Robins Roofing Requirements
UHHZ160306
Design Requirements
- ASCE 7-10 Current Edition, International Building Code, Current Edition, UFC 3-110-03, Exposure C, Robins Base Facility Standards (BFS) Engineering
- Design Architect/Engineer must derive majority of income from roof designs, uplift calculations for all wind zones, and hydraulic calculations for gutters on 100 year flood Metal Roof Types
- 3” Trapezoidal or 2” Architectural and will always require a 360 degree seam mechanically seamed
- No roof penetrations, no glue down attachment of lightning protection system, no dissimilar metal contact
- Lightning Protection System shall meet NFPA 780, UL96A most current edition, LPI 175 Single Ply
- 60 mil PVC with hot air welded seams Warranty
- 20 Year single source NDL weather tightness warranty Installer
- Must have installer trained by roofing manufacturer onsite during installation Inspections
- Manufacture’s inspection once within 3 days of starting roof and one after completion. (Minimum of 2 for fewer than 10,000 sf and 3 minimum over 10,000 sf)
- Written report must be furnished.
- COR must be present during inspection Additional Submittals
- Roofing material
- Sample warranty (before approving roof)
- Uplift calculations for wind zones, and hydraulic for gutters
- Certified installers certificate
- Inspection report