Amendment_0011.pdf

PDF 1 MB Posted

Attached to
New U. S. Courthouse in Harrisburg, Pennsylvania
Solicitation number
GS-03-P-17-AZ-C-0014
Issued by

About this file

Amendment 0011

View the file

Other files

File Type Posted
Amendment_0016.pdf PDF
Amendment_0015.pdf PDF
Proposal_Form_and_Staffing_Plan.xlsx XLSX spreadsheet
Amendment_0014.pdf PDF
Harrisburg_Proposal_Form_12.15.17.xlsx XLSX spreadsheet
Harrisburg_Proposal_Form_10.24.17.xlsx XLSX spreadsheet
Amendment_0012.pdf PDF
2005_Pub_64_Vol_3_JSS_Req_&_Specs.pdf PDF
Proposal_Form_10.16.17.xlsx XLSX spreadsheet
Amendment_0010.pdf PDF
Amendment_0009.pdf PDF
Proposal_Form.xlsx XLSX spreadsheet
Amendment_0008.pdf PDF
Amendment_0007.pdf PDF
Amendment_0006.pdf PDF
Proposal_Form.xlsx XLSX spreadsheet
Amendment_0005.pdf PDF
Form_DS-1_(BLANK).pdf PDF
Amendment_0004.pdf PDF
Amendment_0003.pdf PDF
Amendment_0002.pdf PDF
Amendment_0001.pdf PDF
Attachment_3_-_Small_Business_Utilization_Form.doc DOC document
Attachment_2_-_Past_Performance_Questionnaire.doc DOC document
GSA527.pdf PDF
Attachment_1_-_Past_Project_Form.docx DOCX document
RFP_GS-03-P-17-AZ-C-0014.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

3PQCP

See attached.

3PQCP

General Services Administration 100 S Independence Mall West Philadelphia, PA 19106

General Services Administration 100 S Independence Mall West Philadelphia, PA 19106

GS-03-P-17-AZ-C-0014

1 314

10/17/2017

05/26/2017

Amendment 0011 Solicitation GS-03-P-17-AZ-C-0014

Block 14 continuation:

a) This amendment hereby:

1. removes the CMc 101 - The Agreement, dated September 14, 2017, from the solicitation;

2. removes the Proposal Form, dated September 14, 2017, from the solicitation;

3. removes documents from the Final Concept, issued on September 18, 2017. Offerors shall refer to the government responses to industry questions for the specific documents that have been removed;

4. incorporates government responses to industry questions, as attached to this amendment;

5. incorporates the CMc 101 - The Agreement, dated October 16, 2017, as attached to this amendment;

6. incorporates the Proposal Form, dated October 16, 2017, as attached to this amendment.

i) The government will provide this form in Microsoft Excel; however, the burden of accuracy with regard to formulas shall be on the offeror;

7. incorporates the US Marshals Service Judicial Security Systems Requirements and

Specifications, volume 3, Publication 64, 2005, as attached to this amendment;

8. incorporates revisions to the Final Concept, dated October 16, 2017, to be sent offerors via UPS on Wednesday, October 18, 2017. Offerors shall refer to the government responses to industry questions for the specific documents that have been revised.

9. incorporates the Final Concept in Navisworks format, to be sent offerors via UPS on Wednesday, October 18, 2017. Offerors shall note that the Navisworks format does not include the revisions under block 14, section a, number 8 of this amendment.

10. incorporates a Design Phase Schedule, to be sent offerors via UPS on Wednesday, October 18, 2017.

b) Upon receipt of the UPS package under block 14, section a, numbers, 8, 9, and 10 of this amendment, offerors shall complete the acknowledgement included as page 3 of this amendment and return it to the Contracting Officer and Contract Specialist at the below email addresses, no later than:

Date: Monday, October 23, 2017 Time: 12:00 PM EST Email: Nadya.Popil@gsa.gov and Steven.Sutkin@gsa.gov

c) All other solicitation provisions shall remain unchanged.

Amendment 0011 Solicitation GS-03-P-17-AZ-C-0014

ACKNOWLEDGEMENT PER AMENDMENT 0011 OF GS-03-P-AZ-C-0014

By signature below, I certify that I have received the revisions to the Final Concept, the Final

Concept in Navisworks format, and the Design Phase Schedule for proposal purposes, per

Amendment 0011 of solicitation GS-03-P-AZ-C-0014. I further acknowledge that the information contained within the UPS package are the property of the United States

Government and shall only be utilized for official use. I, or any representative of my company, shall not copy, disseminate, or distribute this information to unauthorized users.

Signature

Name

Title

Company

Government responses to industry questions

# QUESTION GOVERNMENT RESPONSE

Please Reference Amendment 0007: Statement of Work Design Phase Services. On (Section I – Background) the SOW states a copy of the A/E’s scope of work is included as an attachment to the RFP as well as a copy of the CMa’s scope of work. Please provide the scope of work for the A/E and the CMa.

Offerors shall refer to Amendment 0010, which incorporated the scope of work for the A/E and the CMa.

Please clarify Option 1 Site Preparation and Utility Relocation is to be a Firm Fixed Price.

All references to Option 1, Site Preparation and Utility Relocation, shall be changed to a firm-fixed price proposal.

Option 1 Site Preparation and Utility Relocation - Reference C108:

a. Project Notes #18 indicates that all work associated with disconnections or construction of new gas main shall be performed by gas company (UGI Utilities, Inc.). Please confirm that gas company is responsible for removal and restoration of asphalt paving, concrete sidewalks and concrete curb and gutter associated with construction of new gas mains.

Offerors shall refer to Amendment 0011, which removes C108, issued on 09/18/2017 and replaces it with revised C108, dated 10/16/17. The revision addresses the specific responsiblities of the gas company.

Option 1 Site Preparation and Utility Relocation - Reference ES102 and ES103:

a. ES102 and ES103 have different layouts please confirm what sheet is correct.

b. Please provide profiles of the duct banks shown on the Electrical Site Service Plans.

c. Please confirm that the cost for installing the new the duct banks shown on the Electrical Site Service Plans are to be included in the Option 1 Site Preparation and Site Utility Relocation pricing.

d. If we are to install the new duct banks per the Electrical Site Service Plans please confirm we are to include the costs for site restoration including asphalt paving, striping, concrete sidewalks and concrete curb and gutter in the Option 1 Site Preparation and Site Utility Relocation pricing.

e. Please confirm PP&L will furnish and install all new transformers, switchgear and feeders shown on the Electrical Site Service Plans.

f. Please confirm the transformer and switchgear pads shown the Electrical Site Service Plans are to be included in the Option 1 Site Preparation and Site Utility Relocation pricing.

Item a: Sheet ES103 is hereby removed from the Site Preparation Set and shall be considered void with respect to scope of work.

Please follow ES102 for layout and associated scope.

Item b: Duct bank details are shown on ES501.

Item c: Yes; cost for installing the new duct banks shown on the Electirical Site Service Plans are to be included in the Option 1.

Item d: Yes; cost for site restoration including asphalt paving, striping, concrete sidewalks and concrete curb and gutter are to be included in Option 1.

Item e: Yes; PP&L will furnish and install all new tranformers, swichgear and feeders shown on the Electrical Site Service Plan.

Item f: Yes; cost for transformer pads and switchgear pads shown on the ES-102 are to be included in the Option 1.

Option 1 Site Preparation and Utility Relocation - Reference TS101:

a. Please provide profiles of the duct banks shown on the Telecommunications Site Plan.

b. Please confirm that the cost for installing the new the duct banks shown on the Telecommunications Site Plan are to be included in the Option 1 Site Preparation and Site Utility Relocation pricing.

c. If we are to install the new duct banks per the Telecommunications Site Plan please confirm we are to include the costs for site restoration including asphalt paving, striping, concrete sidewalks and concrete curb and gutter in the Option 1 Site Preparation and Site Utility Relocation pricing.

d. Please confirm Others will furnish and install all outside cabling, inner duct in the new duct banks and cable racks in the new manholes shown on the Telecommunications Site Plan.

a: Profiles of the duct banks shown on the Telecommunications Site Plan are unavailable at this time.

b: Yes; cost for installing the new duct banks as shown on the Telecommunications Site Plan are to be included in Option 1.

c: Yes; cost for site restoration including asphalt paving, striping, concrete sidewalks and concrete curb and gutter are to be included in Option 1. Offerors shall refer to Amendment 0011, which removes C108, issued on 09/18/2017 and replaces it with revised C108, dated 10/16/17. The revision includes a revised note section.

d: Yes; cabling, inner duct in the new duct banks and cable racks in the new manholes will be furnished and installed by others.

Please refer to Volume 3 – D. Description of Options. Options 2, 3 & 4 indicate that the respective options “will incorporate scope options identified on the following pages.”

The Bid Form provided in Amendment #7 does not provide a location to report these scope options, other than to incorporate them into the divisional breakout. Please confirm all scope options should be incorporated in the Division breakout.

Offerors shall refer to Amendment 0011, which removes the Proposal Form, dated September 14, 2017 and replaces it with the revised Proposal form, dated 10/16/17. The revised Proposal Form restructures the manner in which offerors shall propose prices for options.

Please clarify whether Option 3 and Option 4 are additive to Option 2. The bid form is setup so that Options 3 and 4 appear additive, however descriptions on page 327 of Volume 3 indicate that both options are to include Volumes 1B, 2B, 3, 4 and 5, and scope descriptions within each Option also appear to be based on each Option being a standalone price.

Options 3 is addititive to Option 2. Option 4 is additive to Option 3.

Offerors shall refer to Amendment 0011, which removes Volume 3 section D, Options, issued on 09/18/17 and replaces it with revised Volume 3 section D, Options, dated 10/16/17.

In Option 2 – 2.02, we are to include 10-year warranty in lieu of 20-years for the following specs 034500, 034900, 071326, 72700, 074213, 075323, 075556, 079200, 084000, 084100 and 084400. Option 3 is additive to Option 2 and does not increase the warranty for the listed specs back to 20-years. Option 4 – 4.08 which is additive to Option 3 we are to increase the warranty from 20-years to 30-years for the listed specs, but shouldn’t this be changed to increasing the warranty from 10-years to 30-years since we don’t include pricing for the 20-year warranty in any of the Option pricing?

No, Option 4 should not increase the warranty from 10-years to 30-years. Offerors shall refer to Amendment 0011, which removes Volume 3 section D, Options, issued on 09/18/17 and replaces it with revised Volume 3 section D, Options, dated 10/16/17.

In Option 3 – 3.01, it states Option 3 does not include scope indicated on drawings with XXX-ALT in the sheet title. Refer to Options 2 and 4 for XXX-ALT sheet relevance.

Since Option 3 is additive to Option 2 and in Option 2 – 2.01, we included the reduced scope of parking shown on L101-ALT-A, L102-ALT-A and C104-ALT-A, for Option 3 do we include the full parking lot shown on L101, L102 and C014. Is there any other items besides 3.02 that we need to include.

No, under Option 3 offerors shall not include the full parking lot specified under Option 2. Offerors shall refer to Amendment 0011, which removes Volume 3 section D, Options, issued on 09/18/17 and replaces it with revised Volume 3 section D, Options, dated 10/16/17.

Refer to Amendment 7 - Statement of Work Design Phase Services – Please confirm we are to include the costs for the Building Envelope Expert Consultant as described in section III.C.7.a in our Base Bid Design Phase Services (CLIN 0001) lump sum cost.

Yes, offerors shall include the Building Envelope Expert Consultant in CLIN 0001 for Design Phase Services.

Refer to Amendment 7 - Statement of Work Design Phase Services – III.C.7.b Building Envelop Mock Up

a. Please confirm we are to include costs for the full-scale façade mock up including shop drawings in the Base Design Phase Services (CLIN 0001).

b. Please confirm we are to include costs for contracting the testing agency for the full-scale façade mock up in the Base Design Phase Services (CLIN 0001).

c. Please provide a drawing showing extent of full-scale façade mock up, showing what materials are to be included and sizes so it can be priced.

a. Yes, costs for full-scale mock-up including shop drawings are to be included in the Base Design Phase Services (CLIN 0001)

b. Yes, costs for contracting the testing agency for the full-scale facade mock-up are to be included in the Base Design Phase Services (CLIN 0001)

c. Drawings showing the extent of the full-scale facade mock-up are not available at this time. Offerors shall assume that a full scale mock-up is defined as one full-scale model of GFRC-1 and adjacent CW-2 at a total size of approximately 27' high x 12' wide.

12 What divisional line item are we to include our bond and insurance cost?

Offerors shall refer to Amendment 0011, which removes the Proposal Form, dated September 14, 2017 and replaces it with the revised Proposal form, dated 10/16/17. The revised Proposal Form includes a section for offerors to propose bond and insurance.

Refer to Amendment 7 - Statement of Work Design Phase Services – III.C.7.b - Court Room Mock Up

a. Please confirm that the costs of the (3) proposed courtroom mock ups are to be included in the Base Design Phase Services (CLIN 0001).

b. Please also confirm that GSA will provide a location for these mock ups to be constructed.

a. Yes, the cost of the (3) proposed courtroom mock ups are to be included in the base design phase services.

b. GSA will not provide a location for the mock ups. The CMc is responsisble to provide a location for these mock ups.

It was stated at the pre-proposal meeting that, though this project has been approved, it has yet to be funded. Can we assume, for the purposes of our proposal, that when the project is eventually funded it will be fully funded (i.e. no incremental funding)?

The government anticipates that the project will be fully appropriated.

Has PP&L been scheduled yet to do the demolition of the existing overhead lines that they are responsible for, and if so, when are they scheduled to perform that work? If they are not is there anticipated date to start the discussions for this work?

The GSA has submitted the required service relocation application to PPL; the schedule for performing the work has not yet been deteremined. Contact has been established with the utility providers and conversations are on-going.

ES101 – In the northern parking lot, pointing to nothing are several arrows showing see note #4. Note #4 states that we are to remove service at residential. Is it just to the plots these arrows point to, or all plots?

Note #4 pointing to 634, 636, 638 and 640 Boyd Steet is void. So is scope of overhead electrical service demolition from PPL pole #5428 to #24104, and removal of poles #24092 and 24104.

TA-000 – AV Responsibility Matrix calls out AV Contractor. Is the AV Contractor to be part of the General Contractor or will this be purchased by the Owner as a separate contract? If by owner, has the AV Contractor been contracted yet, and if so, whom is the contractor?

AV equipment will be provided and installed by third party contractor not included in CMc scope of work. Offerors shall refer to Amendment 0011, which incorporates a Responsibility Matrix, dated 10/16/17, as Appendix A to, Volume 2B - HFC Construction Specifications.

The pile and pile cap details shown on Drawing S400 do not provide the size of the reinforcing steel associated with each of the 7 pile caps. Please provide the bar weight or an allowance for the rebar weight to be included.

Offerors shall refer to Amendment 0011, which removes S400, issued on 09/18/17 and replaces it with revised S400, dated 10/16/17. The revision includesa pile cap schedule that shows the anticipated reinforcing in the pile caps.

The 16” concrete wall shown on S101 has the associated section cut; which is detail 1 on Drawing S401. The size of the reinforcing steel associated with the retaining wall is not identified. Please provide the bar weight or an allowance for the rebar weight to be included.

Offerors shall refer to Amendment 0011, which removes S101 and S401, issued on 09/18/17 and replaces it with revised S101 and S401, dated 10/16/17. The revision includes additional detail on the reinforcing steel associated with the retaining wall.

There is a proposed grade beam shown on Drawing S101. There are no details as to the height and width of the grade beam. Also detail 1 on S401 shows the grade beam but does not show the size of the reinforcing steel associated with the grade beam. Please provide clarification or an allowance for estimating.

The grade beams shall be as follows: On gridline N.8, gridline 2, and gridline P.2 (between gridlines 6 and 8c only), the grade beams shall be 48" high x 48" wide. For all other grade beams, the beams shall be 36" deep x 48" wide.Offerors shall refer to Amendment 0011, which removes S101 and S401, issued on 09/18/17 and replaces it with revised S101 and S401, dated 10/16/17. The revision includes additional detail on the rheight and weight of the grade beam and the reinfircing steel associated with the grade beam.

Does the 28 day cure time referenced in specification section 033000-19 section 2.4 also apply to the polished concrete floor?

Polished concrete floor is not specificed in this project.

Please provide a responsibility matrix identifying the division of owner furnished and installed scope versus contractor furnished and installed scope. The drawings in regards to the AV scope have provide such a matrix however there are several other items for coordination, i.e. the demountable partitions are stated on the drawings as FFE but a specification has been provided for this work

Offerors shall refer to Amendment 0011, which incorporates a Responsibility Matrix, dated 10/16/17, as Appendix A to, Volume 2B - HFC Construction Specifications. The Responsibility Matrix identifies the division of owner furnished and installed scope versus contractor furnished and installed scope.

There are no appliances identified for the staff kitchens and break rooms. Are these to be FFE and not to be included, if they are to be provided please provide an allowance budget or an equipment schedule to be priced.

The appliances will be FF&E and shall not be included in the price proposal.

Due to the extent of time for the preconstruction and the overall duration of the project, it is felt that the project will need to address escalation as a cost factor.

Please provide the rate of escalation that should be carried for the project.

The government will not provide a rate of escalation that should be carried for the project. It is at the offerors discretion to utilize a rate of escation that is appropriate.

Please clarify how the alternates identified in the documents are to be priced. There are more alternates then option pricing categories. Additionally, can a clear alternate narrative be provided for each alternate to be priced?

There are no alternates under this solicitation; however, there are options as part of the requirement. Offerors shall refer to Amendment 0011, which removes Volume 3 section D, Options, issued on 09/18/17 and replaces it with revised Volume 3 section D, Options, dated 10/16/17.

Is the UPS an Optional System as the drawing states? If so what Option should this be priced with?

The UPS is not an option and is part of the project. The word "Optional" was referering to the "Optional Standby Systems" as defined by National Electric Code Article 702.

The Structural Steel drawings shows a reduction for Option 3 (which is assumed to be alternate A). Is the reduction only 25 tons of steel or is it per sheet and a total of 50 tons of steel?

Option 2 includes a 25 ton steel reduction from what is documented on S-109; Option 2 and Option 3 tonnage are the same. Option 4 includes the added cost for steel tonnage as documented on S-109.

The drawings show mobility lifts in association with the Judges Benches, however no specification has been provided for this scope. Are these to be included as part of the pricing or are these to be part of future FFE scope?

Pricing should include three (3) mobility lifts (1 for a District Courtroom, 1 for a Magistrate Courtroom and 1 for the Bankruptcy Courtroom). All other locations are to be provided with necessary power for future addition of lifts.

We are assuming that the finishes stated in the design finish schedule and in the specification, will follow the Courts Design Guide of 2007. Please provide any clarification to rooms that may not follow this standard.

Finishes should meet the US Courts Design Guide 2007 and the General Services Administration P100 Facilities Standards, "Baseline".

The Pre-Proposal Conference materials indicate that the bid guarantee should be in the amount of 20% of the proposed price. Bid Bond standard form 24 also has a section designating an amount not to exceed. Should bidders insert $3,000,000.00 in that space?

In accordance with Federal Acquisition Regular (FAR) 28.101-2(b), the bid guarantee amount shall be at least 20 percent of the bid price but shall not exceed $3 million. The amount of the big guarantee shall be calculated based on the offeror's proposed price, not to exceed $3 million.

31 Please confirm that builder’s risk insurance will not be provided by the Government.

It is confirmed that builder's risk insurance will not be provided by the government.

Refer to section 1C of the agreement. For each option the commencement of work is described as starting “within [x] amount of days after the contractor receives NTP for design phase services”. Does this mean that the option may be exercised 1 day after NTP, or as many as 400 days after NTP (option 4)? Can the government narrow this window so that the contractors and subcontractors can accurately understand the schedule and price accordingly?

Offerors shall refer to Amendment 0011, which removes the CMc 101 - The Agreement, dated 9/14/17 with the revised CMc 101 - The Agreement, dated 10/17/2017. Offerors shall also refer to Amendment 0011, which removes Volume 3 section D, Options, issued on 09/18/17 and replaces it with revised Volume 3 section D, Options, dated 10/16/17.Finally, offerors shall refer to Amendment 0011, which removes Volume 2A and 2B, Sections 012400, issued on 09/18/17 and replaces it with revised Volume 2A and 2B, Sections 012400, dated 10/16/17.The revised versions changes section I.C., Period of Performance.

We recommend requiring the contractors to break out escalation costs, or perhaps including an allowance for escalation.

The government will not provide a rate of escalation that should be carried for the project. It is at the offerors discretion to utilize a rate of escation that is appropriate.

Regarding Food Service equipment, the specifications indicate that the equipment will be supplied by a vendor contracted through the owner. Please confirm that it will be installed by vendor as well.

Offerors shall refer to Amendment 0011, which incorporates a Responsibility Matrix, dated 10/16/17, as Appendix A to, Volume 2B - HFC Construction Specifications. The Responsibility Matrix identifies that the Food Service equipment will be supplied and installed by a vendor contracted through the owner.

In the specifications it says to refer to Security Equipment as part of the electric scope.

Would it be included in the Electric package or separated out itself?

Offerors shall refer to Amendment 0011, which incorporates a Responsibility Matrix, dated 10/16/17, as Appendix A to, Volume 2B - HFC Construction Specifications.

The initial Concept Specifications have an in-depth layout of the Audio-Visual Communications package, but the Final Concept Specifications have not a single mention. However, the drawings indicate that it will be GC work. Please confirm that the drawings are correct in calling out the work for the AV package.

Offerors shall refer to Amendment 0011, which incorporates a Responsibility Matrix, dated 10/16/17, as Appendix A to, Volume 2B - HFC Construction Specifications. The Responsibility Matrix identify responsibility for the work for the AV package.

The specifications mention manufacturers for Isolated Ceilings and Floating Floors, but the drawings do not explicitly indicate which rooms are to have either of these systems.

Can you please identify:

a. Rooms where there are Isolated Ceiling Systems

b. Rooms where there are Floating Floor Systems

Isolated Ceilings and Floating Floor systems are implemented as a result of the USMS FIT room on L2. Refer to notes on A106 & A604, and room type descriptions in Volume 3 associated with 8. District Clerk - Open Office and 16. USMS - FIT Room.

Beginning on p. 101 of Vol. 3, doors, frames, finishes, and hardware are listed by room.

Does a schedule exist for entry, overhead, and security doors as well as coiling grilles? If so, could you please make it available?

A door schedule has yet to be developed at this point in time. Please use Vol. 3 Interior Space Types and look to tags indicated in the drawings for locations of these and other types of doors.

Should doorways shown in the demountable partitions—for example, Vol. 1B A105 Column 6, Row T7—be included in the door scope? The note states demountable partitions are part of FFE.

Offerors shall refer to Amendment 0011, which incorporates a Responsibility Matrix, dated 10/16/17, as Appendix A to, Volume 2B - HFC Construction Specifications. The Responsibility Matrix identifies responsibiliy for doorways in the demountable partitions.

40 Is the Signage package part of the GC scope?

Base building signage is to be provided by the CMc. Offerors shall refer Amendment 0011, which incorporates an added section in Volume 3 - C. Narratives and Reports: Signage.

Regarding the Flooring package, is there an Epoxy finish on any floor in the building?

The specs do not indicate anything. Please confirm either yes or no.

Yes, there is a Epoxy-Resin Terrazzo included. Offerors shall refer to Interior Material Index G005 or Vol. 3. TZ-1 is listed as a . Refer to FAF-1 thru FAF-5 for additional applied floor coatings.

The AESS Built Up Columns along the Curved Arch along column line Ra on drawing S105 (Levels 01 and 02) has no weight/dimension information on it, can you please make this available?

Offerors shall refer to S107 for dimension information for the AESS Built Up Columns along the Curved Arch along column line Ra on drawing S105 (Levels 01 and 02).

The structural steel per detail 10/A313 needed for the exterior GFRC Panels is not shown on the structural plans, please provide size and weights for these components.

The size and weight for the structural steel per detail 10/A313 needed for the exterior GFRC Panels shall be designed and engineered by the successful CMc offeror.

There is access flooring (AF-1) spec’d to be in the courtroom ‘well’. Can a better definition be given on the drawings to where the access flooring will be located in the courtrooms?

AF-1 is located from the spectator rail to the face of the Judge's bench in the long dimension and from both side walls in the short dimension of each courtroom.

Please provide a Responsibility Matrix if it is available indicating GFGI, GFCI and CFCI packages.

Offerors shall refer to Amendment 0011, which incorporates a Responsibility Matrix, dated 10/16/17, as Appendix A to, Volume 2B - HFC Construction Specifications. The Responsibility Matrix identifies indicating GFGI, GFCI and CFCI packages.

C104 – Confirm all work denoted as “By Others” is executed from our proposal. Utility relocations around site are noted as such.

Items noted as "By Others" is work associated Utility Relocations (Option 1: Site Preparation Package) or work anticipated in the future City Roundabout design, to be performed by others.

C105 – Entrance/Exit gates off Harris Street are shown but not called out on subsequent plans. Are they to be executed as part of our proposal? If so, will there be a spec?

Yes, entrance/exit gates off Harris Street are part of CMc Proposal; No specification is provided at this time.

There are no sections/details for on-site asphalt paving, concrete curbs or sidewalks.

Please provide if available.

Details associated with Option 1 are shown on C105. Additonal details have not been developed and will be provided at a future submission.

L-601/602 – At “Low to No” irrigation designations, what type of irrigation system is desired?

Drip Irrigation system is to be used at this area.

There is no planting schedule identifying species of plantings and trees. Please provide.

Offerors shall refer to Amendment 0011, which removes Volume 3:

Section C. Reports and Narratives, issued on 09/18/17 and replaces it with revised Volume 3: Section C. Reports and Narratives, dated 10/16/17. The revision includes a planting schedule.

51 What is the finish for the interior round column covers?

Offerors shall assume that the finish for the interior round column covers are GFRG with 4" base (use base material indicated in Vol. 3 Interior Space Types). See Vol. 2B Section 092713.

52 Are we to include HC lifts at judge’s entrance to each courtroom?

Offerors shall refer to the government response provided for question 28.

53 A202 – Please provide a detail for the light box behind glazing at P1 level.

Offerors shall assume that the detail for the light box behind glasing at P1 level is fully enclosed GWB space painted white to reflect light from ceiling mounted light fixture. See 21/A305.

54 Detail 20/A440 – Please confirm “Art with Architecture” is NIC

Art in Architecture is not a part of the CMc scope of work. Offerors shall refer to Amendment 0011, which incorporates a Responsibility Matrix, dated 10/16/17, as Appendix A to, Volume 2B - HFC Construction Specifications. The Responsibility Matrix identifies responsibility for art in architecture.

A600’s – RCP’s design currently in coordination. Refer to ‘Typical Space Diagrams in Volume 3 Lighting”

Not all ceiling information is shown and coordinated on the A600 series drawings at this time. Refer to Vol. 3 page 231 Lighting Systems for additional information related to typical room lighting strategies.

If rubble, foundations, unsuitable soils are encountered and determined to be removed and replaced, are we responsible?

Unsuitable materials in whatever form will need to be removed as determined by proofrolling the subgrade during construction. The extent of removal will be subject to the type of excavation (trench vs.

bulk) and the loading condition above the soils. Trench excavations will typically require 1 - 2 feet overexcavation whereas bulk excavation below the building or parking area may require greater overexcavation to meet loading conditions. Assume that 500 CY of unsuitable materials will be removed and replaced. Field determinations will be required where unsuitable materials are found

Top of spread footing elevations are provided, but notes and details require spread footings to bear directly on bedrock. If bedrock is deeper than indicated T.O.F/B.O.F, are we responsible to go deeper?

The elevations of the spread footings shall be adjusted as needed so they bear on the bedrock. The footing elevations shown on the plans are approximate based on the information obtained from the geotechnical borings and interpolation between the boring locations.

Variations in the bedrock elevation may require raising/lowering some footings. Assume that an additional 10% CY of concrete is required for deeper footings beyond elevations indicated on design documents.

Geotech report states 6” 2A Modular be placed beneath all slabs AND footings.

Structural plans do not indicate this. Please confirm if this is required under footings.

Offerors shall assume that all footings shall be placed on 6" 2A Modified aggregate for a consistent and uniform bearing condition.

Excavations for footings shall be to competent rock and the rock shall be excavated as necessary to provide a flat bearing surface the specified 6" of aggregate.

ES102/103/501 – Electrical site plans: Please confirm the scope of work we are responsible for and what work the utility company will perform.

The Contractor will trench & backfill, install the transformer foundations, install all duct to feed transformers, and install it’s own customer-owned switchgear. PPL will place transformers on foundations, pull in all conductors, and install meter. See also response to item 4. ES103 is hereby void, follow ES102.

TS102/501 – Telecom plans and details: Please confirm we are responsible for ductbanks and structures only, and that cabling will be done by others.

CMc is responsible for providing ductbanks and structures only.

Cabling will be done by others.

Please confirm that Option 1 Pricing is to include only the sitework indicated in Volume 1A: Erosion Control, Site Demo, Utilities.

Yes, option 1 pricing to include Volume 1A.

62 Can you provide the weight given to a PLA?

No, the government will not provide the weight to the Project Labor Agreement (PLA) technical evaluation factor.

Has a preliminary design schedule been developed, and if so, can it be provided?

This schedule should provide anticipated NTP date along with any major design deliverables.

Preliminary design schedule will be issued on 10/18/17 via UPS.

Schedule includes early dates, and does not include all activities.

Offerors shall refer to CMc contractual dates to be coordinated.

Section III.C.7.B of the CMc Statement of Work calls for a full-scale mock-up of the proposed façade including GFRC details to be produced during the design phase. The section also requires laboratory testing to be performed based on the specifications. Section 08 40 00.1.7.H requires both a visual mock-up and a performance mock-up. Please confirm that both mockups will be done as part of the pre-construction effort during the design phase.

Design-phase mockup will be a full-scale module of GFRC-1 and adjacent CW-2 systems. The total size will be approximately 12'-0" wide x 27'-0" high. This mockup will be for both visual (VMU) and performance (PMU) purposes.

Section 08 44 00 indicates that the extent and number of mock-ups to be confirmed by Architect. Section 08 40 00 indicates that the Contractor shall perform mock-up construction and testing for each specific exterior wall system utilized on the project. For the purposes of pricing the Design Phase Services, please confirm that only the Visual and Performance mockups as specified in Section 08 40 00 (Paragraph 1.7.H) should be included. It is assumed that any additional mock-ups would be added as part of the Construction Phase Services.

See response to question 64 for description of Design Phase mockup. Mock-ups indicated in Section 08 40 00 are part of Construction Phase Services; refer to Question 66 for additional information related to Construction Phase Mock-up scope.

In accordance with Section 08 44 00, please confirm the extent and number of mock-ups to be completed for the exterior wall systems.

The Visual Mock-up (VMU) will include composite mock-ups of portions of systems SCR-1, CW-1A, CW-1B at an approximate size of 15'-0" wide x 20'-0" high x 6'-0" deep and MP-1A, GFRC-2 with soffit return, and WN-2 at an approximate size of 10'-0" x 20'-0" x 6'- 0" deep. The Performance Mock-up (PMU) will be a single composite mock-up, approximately 2-stories high, and consist of a typical bay of GFRC-1, CW-2, CW-3, and SCR-1, CW-1A, CW-1B;

approximate size of PMU will be 30'-0" wide x 27'-0" high.

Please confirm that the CMc is responsible for providing the approved testing agency for the mock-up (in addition to the Owner’s Testing Agency).

CMc is responsible for providing the approved testing agency for the PMU; testing agency will be recommended by the CMc and approved by the GSA.

Please confirm that the required visual and performance mock-ups can be constructed off-site.

Section 014000.1.1.E indicates that mock-ups are to be constructed onsite unless otherwise directed by GSA; Section 08 40 00.3.5.C indicates that mock-up construction and testing will be done off-site. Section 03 45 00.1.6.F and Section 03 49 00.1.6.D indicate that mock-ups will be fabricated at a location designated by the GSA.

The PMU will be done at the testing facility and thus off-site.

The VMU may be located on-site if schedule and space permits.

Can the slides presented by the Design Team at the pre-bid meeting be provided? It seems that only the GSA slides were included in Amendment 008.

No. Offerors shall refer to the Final Concept, issued on 09/18/2017, for additional information.

Please confirm that the round-about and all associated work at the intersection of Reily Street and 7th Street will be completed by the City of Harrisburg. Other than utility relocations as specified, It is assumed that the work of the CMc would end at the curb/public sidewalk.

Yes. All work associated with the traffic circle at the intersection of 7th and Reilly Streets will be performed by others, with the exception of utility relocations.

Referencing Section 084000.1.8.C, the documents require a warranty period of 20 years for the exterior envelope system. Because of the various trades working on the exterior envelope and the maintenance that will be required to be completed by the GSA, this warranty may not be achievable or may add considerable cost to the project. We would recommend including the special warranties as noted in the specifications for the individual components of the exterior envelope system, but would recommend reducing or eliminating the warranty of the exterior envelope system. If we are required to provide the 20-year warranty as stated in the documents, please provide information about the GSA exterior envelope maintenance program.

Provide price per documents. Information on GSA exterior envelopme maintenance program is not available at this time.

Please provide the current BIM model in Navisworks (BIM model in Amendment 3 was in Navisworks).

Offerors shall refer to Amendment 0011, which includes information on the UPS shipment of the Navisworks format.

Please confirm all Options identified in the documents but not listed on the Proposal Form, are to be addressed at a later date (during design phase).

No. A price for all options is required at the submission of Phase II proposals.

74 INTENTIONALLY LEFT BLANK

Page 113 of the Solicitation indicates that CMc deliverables are due within 14 days of receipt of the design deliverable. Given the size and complexity of the project, and the anticipated level of detail that will be required, please consider extending the period for the CMc to produce their deliverables. On previous projects of similar size and scale, we have seen durations of 4-6 weeks depending on level of design.

The solicitation shall remain unchanged. Each written deliverable from the CMc is due to the Contracting Officer within fourteen (14) days from the CMc’s receipt of the A/E’s design-related submission.

Please confirm that the Design Contingency is being carried by the Government and that we should not include costs for design development and revisions in the CMc's

ECW.

Design contingencies are not carried seperately by the government.

It is at the offeror's discretion to carry design contingencies in their

ECW.

Specification section 280000 and the Security Systems narrative reference security systems drawings, however there are no security systems drawings in the drawing set. Please provide security systems drawings.

Security drawings are currently in development and will be provided at a later submission. Please look to referenced specification and narrative for scope information at this time.

Reference the proposal form issued in amendment 7. On the last page of the proposal form, there is a "TOTAL CONTRACT PRICE" which is to be the sum of CLINS0001-0005. We assume that CLINs 0002-0005 should not be full project values. Per the pre-bid meeting held on 9/22/17, it appears that the intention is for Option 3 to be considered "the base bid", incorporating the reduction of steel by 25 tons per the Option Narrative. Please clarify:

A.) Is CLIN0003 - Option 2 - to be a deductive item from Option 3?

B.) Is CLIN0005 - Option 4 to be an add to Option 3?

CLINs 0002, 0004 and 0005 should not be full project values. The price for the building shall only be included in CLIN 0003, Option 2.

Offerors shall refer to Amendment 0011 for a clarification on options.

Subcontract award data reported by the Contractor and subcontractors shall be limited to awards made to their immediate next-tier subcontractors.

Subcontract award data reported by the contractor and subcontractors shall be limited to awards made to their immediate next-tier subcontractors.

Where will the various design meetings listed in the Statement of Work for Design Phase Services be held during the design phase? The SOW references jobsite offices but the Solicitation as a whole does not specify if jobsite offices will be established in Harrisburg for the design team and/or GSA.

Offerors shall refer to Amendment 0010, which includes the CMa meeting matrix at the end of the SOW.

The Statement of Work for Design Phase Services requires the CMc to construct three (3) courtroom mock ups for massing purposes. Does GSA have a location where these shall be built during design phase services or does the CMc need to provide a warehouse or other location for the mock ups to be built?

It is hereby clarified that the CMc shall provide a warehouse or other location for the mock ups to be built.

Is the CMc responsible for providing office space/trailers for the GSA at jobsite during construction?

CMc is responsible for GSA/CMa/AE trailers as specified in Volume

The Statement of Work for Design Phase Services references the Statement of Work for the CMa and states that it has been provided. Please provide this document for review by CMc.

Offerors shall refer to Amendment 0010, which includes the CMa

SOW.

Reference is made to the weighting of components between the Technical Proposal and Price Proposal and specifically between the Management Approach and the Small Business Plan and Project Labor Agreement components. Will GSA provide the scoring system that will be used to evaluate these components?

No, the government will not release the plan for source selection.

85 Confirm Option 1 - Site Preparation and Utility Relocation is Firm Fixed Price. Offerors shall refer to the government response to Question #2.

The overall durations and subsequent construction durations for the Construction Options are inconsistent between the Agreement (Section I.C) and the Description of Options (Specifications Volume 3, Pg 327). Please clarify the overall durations for performance of the Construction Options.

Offerors shall refer to Amendment 0011, which removes the CMc 101 - The Agreement, dated 9/14/17 with the revised CMc 101 - The Agreement, dated 10/17/2017. Offerors shall also refer to Amendment 0011, which removes Volume 3 section D, Options, issued on 09/18/17 and replaces it with revised Volume 3 section D, Options, dated 10/16/17.Finally, offerors shall refer to Amendment 0011, which removes Volume 2A and 2B, Sections 012400, issued on 09/18/17 and replaces it with revisedVolume 2A and 2B, Sections 012400, dated 10/16/17.The revised versions changes section I.C., Period of Performance.

Glazing type GLE-2 is shown within curtainwall CW-3 on the South tower facade on A201. Glazing type GLE-1 is shown withing curtianwall CW-3 on the North tower facade on A203. Please confirm this is correct. If not, please confirm GLE-1 should be used at both of these locations.

Any reference to GLE-1 shall be removed and replaced with GLE-2 for CW-3 for both the south and north facades.

IMP-1 is shown between overhead doors on A102. MP-1B is shown between the same overhead doors on 3/A303. Please confirm MP-1B is to be used at this location.

Any reference to IMP-1 between overhead doors on A102 shall be removed and replaced with MP-1B.

Please provide the locations for motorized and manual roller window shades as no locations are indicated in the drawings per the interior material index, drawing G005.

Offerors shall refer to Amendment 0011, which removes Volume 3:

Section C. Reports and Narratives, issued on 09/18/17 and replaces it with revised Volume 3: Section C. Reports and Narratives, dated 10/16/17. The revision includes the locations for motorized and manual roller window shades.

Please provide the locations for interior wall system IWS-1 as no locations are indicated in the drawings per G005.

IWS-1 is demountable partitons located at tenant spaces as indicated in Vol 1B on G005. Refer to graphic key at upper right corner of sheets where demountable partitons are indicated in plan.

Section 3.3 of the AV narrative states that "some equipment can be purchased for initial occupancy, while other equipment purchases can be deferred". Please clarify what AV equipment needs to be provided

Offerors shall refer to Amendment 0011, which incorporates a Responsibility Matrix, dated 10/16/17, as Appendix A to, Volume 2B - HFC Construction Specifications. The Responsibility Matrix clarifies the AV equipment that needs to be provided.

The AV Scope of Responsibilities Matrix in the AV narrative states that not all items listed in the matrix may be required at this time. Please clarify what items in the matrix do and do not need to be provided

Offerors shall refer to Amendment 0011, which incorporates a Responsibility Matrix, dated 10/16/17, as Appendix A to, Volume 2B - HFC Construction Specifications. The Responsibility Matrix clarifies the equipment that does not need to be provided.

The Telecommunications narrative does not include any requirements for structured cabling and there is no specification section for structured cabling. Please clarify if structured cabling is to be provided in this bid. If so, please provide a narrative description of the requirements and specifications.

Structured cabling is not a requirement under this project.

Specification 284619 Part 2 says to "refer to individual specifications sections for acceptable manufacturers and products for all associated detention work". Please provide individual specification section for detention monitoring and control equipment.

Specification section has not yet been developed.

No specifications have been issued for access control, intrustion detection, video surveillance or other security systems. Please confirm that only security rough in is to be provided (to include conduit, backboxes and power conenctions).

Offerors shall refer to Amendment 0011, which incorporates a Responsibility Matrix, dated 10/16/17, as Appendix A to, Volume 2B - HFC Construction Specifications. The Responsibility Matrix clarifies the CMc's responsibilities in terms of access control, intrusion detection, video surveillance, or other security systems.

The fuel oil flow diagram on H505 locates the fuel oil storage tank on the 1st Floor of the building, and says to “refer to architectural drawings for location of fuel oil storage tank.” However, the architectural drawings do not show the tank location. Please confirm that the fuel oil storage tank, fuel oil pump, fill box, and vent lines are to be installed in the Fuel Storage room in the northeast corner of Level GF as shown on Life Safety plan LS001.

It is confirmed that the fuel oil storage tank, fuel oil pump, fill box, and vent lines are to be installed in the Fuel Storage room in the northeast corner of Level GF as shown on Life Safety plan LS001.

The fire department connection is shown on Level 1 on riser diagram FP-030, but the exact location is not shown on the fire protection plan drawings. Level GF East plan FP-102 refers to SU-100 for the “FDC on site.” SU-100 calls out a fire department connection on the north side of the building, but it appears to fall outside of the building…