reduce the production requirement further.

File details come from the government source that posted it. Updated .