This document contains a pre-solicitation notice and draft performance work statement for the BRAC Environmental Construction Optimization Services (BECOS) contract opportunity. The Air Force is seeking six regional contractors to perform environmental remediation and construction services at 40 BRAC installations over a 10-year period of performance. The work will involve CERCLA and non-CERCLA sites requiring long-term monitoring, groundwater treatment, landfill capping, and five-year reviews. Contractors will implement optimization strategies to enhance remedial progress and advance sites to completion. The pre-solicitation provides notice of the agency's intent to issue a request for proposal in November 2019, with questions due by November 4th. The final solicitation is expected to result in six single-award IDIQ contracts for fixed-price and cost-reimbursable work.

NC TO2 PWS

View the file

Other files

File Type Posted
RFI__5_BECOS.pdf PDF
RFI_5_BECOS_Response_Matrix_Attch_1.xlsx XLSX spreadsheet
Northeast_Region_BECOS_IDIQ_PWS_Attachment_4.docx DOCX document
Northeast_Region_BECOS_IDIQ_PWS_Attachment_3.docx DOCX document
Northeast_Region_BECOS_IDIQ_PWS.docx DOCX document
Northeast_Region_BECOS_IDIQ_PWS_Attachment_1.xlsx XLSX spreadsheet
Northeast_Region_BECOS_IDIQ_PWS_Attachment_2.docx DOCX document
Midwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req Wurtsmith Dft 24 SEP 19 v3.0.docx DOCX document
Midwest_Region_BECOS_IDIQ_PWS_Attachment_3_-_Deliverable_Review_Process_Draft_18_Sept_19_v1.0.docx DOCX document
TO2 PWS Attch 2 Central South - Base Specific Req Kelly Dft 20 SEP 19 v3.0.docx DOCX document
Midwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req Gentile Dft 24 SEP 19 v3.0.docx DOCX document
TO2 PWS Attch 2 Central South - Base Specific Req Myrtle Beach Dft 20 SEP 19 v3.0.docx DOCX document
NORCAL_Region_BECOS_IDIQ_PWS_Draft_18_SEP_19_v4.0.docx DOCX document
DRAFT_10242019_Central_South_IDIQ_TO1_TO2_CLIN_Structure_and_Price_Model_v2.xlsx XLSX spreadsheet
BECOS_IDIQ_DD1423_CDRLS_EXHIBIT_C002_(MGMT)_27_Sep_19.zip ZIP file
NorCal Region BECOS TO 2 PWS_Draft_25 SEP 19 v3.0.docx DOCX document
NorCal Region BECOS TO 2 PWS Attch 2 - Base Specific Req McClellan Dft 19 SEP 19 v3.0.docx DOCX document
Southwest_Region_BECOS_IDIQ_QASP_dft_24_Oct_19_v1.0.docx DOCX document
Northeast_Region_BECOS_IDIQ_QASP_dft_24_Oct_19_v1.0.docx DOCX document
20191024_Section_M_Draft_RFP.pdf PDF
IDIQ_PWS__Attch_4_Central_South_-_Performance_Objectives_Defined_Dft_18_Sept_19_v1.0.docx DOCX document
Galena_Alaska_Region_BECOS_IDIQ_PWS_Attachment_1_-_Base_Site_List_Draft_18_Sept_2019_v1.0.xlsx XLSX spreadsheet
Southwest_Region_BECOS_IDIQ_PWS_Attachment_1_-_Base_Site_List_Draft_18_Sept_2019_v1.0.xlsx XLSX spreadsheet
TO2 PWS Attch 2 Central South - Base Specific Req England Dft 20 SEP 19 v3.0.docx DOCX document
Galena_-_Alaska_Region_BECOS_IDIQ_PWS_Draft_18_SEP_Dft_19_v4.0.docx DOCX document
Midwest_Region_BECOS_IDIQ_PWS_Attachment_4_-_Performance_Objectives_Defined_Draft_18_Sept_19_v1.0.docx DOCX document
Central_South_Region_BECOS_IDIQ_QASP_dft_24_Oct_19_v1.0.docx DOCX document
Northeast Region BECOS TO 2 PWS_Draft_25 SEP 19 v3.0.docx DOCX document
Midwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req O'Hare Dft 24 SEP 19 v3.0.docx DOCX document
BECOS_TO_1_DD1423_CDRLS_EXHIBIT_B006-B007-B008_(ADMN)_17_Oct_19.zip ZIP file
IDIQ_DD1423_CDRLS_Central_South_EXH_C002_(MGMT)_Dft_27_Sep_19.zip ZIP file
Southwest_Region_BECOS_IDIQ_PWS_Draft_18_SEP_19_v4.0.docx DOCX document
IDIQ_PWS__Attch_2__Central_South_-_Acronyms_and_Definitions_Dft_18_Sept_19_v1.0.docx DOCX document
Midwest Region BECOS TO 2 PWS_Draft_25 SEP 19 v3.0.docx DOCX document
Midwest Region BECOS TO 2 PWS Attachment 1 Dft Site List 25 SEP 19 v2.0.xlsx XLSX spreadsheet
Midwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req KI Sawyer Dft 24 SEP 19 v3.0.docx DOCX document
Midwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req Richards Gebaur Dft 24 SEP 19 v3.0.docx DOCX document
TO2 PWS Attch 2 Central South - Base Specific Req Eaker Dft 20 SEP 19 v3.0.docx DOCX document
Northeast Region BECOS TO 2 PWS Attachment 1 - Site List Dft 25 SEP 19 v2.0.xlsx XLSX spreadsheet
TO2 PWS Attch 2 Central South - Base Specific Req Reese Dft 18 SEP 19 v2.0.docx DOCX document
Draft_RFP_BECOS_Section_E_Clauses.pdf PDF
Galena_-_Alaska_Region_BECOS_IDIQ_PWS_Attachment_3_-_Deliverable_Review_Process_Draft_18_Sept_19_v1.0.docx DOCX document
NORCAL_Region_BECOS_IDIQ_PWS_Attachment_4_-_Performance_Objectives_Defined_Draft_18_Sept_19_v1.0.docx DOCX document
Attachment_6_Fully_Burdened_Labor_Table_Compensation_Plan.xlsx XLSX spreadsheet
Midwest Region BECOS TO 2 PWS Attch 2 - Base Specific Req Rickenbacker Dft 24 SEP 19 v3.0.docx DOCX document
BECOS_TO_2_DD1423_CDRLS_EXHIBIT_B006-B007-B008_(ADMN)_03_Oct_19.zip ZIP file
Southwest_Region_BECOS_TO_1_PWS_Draft_17_OCT_19_v3.0.docx DOCX document
BECOS_IDIQ_DD1423_CDRLS_EXHIBIT_A016_(DRPR)_27_Sep_19.zip ZIP file
Northeast Region BECOS TO 2 PWS Attch 2 - Base Specific Req Dft Griffiss 24 SEP 19 v2.0.docx DOCX document
TO1_PWS_Central_South_Dft_17_OCT_19_v3.0.docx DOCX document
Show 40 more

Latest 50 of 120 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4890-06-R-9999

Attachment 1

APRIL XX, 2009

- final –

BECOS TO 2

ATTACHMENT 2

19 September 2019

1.1 Scope

The former Castle AFB is listed on the National Priorities List (NPL) and has a Federal Facility Agreement (FFA) in place. A Preliminary Closeout Report was prepared by the United States Environmental Protection Agency (USEPA) in 2006. Records of Decision (RODs) have been signed for all Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA) sites included in this task order and Last Remedy in Place (LRIP) has been achieved for the base.

The 18 sites included in this task order are being addressed following the CERCLA process or state corrective action program (non-CERCLA). There are two CERCLA sites in remedial action-operation (RA-O) and all CERCLA sites require IC monitoring and Five Year Review. Groundwater pump and treat systems are currently operating at these two of the sites (OT029 and OT030). The Operable Unit (OU)-1 Basewide Phase 3 groundwater treatment plant is currently operating at OT029 and the OU-2 groundwater treatment plant (Main Base Plant) is currently operating at OT030. Groundwater contamination associated with former Air Force activities has migrated beyond the former base property boundaries. Seven of the CERCLA sites are associated with three capped landfills/sites with ongoing Long-term Management. One CERCLA site has ICs and requires Five-Year Review only. Eight petroleum-contaminated sites have ICs and require non-CERCLA Five Year Review only.

In addition to the requirements presented in this PWS, this scope includes the following:

· Monitoring for 1,2,3-TCP.

· Replacement of wells that are dry due to lowering groundwater table, as needed.

Contractors are not responsible for the following:

· No additional base-specific exclusions.

1.3 Applicable Documents

Key Documents

Entry No.
Document Title
Location
Date Issued
1
FFA
AR 1007
July 1, 1989
2
Comprehensive Basewide (CB) ROD - Part 1 (Groundwater)
AR 1586
January 31, 1997
3
CB ROD - Part 2
AR 2747
July 31, 2006
4
Source Control Operable Unit (SCOU) ROD - Part 1
AR 2246
September 1, 2002
5
SCOU ROD - Part 2
AR 2244
May 1, 2003
6
Revised SCOU ROD - Part 3
AR 2736
September 16, 2005

1.4 Work Ramp-Up and Transition

Transition of Work

Contract No.
Project Name
Field Support

Complete Reporting Complete

FA8903-16-F-0018
Castle/Mather/Norton PBR Contract
9/30/2021
9/30/2021

1.5 Remedial System Components

· See Attachment 1 regarding remedial system components.

2.6.1 Meeting/Teleconference Support

· BRAC Cleanup Team (BCT) meetings are conducted annually at the former McClellan AFB (or comparable mutually agreed location for future meetings). Periodic technical meetings are conducted as needed in person or by teleconference.

2.6.2 Public Meetings and Hearings

· The Restoration Advisory Board has been adjourned and no other public meetings are currently scheduled. The contractor shall support public meeting requirements as necessary in association with contractor’s implementation plans

2.6.5 Site Access: Permits, Easements, and Work Site Access

· All existing off-base easements extend beyond this task order POP.

2.9 Contractor Documentation

· No base-specific requirements.

3.4 Computer Aided Design Drawing (CADD) and Geographic Information Systems (GIS) Updates

· No base-specific requirements.

6.14 Land Use Controls (LUC)

· The contractor shall conduct annual inspections and reviews to confirm compliance with all CERCLA and non-CERCLA environmental restrictions associated with the sites. Where possible, the contractor shall obtain and provide copies to the Air Force of annual reporting required by state covenants for applicable sites by respective property owners. An annual inspection report shall be provided or otherwise included in site reports by the contractor to confirm implementation of environmental restrictions.

· The contractor shall provide supporting information and technical support to the Air Force for property owner requests to remove restrictive covenants.

6.15 Five-Year Reviews

· The current PBR contractor will complete the Five-Year Review in March 2019. The next Five-Year Review is due in March 2024.