Southwest_Region_BECOS_IDIQ_PWS_Attachment_3_-_Deliverable_Review_Process_Draft_18_Sept_19_v1.0.docx
DOCX document 44 KB Posted
- Solicitation number
- FA8903-20-R-0002
About this file
This document outlines a draft request for proposal for environmental construction optimization services at 40 Base Realignment and Closure installations. The Air Force seeks six indefinite delivery/indefinite quantity contracts for environmental remediation and construction work at the installations. The contracts would be awarded on a single-award basis for each of five continental U.S. regions and Galena, Alaska. Work would include maintaining remedies, implementing optimizations, and advancing sites to completion. The period of performance is anticipated as 10 years from July 2020 to July 2030, with initial task orders issued from July 2020 to July 2025 and a potential three-year extension. Questions on the draft RFP are due by November 4, 2019.
SW IDIQ ATTCH 3
View the file
Other files
Show 40 more
Latest 50 of 120 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Southwest Region Enclosure 3
Deliverable Review Process Air Force Contractor Regulators Task: Prepare working copy document.
Timeframe: Dependent on task Scope: Dependent on task Task: Review working copy document.
Timeframe: 30 calendar days (max) Scope: Comments will focus on regulatory, factual, technical, and legal issues and should not conflict with the terms and conditions of the contract (e.g., directing the contractor on approach).
Tasks: Incorporate review comments. Prepare submittal letter.
Timeframe: Dependent on task Scope: Evaluate and incorporate all regulatory, factual, technical, and legal Air Force comments that do not conflict with the terms and conditions of the contract.
Task: Review draft document and sign submittal letter if document is acceptable. Return for further revisions if required.
Timeframe: 7 calendar days (max) Scope: Review and sign submittal letter. Provide letter to Contractor.
Task: Obtain regulatory review of draft document.
Timeframe: TBD Scope: Distribute submittal letter and document to regulators. Provide copies to the Air Force.
Task: Provide regulatory review.
Timeframe: FFA/DSMOA/Circumstantial Scope: Provide regulatory review of submitted document.
Tasks: Resolve comments and revise document. Prepare submittal letter.
Timeframe: TBD Scope: Provide timely evaluation and resolution of regulatory comments with a goal of meeting predetermined objectives.
Task: Submit final document.
Timeframe: TBD Scope: Submit final document for regulatory acceptance/concurrence.
Task: Review final document and sign submittal letter if document is acceptable. Return for further revisions if required.
Timeframe: 7 calendar days (max) Scope: Review and sign submittal letter. Provide letter to Contractor.
Task: Accept final document.
Timeframe: FFA/DSMOA/Circumstantial Scope: Accept final document and provide written notice.
Note: This is a generic document review process for this contract. Actual review times will be based on the Federal Facility Agreement (FFA) where applicable or the Joint Execution Plan (JEP) and associated schedules developed under the Defense State Memorandum of Agreement (DSMOA). Agencies reviewing the document may make specific requests based on complexity of the deliverable or work load of their technical review team that impact review timelines. Depending on the document, there may or may not be a draft version or there may be multiple draft versions.