QA_LOG_11_OCT_2019.xlsx
XLSX spreadsheet 41 KB Posted
- Attached to
- WPAFB 2020-2025 Multiple Award Construction Contract Federal contract opportunity
- Solicitation number
- FA860119RA043
About this file
This document provides details regarding a solicitation for a Multiple Award Construction Contract (MACC) to be awarded by the Department of the Air Force Materiel Command Lifecycle Management Center located at Wright Patterson Air Force Base. Up to twelve contractors will be selected to form a pool eligible to compete for individual task orders ranging from $1 million to $10 million for construction and facilities maintenance projects at Wright Patterson Air Force Base over a five-year period. Both design-build and design-bid-build project types are included. An evaluation involving a sample project will be used to select awardees. Awardees must have a bona fide place of business within Small Business Region V. Both 8(a) and small business set-asides are included.
View the file
Other files for this federal contract opportunity
Show all 44
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Section J, Attachment 10 Q&A LOG, Solicitation: FA8601-19-R-A043 | ||||||||
| Should there be any discrepancy and/or inconsistency between what is written here and what is in the Final FOPR , the Final FOPR shall take precedence. | ||||||||
| Tracking Number | Document | Provision | Subject | Question | Answer/Comment | Date of Receipt | Date of Posting | Revision |
| 0001 | Solicitation | N/A | Liquidated Damages | Please provide the amount of liquidated damages per day for the sample project. | There are no liquidated damages for the sample project. The sample project is not funded. The sample project will be utilized to evaluate Offerors for award onto the MACC contract. The Government reserves the right to award the sample project if funding becomes available. | 23-Sep-19 | 1-Oct-19 | |
| 0002 | Attachment 08 | N/A | Sample Project Plans | I want to double check that the correct plans are posted for the 2020-2025 Multiple Award Construction Contract # FA860119RA043. Just a little confused on some of the information posted. Is there two different soliciattion numbers? In the Amendment 1 the plans have a solicitation number of FA8601-15-D-0007, are those correct? If you can please let me know. | The amendment drawings for the sample project are correct. |
The solicitation # you’re seeing is from the 100% design effort the government purchased and has provided to assist potential MACC awardees in proposing towards the sample project.
As mentioned in the summary of package changes 19 Sept 2019, the attachment file is provided to allow for 34x22 printing of the design drawings, which was found to be not possible after posting. These drawings are correct, and the attachment in the amendment contains pages 19-94 from the first package titled: Atch_08_Sample_Project_18_September_2019_1-250.pdf.
| 23-Sep-19 | 1-Oct-19 | ||||
| 0003 | Solicitation | N/A | General | How many task orders do you anticipate being solicited annually under this MACC? | The current MACC program at WPAFB received an average of 13 solicitations for projects annually. The current MACC was established to cover projects from $1M-$5M. |
The new MACC is expanding that intended range from $1M - $10M and at the time of the issuance of this solicitation, the Government is anticipating the amount and number of MACC task orders to grow over the next five years.
| 24-Sep-19 | 1-Oct-19 | ||||||
| 0004 | Solicitation | N/A | General | What is the minimum size for a task order under the MACC? | In accordance with the clause 52.216-19 Ordering Limitations in the solicitation. The minimum order that will be placed under the MACC will be $2,500. This is to cover the guaranteed minimum for the establishment of the contract. The Government intends to utilize the MACC for requirements from $1 Million to $10 Million. However, the Government retains the right to issue solicitations to MACC awardees for requirements under $1 Million when the Government determines the use of the MACC to be in its best interest. | 24-Sep-19 | 1-Oct-19 |
| 0005 | Attachment 01, Section L | Table 1, Volume I: Executive Summary and Contract Documentation Page Limitation | Proposal Organization and Page Limits | Table 1: Proposal Organization and Page Limits shows that Volume I: Executive Summary and Contract Documentation is limited to five pages; however, there is more than five pages worth of information required in Volume I. We respectfully request that the government remove all Contract Documentation (3.2, 3.2.1, 3.2.2, 3.2.3, 3.2.4, 3.2.5, 2.3.6 and 3.2.7) from the page limitations. | Agreed. Table 1 updated to reflect "5 page maximum for Executive Summary. No Page Limitation for Contract Documentation requested in 3.2 and its subparagraphs below". | 24-Sep-19 | 1-Oct-19 |
| 0006 | Attachment 01, Section L | Table 1 and Paragraph 4.2 | Proposal Organization and Page Limits and Organization | Table 1: Proposal Organization and Page Limits shows that Volume II, Technical SubFactor 1: Management Approach (Work Plan) is limited to 35 pages; however, paragraph 4.2 Organization (page 10 of Section L) states that the entire Technical Volume is limited to 35 pages. Can you please clarify the page limits for each SubFactor in Volume II? | Agreed. Updated Paragraph 4.2 to reflect what is requested in Table 1. | 24-Sep-19 | 1-Oct-19 |
| 0007 | Attachment 01, Section L | Table 1 and Paragraph 4.2 | Proposal Organization and Page Limits and Organization | Table 1: Proposal Organization and Page Limits shows that Volume II, Technical SubFactor 2: Prior Experience is limited to 10 pages. Are these 10 pages included in the 35-page limit for Volume II, mentioned in paragraph 4.2 Organization (page 10 of Section L)? | Agreed. Updated Paragraph 4.2 to reflect what is requested in Table 1. 10 pages are not included in the 35 page limit. Please note the update. | 24-Sep-19 | 1-Oct-19 |
| 0008 | Attachment 01, Section L | Table 1 | Proposal Organization and Page Limits | Table 1: Proposal Organization and Page Limits states we need to submit “1 unsanitized” and “1 sanitized” version of Volume II, Technical SubFactor 1: Management Approach (Work Plan); however, under “Paper Submission” it only shows “1”. Since all other SubFactors only need “1 unsanitized” copy, is it acceptable to include one complete “unsanitized” Volume II – Technical (including all SubFactors) and then one separate “sanitized” copy of SubFactor 1, only? | Yes, that is acceptable. Updated Table 1 to reflect that 2 paper submissions are required for Volume II, Technical Subfactor 1: Management Approach (Work Plan): 1 sanitized and 1 unsanitized version. | 24-Sep-19 | 1-Oct-19 |
| 0009 | Attachment 01, Section L | 4.2.3.3 | SubFactor 3: Technical Execution of Sample Project | Section L, Paragraph 4.2.3.3 SubFactor 3: Technical Execution of Sample Project we need to provide, “A Schedule Plan that includes key project milestones, a phasing plan, crew assembly and work schedule, and a safety plan.” In reference to the Safety Plan, are you requesting a Safety Plan in this section in addition to the Schedule? If so, can you provide more details? | Yes. We want ALL of these things. |
More guidance on Safety Plan: Reference Attachment 03, Statement of Work, Paragraph 14.2, "all work shall comply with… USACE Manual EM3858-1-1" Appendix E: Link to EM 385-1-1 https://www.usace.army.mil/Safety-and-Occupational-Health/Safety-and-Health-Requirements-Manual/ Appendix A-1 of EM 385-1-1 is titled “Minimum Basic Outline for Accident Prevention Plans”
| 24-Sep-19 | 1-Oct-19 | |||
| 0010 | Attachment 08 | N/A | Sample Project Plans | Note 15 on drawing H-100 calls for treatment of ALL windows and door frame caulking as asbestos (unless testing proves it to be not asbestos). The plan shows the entire building while the sample project is concentrated on Areas A and B only. Shall we work on the entire building to remove and replace caulking for the windows and door frames or within work areas A & B exclusively? |
- Can you please provide your intentions for this project.
Doors are only to be abated in the New Work Area, as defined in Sheets A-101 and A-102. Windows there is a requirement to abate all in the New Work Area as defined on sheets A-101 and A-102 and a provide a bid option to abate at windows throughout. See sheet A-601 for requirement and definition of new work areas and for base bid and option.
| The sample project is not funded. The sample project will be utilized to evaluate Offerors for award onto the MACC contract. The Government reserves the right to award the Sample project if funding becomes available | 25-Sep-19 | 1-Oct-19 | ||||
| 0011 | General | N/A | N/A | I have looked through attachments 01-10 along with the Solicitation and I’m still not finding what to bid on exactly? Or how we can be a chosen contractor. I’m not sure what exactly we should be bidding on? Or who would be making the decision for choosing the contractor. | Instructions to Offerors and Evaluation factors are provided in Section L (attachment 01,) and Section M (attachment 02,) of the solicitation. This acquisition will utilize the Lowest Price Technically Acceptable (LPTA) source selection procedures in accordance with FAR 15.101-2 and 15.3 as supplemented by the DoD Source Selection Procedures referenced in DFARS 215.300 and the AFFARS Mandatory Procedures 5315.3 to make an integrated assessment for a best value award decision. The Government will select proposals with the lowest evaluated price from among those meeting the acceptability standards for non-price factors. Contract(s) may be awarded to Offerors who are deemed responsible in accordance with FAR 9.1, as supplemented, whose proposal conforms to the solicitation requirements (to include all stated terms, conditions, representations, certifications, and all other information required by Section L of this solicitation) and is judged based on the evaluation factors and subfactors to represent the lowest-priced technically-acceptable. |
The Government intends to award up to 12 contracts; four (4) reserved for 8(a) and up to eight (8) small businesses as a result of this solicitation. The Government reserves the right to award fewer ID/IQ contracts than indicated in the range above, or to award no contracts at all, if the Source Selection Authority (SSA) determines it is in the Government’s best interest.
| 25-Sep-19 | 1-Oct-19 | ||||||
| 0012 | General | We received a wage determination sheet in the amendment 002. What has changed on the wage determination sheet from the previous one? Please help. Thanks | Nothing has changed – Typically a wage determination is incorporated in the contract. We recognized it had not been included and so posted the wage determination that would be utilized, and that an SF 30 would be forthcoming to officially incorporate it into the contract. It is now officially part of the solicitation on the FBO posting as the package titled: Amendment 2, with no change from the Wage Determination posted 18 Sep 2019. | 26-Sep-19 | 1-Oct-19 | ||
| 0013 | General | Section L | Can you please confirm that the Title Page (required with FAR 52.215-1) does NOT count toward the page limitations? | The title page will not count towards the page limitations. | 26-Sep-19 | 1-Oct-19 | |
| 0014 | Attachment 04/05 | Section L | Is it acceptable to recreate Attachment 04 - Experience Overview Sheet and Attachment 05 - Experience Information Sheet in Microsoft Word to ensure we comply with the Times New Roman font requirement? | Please utilize Attachment 04 and Attachment 05 as provided to meet the requirements in Section L 4.2.3.2 | 26-Sep-19 | 10-Oct-19 | |
| 0015 | Sample Project | N/A | Sample Project Attachment | Detail 5/A-302 indicated that there are some roof penetrations while a roof plan is missing. Please provide the roof plan | No roof plan will be provided. Provide roof penetrations whre indicated on the discipline drawings. | 26-Sep-19 | 1-Oct-19 |
| 0016 | Sample Project | N/A | Sample Project Attachment | Please provide locations of mirror M2 24”x72”. | .M2 Mirror locations are indicated on Sheet A-401. | 26-Sep-19 | 10-Oct-19 |
| 0017 | Sample Project | N/A | Sample Project Attachment | Please clarify discrepancies between elevations on A-401 and Room Finish Schedule for all restrooms. | Room Finish Schedule is added to the solicitation package as Attachment 12, Room Finish Schedule. | 26-Sep-19 | 10-Oct-19 |
| 0018 | Sample Project | N/A | Sample Project Attachment | Please provide finishes for Fire Pump and Electrical Rooms in Area B | See RFI 0017 | 26-Sep-19 | 10-Oct-19 |
| 0019 | Sample Project | N/A | Sample Project Attachment | Do we need plywood on walls in Electrical Room in Area B? | Plywood is not required on electrical room walls in Area B. Means and methods may suggest that as an option. | 26-Sep-19 | 1-Oct-19 |
| 0020 | Sample Project | N/A | Sample Project Attachment | Do we need signage for Area B? | Provide signage as per sheet I-121. Detail 2 is for the restroom in Area B, not Area A as is titled. Revise detail 2 title to read "AREA B- RESTROOM SIGNAGE PLAN". | 26-Sep-19 | 10-Oct-19 |
| 0021 | Sample Project | N/A | Sample Project Attachment | What is the thickness of the demolished concrete floor per 2/AD102? | See RFI 0022. | 26-Sep-19 | 1-Oct-19 |
| 0022 | Sample Project | N/A | Sample Project Attachment | Note 3 on drawing AD101 calls for demolition of existing shelves. Please provide additional info/details for these shelves (quantities, size, weight, photos, materials etc.). | Photos will be permitted at the site visit. Indicated depths vary from 2" to 6". Assume 6". | 26-Sep-19 | 1-Oct-19 |
| 0023 | Attachment 07 & 08a | Multiple | Cost Estimate Breakdown | Attachments 07 and 08a appear to require Contractors to submit significant detail as a cost breakdown for each bid. |
o Please clarify that the detail of hours, units, unit costs, etc., is required only for the Prime Contractors labor categories and direct-purchased materials, and NOT for trade subcontractors’ work, since:
Many trade subcontractors will choose not to bid on task orders (especially smaller SOWs) because of the excessive effort required to bid, and the proprietary cost information this detail will reveal.
Trade subcontractor’s proposals are often received very close to the bid due date/time, and the will typically be insufficient time to verify and consolidate this information into a single Attachment 07 and 08a.
If some trade subcontractor detail is needed for evaluation, please consider requiring that it be submitted only by the “apparent low bidder” as “pre-award information”, after initial proposals have been evaluated by the government.
| Please see attached revised Attachments 07, 08a, along with example. | 25-Sep-19 | 10-Oct-19 | ||
| 0024 | Attachment 01, Section L | 4.2.3.3 | SubFactor 3: Technical Execution of Sample Project (Requirements for Design Validation Report, List of Drawings and Bill of Quantities) | Please confirm that a Design Validation Report, List of Drawings & Bill of Quantities are required for a Design/Build project only. If so, and since the Sample Project does not require design services, these items would not be required for the execution of the Sample Project and therefore are not required for this proposal. |
If this is not the case, please clarify, and the following questions apply:
Re: the Bill of Quantities required in the task order proposal:
o Please confirm that a Bill of Quantities will only be required for a Design-Build task order.
o Will the Contractor be responsible for delivering only the proposed quantities in their Bill of Quantities?
o For Bid-Build projects, this requirement would significantly increase the cost of proposal preparation for and would significantly increase risk for the Prime Contractors by adding this extra “scope” document to each trade subcontractor’s proposal.
| See RFI 0023 | 25-Sep-19 | 10-Oct-19 | ||
| 0025 | Note 15 on drawing H-100 calls for treatment of ALL windows and door frame caulking as asbestos (unless testing proves it to be not asbestos). The plan shows the entire building while the sample project is concentrated on Areas A and B only. Shall we work on the entire building to remove and replace caulking for the windows and door frames or within work areas A & B exclusively? | Doors are only to be abated in the New Work Area, as defined in Sheets A-101 and A-102. Windows there is a requirement to abate all in the New Work Area as defined on sheets A-101 and A-102 and a provide a bid option to abate at windows throughout. See sheet A-601 for requirement and definition of new work areas and for base bid and option. |
| The sample project is not funded. The sample project will be utilized to evaluate Offerors for award onto the MACC contract. The Government reserves the right to award the sample project if funding becomes available. | 25-Sep-19 | 1-Oct-19 | ||||||
| 0026 | Attachment 08, Sample Project | 501-751, 09 00 00 - paragraph 1.3.1 | General | Is the Key Personal Qualifications information noted in this paragraph required for this proposal, or will the submittal of this information be required after contract award? | The successful Offeror will be expected to provide this information upon award as a submital. | 19-Sep-19 | 1-Oct-19 | |
| 0027 | Attachment 02, Section M and Solicitation | Section M: 2.1.3 | General | Reference: SF1442 Block 10, Item #9 states, in part: |
“IAW FAR 36.204 the disclosed order of magnitude for the Sample Project, utilized for award evaluation purposes only…” whereas Attachment 02, Section M, paragraph 2.1.3, Item #5 states, “Upon contract award and pursuant to availability of funds, the Government reserves the right to, and intends to award, this sample project, as a task order to a single contractor under the MACC.”
a. Please clarify whether the Sample Project will be awarded.
| There is currently no funding available for this effort. If funding becomes available, the Government reserves the right to award the Sample Project to the Lowest Price Technically Acceptable offeror. | 19-Sep-19 | 1-Oct-19 | ||
| 0028 | Attachment 01, Section L | 3.2.4 | Subcontracting Requirement | Reference: Section L, 3.0, Volume I, Subsection 3.2, Paragraph 3.2.4 instructs to submit Bond electronically for 20% of proposed Sample Project, while the SF1442, Block 13 (b) states that there is No Guarantee required. |
| a. Please clarify. | This text in Section L will be removed as the effort is this requirement is no longer valid. Bid-Bonds have been waived for the entirety of the contract IAW FAR 28.101-1(c), and will not be required for the contract duration. Payment and Performance Bonds will still be required when necessary. | 19-Sep-19 | 1-Oct-19 | ||
| 0029 | Attachment 01, Section L | 2.1.10 | Teaming/Partnering | Reference: Attachment 01, Section L, paragraph 2.1.10, “Teaming/Partnering” instructs: “If the offer is based on a teaming/partnering relationship, the Offeror shall provide all required solicitation information for all parties including a copy of the teaming/partnership agreement. “ |
a. Is this requirement meant to include the design firm(s) the Offeror anticipates using on this contract? If so, will a Teaming Agreement bind the Offeror to utilize the same Designer for every Task Order requiring design services? Or is this Teaming Agreement for the Sample Project only?
b. What is meant by “Offeror shall provide all required solicitation information for all parties…”? Please clarify what information is required for Teaming Partners other than the Teaming Agreement. There are no instructions in Section L regarding this information.
| a&b. A teaming agreement will not bind the offeror to utilize the same Designer for every Task Order. Offerors will provide a copy of the teaming agreement to comply with FAR 52.207-6. | 19-Sep-19 | 1-Oct-19 | |
| 0030 | Attachment 01, Section L | 4.2.3.3 | Reference: Attachment 01, Section L, paragraph 4.2.3.3, Item #1 instructs the Offeror to provide “A Design Validation Report that reflects discipline specific analysis.” |
a. Could the government provide a sample of a Design Validation Report or an outline of one, so as to indicate the elements required in such a report?
b. Paragraph 4.2.3.3 also instructs the Offeror to include a list of Drawings and Bill of Quantities identifying the paragraph and page numbers where they exist. The List of Drawings and Bill of Quantities will not count towards the page limit.” Please provide additional guidance regarding the details required/expected in the List and Bill of Quantities.
| A Design Validation Report is not required for the Sample Project. A Design Validation Report may be required at the task order level, and an example may be requested at that time. | 19-Sep-19 | 1-Oct-19 | |||||
| 0031 | Attachment 01, Section L | Attachment 01, Section L directs the proposers to develop technical and cost proposals on the basis of information provided for a “sample” project. Is this a project that will be awarded based on the technical and price proposals provided by one of the contractors selected to receive an ID/IQ contract? | See response to RFI 0001. | 27-Sep-19 | 1-Oct-19 | ||
| 0032 | Attachment 01, Section L | 4.2.3.2, 1.11. 1.12 | Bulletin 1 in Attachment 01, Section L, Paragraph 4.2.3.2 references Attachment 01, paragraph 1.11 or 1.12. Please provide direction on the location of these paragraphs. | Reference to be changed as follows: Attachment 03 SOW, 1.4.5. or 1.4.6. | 27-Sep-19 | 1-Oct-19 | |
| 0033 | Solicitation | Amendment #1 | Small Business Restriction | Amendment #1 Communicates that an Added Special Restriction: All Offerors must have a bona fide place of business within Small Business Region V to be eligible for award and subsequent task orders. Our firm is a Small Business that has offices throughout the country. We have an office in Ohio. The SBA has communicated that they perform "bona fide" certifications for companies participating in the 8(a) program only. Please clarify how you would like Small Businesses to comply with this requirement? | The SBA will verify bona fide place of business in Revion V for 8(a) Small Business concerns. In order to comply with solicitations terms for all other eligible offerors, all offerors are required to have a bona fide place of business in Small Business Region V. The CO will verify all non 8(a) offerors assertion that they have a bona fide place of business in Small Business Region V, as is required to be considered responsive in compliance with the solicitation terms. | 27-Sep-19 | 1-Oct-19 |
| 0034 | Attachment 01, Section L | 4.2.3.3 | Design Validation Report | Attachment 01, Section L, Paragraph 4.2.3.3 requires the Offeror to provide a Design Validation Report for the sample project. Since the design documents are 100% complete, we are requesting further details on what is expected as part of this report; for example, should this be a code compliance review? | A Design Validation Report is not required for the Sample Project. A Design Validation Report may be required at the task order level, and an example may be requested at that time. | 27-Sep-19 | 1-Oct-19 |
| 0035 | General | Sample Project | The finish schedule on page I-102 shows room 100 Warehouse receiving Ceramic tile and ceramic tile cove base. Is this correct? Or, do they want Resilient cove base on the warehouse side of the new walls with existing flooring? | See RFI 0017 | 30-Sep-19 | 10-Oct-19 | |
| 0036 | General | Sample Project | For rooms 115, 116, 118 & 119: the finish schedule only shows wall tile on 1 wall in each restroom, yet, the elevations on page A-401 show wall tile on 2 walls in each room. | See RFI 0017 | 30-Sep-19 | 10-Oct-19 | |
| 0037 | General | Sample Project | Also for the restrooms, The finish schedule call for ceramic tile cove base in all restrooms. They are using a metal trim for the transition between floor and wall tile. Are we to use the metal piece where there is wall tile and the cove pieces where there is no wall tile? | See RFI 0017 | 30-Sep-19 | 10-Oct-19 | |
| 0038 | Section L/M | L 4.2.3.3 & M 2.1.4 | Bonding | If an SBA 8(a) firm enters an acceptable Teaming/Partnering agreement with a firm that meets the minimum bonding capacity ($5M/$10M). Is the SBA 8(a) firm required to independently meet the minimum bonding capacity? | All Offerors must comply with Section L 4.2.3.3 and Section M 2.1.4 . A Teaming/Partnering agreement will not fulfill an offerors requirement to meet this criteria. A joint venture would be required to meet the aforementioned instruction to offerors and evaluation criteria. | 30-Sep-19 | 1-Oct-19 |
| 0039 | General | Please confirm that offerors are not required to apply to the Joint Certification Program (JCP) through the Defense Logistics Information Service (DLIS). JCP certification of offerors was required prior to award of the current MACC program. No indication/requirement for JCP certification is found in the MACC 2020-2025 RFP. | There is no requirement for JCP certification for this solicitation. Prior MACC RFP has no bearing. | 28-Sep-19 | 10-Oct-19 | ||
| 0040 | Attachment 01, Section L | 2.2 | Sec L para 2.2: For Volume II para. 4.2.3.1 Tech Subfactor 1 Management Approach, one sanitized and one non-sanitized copy is to be provided. Should the non-sanitized and sanitized copy be in two separate binders for the paper submission? Should the non-sanitized and sanitized electronic copy be provided on the same CD-A, or should a third CD be provided which ONLY includes the sanitized version? | Per Section L 2.2.1, the sanitized and non-sanitized copy are to be provided in the same binder. | 28-Sep-19 | 10-Oct-19 | |
| 0041 | Attachment 01, Section L | 2.2.5 | Sec L para 2.2.5: Sec. L states that a cover page is required on each Volume, and that the cover page shall include the offeror's name, for both sanitized and unsanitized. Please confirm that the cover page of the sanitized Volume II para. 4.2.3.1. Tech Subfactor 1 Management Approach is to contain the offeror's name? The footnote under Table 1 in para 2.2 states "*Sanitized copy shall remove all references to the name of the Prime Contractor and Subcontractor(s). " | Per Section L 2.2 Table 1, *Sanitized copy shall remove all references to the name of the Prime Contractor and Subcontractor(s).' | 28-Sep-19 | 10-Oct-19 | |
| 0042 | Attachment 01, Section L and Attachment 02, Section M | Section M: 2.1.1.1 and 2.1.1.2 AND Section L: 4.2.3.1 | Volume 2 Subfactor 1 Management Approach requires submittal of a MACC Program QC Plan and Multi-Project Management Plan. Section J Attachment 3 Para 11.2 indicates that the QC staff is to be idenfied by name with resumes included in the Volume 2 Section L Para 4.2.3.1 QC Plan deliverable. The Multi-Project Management Plan description at Section J Attachment 3 Para 3 requires a program organizational chart with names of assigned personnel, but does not indicate that resumes are required to be included in the proposal deliverable. |
Does the government require resumes to be included in the Multi-Project Management Plan?
| Please consider increasing the page limitation on Volume 2 to account for the QC Plan and Multi-Project Management Plan (see RFI 11)? | Correct, Section J Attachment 3 para 3 requests an organizational chart, and does not call for resumes. | 28-Sep-19 | 10-Oct-19 | ||||
| 0043 | Attachment 01, Section L | 3.2.3 | Sec L para 3.2.3 states that the offeror is to "complete" provision 52.219-28. Please advise what specifically is to be included in the proposal in regard to 52.219-28 52.219-28 – Post-Award Small Business Program Rerepresentation? Does the offeror need to include a statement in its proposal in accordance with para. (g) of the clause, or, if the offeror's Reps and Certs are current in SAM, as of the date of the proposal, is the active SAM profile sufficient to meet the requirement of Sec L para 3.2.3 as it relates to 52.219-28? | Per Section L para 3.2.3, please fill out all clauses as applicable. If SAM reps & certs cover the clause, please refer to it with the submission. Failure to comply may result in the offer being deemed non-responsive to the terms and conditions of the solicitation. | 28-Sep-19 | 10-Oct-19 | |
| 0044 | Attachment 01, Section L | 3.2.3 | Sec L para 3.2.3 states that the offeror is to "complete" provision 52.204-8 "Annual Representations and Certifications" and 52.209-7 "Information Regarding Responsibility Matters" in Section K, and all other clauses and provisions, including exceptions or deviations, within Section I, K, and L, as applicable to the Offeror. This requirement is typcially automatically met by maintaining an active registration in SAM. Please identify what specific information or acknowledgement is to be included with the propsal? | Per Section L para 3.2.3, please fill out all clauses as applicable. If SAM reps & certs cover the clause, please refer to it with the submission. Failure to comply may result in the offer being deemed non-responsive to the terms and conditions of the solicitation. | 28-Sep-19 | 10-Oct-19 | |
| 0045 | Attachment 01, Section L | 2.2 | Sec L para 2.2 Table 1 identifies a page limit on Volume I of 5 pages maximum. Please confirm that the 5 page limit is only intended to apply to paragraph 3.1.2 Narrative Summary, and NOT to paragraphs 3.1.1, 3.1.3, 3.2.1, 3.2.2, 3.2.3, 3.2.4, 3.2.5, 3.2.6, or 3.2.7 either by paragraph limitation or in aggregate. Most all items to be included in Volume I have numerous pages that cannot be reduced do to the nature of the documentation required. | Per Section L para 2.2, Table 1, Page limit for Volume 1 refers to a page limit only for the executive summary, referring to Section L para 3.1.2. The rest of the referenced Section L paragraphs are unlimited. | 28-Sep-19 | 10-Oct-19 | |
| 0046 | Attachment 01, Section L | 2.2.4 | Sec L 2.2.4 PAGE SIZE AND FORMAT: please confirm that size/formatting of documents in Volume 1 paragraphs 3.1.1, 3.1.3, 3.2.1, 3.2.2, 3.2.3, 3.2.4, 3.2.5, 3.2.6, and 3.2.7 are exempt from the requirements of Section L paragraph 2.2.4? Most all items to be included in Volume 1 contain formatting that is not in compliance and that is incompatible with the requirements of para. 2.2.4. (1442, SF30's, JV agreements, etc.). The only document in Volume 1 that can comply with the formatting requirements of para 2.2.4 is the Narrative Summary para 3.1.2. | This refers to contractor submissions. Any documentation that is prepared by the Offeror must comply with the page size and formatting requirements laid out in Section L, Paragraph 2.2.4. Forms that are to be filled out by the Contractor that may not meet this provision are exempt by their nature. Therefore, the SF 1442 and SF 30 are exempt, as the Contractor is not preparing the form, but filling it out. Anything provided by the Contractor that is not a fill in form that the Government requests the contractor complete must meet the requirements in Section L paragraph 2.2.4. | 28-Sep-19 | 10-Oct-19 | |
| 0047 | Attachment 01, Section L | 2.1.9 | Sec L para 2.1.9 instructs joint venture offerors to include a copy of their JV agreements with the proposal. Please confirm that those agreements are to be copied into Volume 1 at 3.2.7? | Yes, they may be copied into Volume 1 | 28-Sep-19 | 10-Oct-19 | |
| 0048 | Attachment 01, Section L | 2.1.9 | Sec L para 2.1.9 states that SBA must approve any JV agreements before contract award, but also states that no corrections or changes to the JV agreement is permitted after proposals are submitted for the MACC program. Please clarify - if a JV agreement is submitted to SBA prior to the MACC program due date, if after the bid is submitted (and before the MACC program is awarded), should SBA require changes to a JV agreement, that it is permissible to make necessary changes for successful acceptance by the SBA of the offeror's JV agreement for award of a MACC contract to the JV? | The intent of Section L para 2.1.9 is to have Joint Venture agreements prior to submission. Changes may risk elgibility of the offeror for award and are highly discouraged. | 28-Sep-19 | 10-Oct-19 | |
| 0049 | Attachment 01, Section L | 4.2 | Sec L para 4.2 outlines Volume II as if subfactor 1, 2, 3 and 4 is to be packaged in Volume 2. Sec L para 2.2 Table 1 indicates that each subfactor is a separate Paper Submission Binder and Electronic File. Is each subfactor of 4.2 to be a separate Paper Submission Binder and Electronic File, or, should all of Volume II be included in one consolidated Paper Submission Binder and one Electronic File? If Volume II is to be combined/consolidated so that all subfactors are included, please identify how to the offeror is to treat/submit subfactor 1, management approach, in regards to the required sanitized and non-sanitized version (see also RFI 001)? | Volume II should be included in one consolidated Paper Submission Binder and one Electronic File. | 28-Sep-19 | 10-Oct-19 | |
| 0050 | Attachmen t01, Section L | 4.2 | Sec L para 4.2 outlines Volume II as if subfactor 1, 2, 3 and 4 is to be packaged in Volume 2 with a total 35 page limit. Sec L para 2.2 Table 1 indicates that each subfactor is a separate Paper Submission Binder and Electronic File with varrying page limits (35pg for subfactor 1, 10pg for subfactor 2, no limit for subfactor 3, 4 and 5.) Please clarify the page limitation for the entire Volume II and then for each subfactor? | Sec L para 2.2 Table 1 states that each technical subfactor is included in Volume II. The page limitation for each technical subfactor is indicated for Volume II by each individual sub-factor that encompasses it, per Sec L para 2.2 Table 1 and Sec L para 4.2. As some sub-factors have varying page limitations, to include unlimited pages for Technical Execution of Sample Project, it would be impossible to define an overall Volume II page limitation. | 28-Sep-19 | 10-Oct-19 | |
| 0051 | Attachmen t01, Section L | 4.2.3.2 | Sec L para 4.2.3.2 requires 3 to 5 projects for prior experience, and requires the offeror to provide an Experience Overview Sheet, IAW Section J, Attachment 04 summarizing all example projects, and an Experience Information Sheet, IAW Section J, Attachment 05, for each project. The Experience Overview template is 1 page and the Experience Information Sheet template is 2 pages. If 5 projects are offered and all required templates are provided the section will be 11 pages in length. Sec L para 2.2 Table 1 places a 10 page limit on this section. Please advise, may the 10 page limit be increased to 11 pages to allow 5 projects? | The Experience Overview sheet, Section J Attachment 04 is a summary of each of the projects to be submitted. The Experience Information Sheet, Section J Attachment 05 details each of the projects listed on Attachment 04. The Page limitation as mentioned in Sec L para 2.2 Table 1 and Sec L 4.2 for SubFactor 2 will be updated to allow for an 11 page limitation. | 28-Sep-19 | 10-Oct-19 | |
| 0052 | Attachment 01, Section L And Attachment 02, Section M | Section L: 5.2.4 |
Section M: 2.1.3.5 Cost Estimate Breakdown Sec L para 5.2.4 states "if an Offeror places a zero amount in any cell, the Offeror must affirmatively state that fact and provide a rationale in the price volume". Section J Attachment 07 is a blank 3052. I infer from the statement in para 5.2.4 that there may have been an intent for the 3052 to be pre-populated with line items that require the offeror to input quantity and price values into cells. Even if pre-populated line item take-offs were input by the government, many cells would have zero values.
Q1 - Please comment on the governments expectations regarding cells and zero values?
Additionally, Section M Para 2.1.3.5.a and b indicates that a detailed line item estimate is required:
Q2 - is it required that each division (as indexed on page 100 and page 101 of "Atch_08_Sample_Project_18_September_2019_1-250.pdf") on the AF3052 be provided with an muli-line itemized estimate identifying all materials and labor that make up the proposal for each division (could be 100's of lines per division), or that simply one estimate line is to be provided for each division with lump sum material, labor and equipment identified? In other words, please clarify that an R.S. Means type estimate for the project is not requested and confirm that a single line per specification section is sufficient on the AF3052 to fulfill both the Volume 2 Section L Para 2.1.3.5 (redacted costs) and Volume 3 Section L Para 5.2.4 (non-redacted) proposal deliverable requirements?
| The attachment/3052 has been updated. Please see attachment 07, 08a, and example. | 28-Sep-19 | 10-Oct-19 | |||||
| 0053 | Attachment 01, Section L | Proposal Organization and Page Limits | Table 1: Proposal Organization and Page Limits states that Technical SubFactor 2: Prior Experience is limited to 10 pages. This SubFactor requires us to submit both Attachment 04 and Attachment 05 (for five projects). Since we are submitting five projects and Attachment 05 is two pages, that puts us at the 10-page limit. Would the government consider increasing the page limits for SubFactor 2: Prior Experience to 15 pages? | See RFI 0050 | 2-Oct-19 | 10-Oct-19 | |
| 0054 | Attachment 01, Section L | 2.1.2 | RFIs | Will you answer more questions after 27 September 2019 since the site visit is not until 2 October 2019 and we are sure to have questions after a site visit? | See Section 2.1.2. | 27-Sep-19 | 10-Oct-19 |
| 00055 | Attachment 05 | N/A | Experience Information Sheet | The definition of Prime Contractor states “A contractor that performed at least 20% of the work, and managed all other work for the project. “ Is it possible that you can modify the percentage to “at least 15%” for small businesses? | Yes, amended. | 27-Sep-19 | 10-Oct-19 |
| 0056 | Attachment 01, Section L and Attachment 06 | 3.2.4 and 4.2.3.4 | Bonding | Bonding – Under Volume 1 3.2.4 Bid Bond – It state we shall “submit a bond electronically”. Is this a separate document? Where do we submit it electronically, email? or just on the CD? Then on Volume II 4.2.3.4 Subfactor 4: Bonding – Use Section J, Attachment 6 which states we have to send to bonding company and then they send back to you (Michael) so this will be electronic. Do you want a paper copy of Attachment 6 to inserted in this section to show we sent it to our bonding company? | Section L 3.2.4 was modified, Bid bonds are not required for the sample project nor the duration of the MACC effort. Section L 4.2.3.4 instructs offerors to complete Section J Attachment 6. The offeror is required to complete the highlighted portions on Page 1 & 2, and send to the surety, who will return the Responsibility Questionairre to Ms. Jessica Shively as stated on Page 1. | 27-Sep-19 | 10-Oct-19 |
| 0057 | Attachment 01, Section L | 3.2.5 | Under Volume I 3.2.5 Financial Resources – submit income statement and balance sheet for previous 5 years. Our report from our accounting firm is a good 30 pages long. Will this be used against the 5 pages maximum for this section? The information asked for in Volume I exceeds 5 pages. (3.1.1 = 1 page; 3.1.2 = 1 page; 3.2.1 = 2 pages; 3.2.4 (electronic? See question 3); 3.2.5 letter from financial institution and bonding company = 2 pages [not including income statement and balance sheet]. That is 6 pages already. | See RFI 005. | 27-Sep-19 | 10-Oct-19 | |
| 0058 | General | Amendments | Also on FBO, I know you had IT issues but it shows Amendment 1 dated 9/19/19, Amendment 2 dated 9/25/19 and Amendment 3 dated 10/1/19. You have only officially issued Amendment 1 dated 9/25/19 and 2 dated 10/1/19, correct? | All amendments have been officially issued. An SF 30 was only created on 25 September 2019 and 1 October 2019. The 25 September 2019 SF 30 encompasses amendments from 19 September 2019 and 25 September 2019. Please note the Summary of Package Changes. | 27-Sep-19 | 10-Oct-19 | |
| 0059 | Attachment 01, Section L | 5.5 | Pricing | Please clarify what “additional cost information” is referring to in Section L 5.5. Is Section L 5.5 referring to Attachment 07-Construction Estimate Breakdown? | If necessary, additional cost information (certified cost or pricing data, or other than certified cost or pricing data) will be identified at the time it is requested. Attachment 07 is required for this solicitation and may be required for subsequent task orders. | 4-Oct-19 | 10-Oct-19 |
| 0060 | Attachment 01, Section L | 4.2.3.3. | General | Does the Construction Estimate Breakdown need to be submitted with our proposal or afterward upon request? | Yes, with the proposal, in order to evaluate the Sample Project IAW Sec L 4.2.3.3 | 4-Oct-19 | 10-Oct-19 |
| 0061 | Attachment 01, Section L | 5.0 | General | Do mandays/manhours and rates need to be listed on the Construction Estimate Breakdown? This is not how subcontractors submit pricing to general contractors. | Yes, Please see attachment as an example | 4-Oct-19 | 10-Oct-19 |
| 0062 | Attachment 01, Section L | 5.0 | General | Is listing only the totals on the Construction Estimate Breakdown acceptable? | No. Please see response to RFI 0052 | 4-Oct-19 | 10-Oct-19 |
| 0063 | Solicitation | General | Are offers for this solicitation expected to fill out price information in Section B of the Solicitation? | The offeror is not required to fill out Section B. | 4-Oct-19 | 10-Oct-19 | |
| 0064 | Attachment 01, Section L | 2.2.1 | General | Per Section L, Table 1, how are we to submit one sanitized and one un-sanitized copy of only Subfactor 1 of Volume II? Per paragraph 2.2.1, each Subfactor is not separately bound; the Volumes are separately bound. Would it be possible to submit one sanitized and one unsanitized copy of the entirety of Volume II, including all four Subfactors? | See RFI's 0040 and 0041 | 4-Oct-19 | 10-Oct-19 |
| 0065 | Attch 08 Seed TO Dwgs: A-111 Note 6 | Sample Project Attachment | Reference A-111. Note 16. What is the spacing of the 800S162-68 (50 KSI) cold formed joists? | CE will attempt to gather information, however information might not be available in time for submission. | 4-Oct-19 | 10-Oct-19 | |
| 0066 | Attch 08 Seed TO Dwgs: A-111 Sec. 3 | Sample Project Attachment | Reference 3/A-111. There is a space adjacent to the Mezzanine that cannot be accessed (Plan East). Please confirm there is no access to the space, and it will remain unfinished. | See drawing 1/A121. ACT ceiling below will allow access. | 4-Oct-19 | 10-Oct-19 | |
| 0067 | Attch 08 Seed TO Dwgs: A-302 Sec. 6 | Sample Project Attachment | Reference 6/A-302. There is no foundation below the operable partition support steel. Please confirm no foundation is required at this location. | See Keynote 12 Sheet A-111 and wall foundtaions detail 1/A-301. | 4-Oct-19 | 10-Oct-19 | |
| 0068 | Attch 08 Seed TO Dwgs: I-101 Gen Note 5 | Sample Project Attachment | Reference I-101. General Note 5. Install Mini-Blinds at all windows. Please confirm interior and exterior windows are to receive mini-blinds. | Confirmed. All interior and exterior windows are to receive mini-blinds. | 4-Oct-19 | 10-Oct-19 | |
| 0069 | Attch 08 Seed TO Dwgs: I-101/102 | Sample Project Attachment | Reference I-101/I-102. Please provide a manufacturer and specification for Sealed Concrete. | See Interior Room Finish Key note for Painted Concrete - PC1 | 4-Oct-19 | 10-Oct-19 | |
| 0070 | Attch 08 Seed TO SOW: Para. 1.01.C.2 | Sample Project Attachment | Reference Statement of Work Paragraph 1.01.C.2. The period of performance is listed as 520 days; this project will not require 520 days if completed in a single phase. Is there any phasing required? | No phasing required | 4-Oct-19 | 10-Oct-19 | |
| 0071 | No Ref | Sample Project Attachment | Will other areas of the building be occupied by the Government during the renovation? | Other areas of the building will be occupied by the Government during the renovataion. | 4-Oct-19 | 10-Oct-19 | |
| 0072 | No Ref | Sample Project Attachment | Will material be removed from shelves prior to renovation? If not, what is the expectation for covering and protecting supplies and material on the shelves? | Government will remove items from shelves prior to notice to proceed. | 4-Oct-19 | 10-Oct-19 | |
| 0073 | Attch 08 Seed TO Dwgs: M-601 | Sample Project Attachment | Reference M-601. Split System A/C Furnace Schedule. Please provide information AC & CU 3-6. | See appendix H of Design Analysis | 4-Oct-19 | 10-Oct-19 | |
| 0074 | Attch 08 Seed TO Dwgs: C-101 | Sample Project Attachment | Please provide as-builts of the docks. If as-builts are not available, please advise: |
a. Thickness of concerete pavement?
b. Thickness of concrete stem/foundation wall?
| c. Depth and type of aggregate backfill? | Information requested is not available. | 4-Oct-19 | 10-Oct-19 | ||
| 0075 | Attch 01 Sec L: 4.2.3.3 | SubFactor 3 Technical Execution of the SEED | Previous Government RFI 0009 response to the "safety plan" reference in Atch 01 Sec L Para 4.2.3.3.2 (now 4.2.3.3.1 per Sec L Amend 3) is not clear, both in the question and government answer. The reference to "safety plan" in 4.2.3.3 is specifically in regard and inclusive of the "schedule plan" deliverable description. We believe that the reference to "safety plan" is erroneous, and that the RFP author of Sec L Para 4.2.3.3 and Sec M para 2.1.3 intended for the "safety plan" verbiage to be "safety references within the project schedule as they relate to project construction activities", not as a requirement for a specific safety plan. | ||
| Q1: Please confirm that a safety plan IS NOT required and confirm that the narrative above is accurate? | Safety Plan is not required as part of the sample proposal, however effort to produce/submit should be included in cost estimate. | 4-Oct-19 | 10-Oct-19 | ||
| 0076 | Attch 01 Sec L: 4.2.3.1 | SubFactor 1 Management Approach | Previous Government RFI 0026 response regarding staffing resumes/qualifications for the SEED TO DIV 09 90 00 indicates that the information is not to be included in the MACC proposal, but will be required upon award. To note - the question WAS SPECIFIC to a painting specification requirement. In regards to the MACC program proposal - the only location where name and qualifications are identified as a deliverable requirement is at Atach 1 Sec L Para 4.2.3.1.1.a, where the QC plan requests names, qualifications and duties of each person assigned. |
Q1: What are the governments expectations for MACC offerors' proposals in regard to MACC Program Staffing?
Q2: Does the QC plan deliverable need to provide names and qualifications for the SEED, as a deliverable now, to fulfill Atach 1 Sec L Para 4.2.3.1.1.a?
Q3: If names and qualifications are required, are resumes also required?
| Q4: Do other MACC program positions need to be idenfied by name, qualification and resume (such as the CM, SSHO, Superintendents, etc.), as part of the MACC program proposal, or does that info only need to be provided after award of the MACC program contract? | Q1: Requirement is to provide a sample of a QC plan, not to provide a completely developed plan with names assigned to roles. The intent is to provide a organizational chart with lines of authority, not to have names assigned to those roles. Q2: Names are not required but qualifications are. Q3: Since names are not required, resumes are not required for the sample project. Q4: the positions need to be defined not the names. | 4-Oct-19 | 10-Oct-19 | |||||
| 0077 | Attch 01 Sec L: 2.1.10 | Teaming/Partnering | Previous Amend 3 RFI 029 question and answer was focused on design partner teaming agreements. We believe that both the question and answer was to clarify a circumstance encountered in the last MACC program that prevented contractors from proposing on task orders where their (the prime MACC contractor) had a teaming agreement in place with the RFP preparer, and that the question's reference back to Atch 01 Sec L 2.1.10 was misconstrued. From our overview of the previous MACC in comparrison to the new 2020-2025 program, teaming agreements at a tier subcontractor level is no longer desired. Teaming Agreements as it relates to Atch 01 Sec L Para 2.1.10 and to FAR 52.207-6 (referenced in government answer to RFI 0029) are in regard to prime contract offerors who intend to use qualifications of two or more firms to meet MACC program requirements. | |||||
| Q1: Please confirm that the government DOES NOT desire or require that MACC prime contract offerors enter into or provide teaming agreements to the government (for the MACC proposal) with subcontractors (including designers), unless the offeror intends to use specific subcontractors' resources to qualify for MACC program requirements (bonding, past performance, personnel, etc.). | Previous MACC and this MACC are two separate programs. We require teaming | 4-Oct-19 | 10-Oct-19 | |||||
| 0078 | Attch 01 Sec L: 2.1.10 | Teaming/Partnering | Previous Amend 3 RFI 029 question and answer was focused on design partner teaming agreements. We believe that both the question and answer was to clarify a circumstance encountered in the last MACC program that prevented contractors from proposing on task orders where their (the prime MACC contractor) had a teaming agreement in place with the RFP preparer, and that the question's reference back to Atch 01 Sec L 2.1.10 was misconstrued. From our overview of the previous MACC in comparrison to the new 2020-2025 program, teaming agreements at a tier subcontractor level is no longer desired. Teaming Agreements as it relates to Atch 01 Sec L Para 2.1.10 and to FAR 52.207-6 (referenced in government answer to RFI 0029) are in regard to prime contract offerors who intend to use qualifications of two or more firms to meet MACC program requirements. | |||||
| Q1: Please confirm that the government DOES NOT desire or require that MACC prime contract offerors enter into or provide teaming agreements to the government (for the MACC proposal) with subcontractors (including designers), unless the offeror intends to use specific subcontractors' resources to qualify for MACC program requirements (bonding, past performance, personnel, etc.). | Teaming Agreements are not required unless the offer is based on a teaming/partnering relationship, IAW Section L 2.1.10, or unless specified or required to compete for MACC Task Order requirements. | 4-Oct-19 | 10-Oct-19 | |||||
| 0079 | Attch 08 Seed TO Dwgs: C-501 | Sample Project | Does the PIV on C-501 need to have a tamper switch tied to the fire alarm system ? | Yes. | 4-Oct-19 | 10-Oct-19 | ||
| 0080 | Attch 08 Seed TO Dwgs | Sample Project | Suspect there may be issues achieving Fire Alarm/MNS Audibility and Intelligibility (Reverb / Speaker feedback) due to steel surfaces on LOC microphone - please identify extent of effort required of contractor if intelligibility cannot be achieved? | For the purpose of this proposal, bid as per contract drawings. This will be reviewed/corrected prior to funded project release. | 4-Oct-19 | 10-Oct-19 | ||
| 0081 | Attch 08 Seed TO Dwgs | Sample Project | The fire jockey pump CP is located on the generator, but the Fire Pump Controller is not shown to be on gen power is this correct? | For the purpose of this proposal, bid as per contract drawings. This will be reviewed/corrected prior to funded project release. | 4-Oct-19 | 10-Oct-19 | ||
| 0082 | Attch 08 Seed TO Dwgs | Sample Project | Does the new service entrance transformer need EMCS compatibility ? | The service entrance transformer does not need EMCS compatibility. | 4-Oct-19 | 10-Oct-19 |
This is the start of the file's text. The full file is on GovTribe.