RFI__5_and_Note_to_Offerors.docx
DOCX document 13 KB Posted
- Attached to
- Civil Engineering Multiple Award Construction Contract (CEMACC) Federal contract opportunity
- Solicitation number
- FA8501-17-R-0001
About this file
RFI #5 and Notice to Offerors
View the file
Other files for this federal contract opportunity
Show all 50
Civil Engineering Multiple Award Construction Contract (CEMACC) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI #5 and ***NOTE TO OFFERORS****** Question:
The Design Schedule defined in the B140 CMM SOW calls for a design schedule that will extend to 120 days. Amendment 2 calls for the 140 CMM project to be completed in 153 days from the Construction NTP. Is it correct that the Construction NTP will be issued after the Final Design Submittal is completed and approved?
Answer:
The period of performance was separated between Design and Construction on this project. The design phase period of performance for 160049 is 120 days and the construction period of performance is 153 days as indicated in FAR Clause 52.211-10 which would give you the total of 273 days
Question:
The Design Schedule defined in the B149 Locker Room SOW calls for a design schedule that will extend to 135 days. Amendment 2 calls for the 149 Locker Room Project to be completed in 153 days from the Construction NTP. Is it correct that the Construction NTP will be issued after the Final Design Submittal is completed and approved?
Answer:
In addition, the design phase period of performance for 160082 is 135 days and the construction period of performance is 153 days which would give you a total of 288 days that you made reference to in your question.
The design period of performance is captured in the SOW and the Construction Period of Performance is captured in the FAR Clause.
*****NOTE TO OFFERORS*******
Please note that 20 Feb 2017 is a federal holiday. Please do not arrange for delivery of proposals on that date as no one will be here to accept them.