12_Attachment_1C_Hill_AFB_Civil_Engineering_Requirements.docx
DOCX document 272 KB Posted
- Attached to
- Temporary Facility T-2728 Federal contract opportunity
- Solicitation number
- FA8219-18-R-0010
About this file
Attachment 1C Hill Air Force Base Civil Engineering Requirements
View the file
Other files for this federal contract opportunity
Show all 47
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 1C – Base Civil Engineering Requirements
Temp-2728 Program
Applicable sections from the Base Facility Design Standard
INTRODUCTION: Because this procurement is considered an equipment purchase, The Base Facility Design Standard only applies to utility and site preparation aspects supporting the equipment. The excerpts below outline the requirements of HAFB Civil Engineering regarding site work, excavation, utility connections and metering, roads and parking lots, fire protection, electrical, lighting, access control, and intrusion detection which apply to the Minor Construction portion of this procurement.
SECTION 1 DOES NOT APPLY
2. SPECIAL CONSIDERATIONS
2.1 Base Location:
Hill Air Force Base is located near Ogden, Utah approximately 30 miles north of Salt Lake City at an elevation of 4700 Ft above sea level.
2.2 Construction Season Limitations:
Earthwork can normally only be accomplished from 15 March to 15 November. Paving is normally accomplished from 15 May through 01 October. Structural work may generally be accomplished on a year round basis, but it must be protected from temperature extremes. Built-up roof construction is generally limited to the period from 15 May through 15 October.
2.3 Soil and Foundation Considerations:
Typical soils range from sand to silty sand with thin discontinuous layers of silty clay and clayey silt being common. Potable wells have a static water level of approximately 500 feet below the surface; however, perched water may be encountered at more shallow depths. The average soil pH is approximately 7.8. The soil resistivity ranges from 2,000 to 15,000 ohms/cm. Spread footings are the typical structural foundation. All footings shall be at least 3 feet below grade.
2.5 General Security Requirements:
2.5.1 Design and construction contractors must coordinate with the Contracting Officer concerning obtaining the paperwork for identification badges (AFMC Form 496).
2.5.1.1 In order to gain access to restricted area contractors must submit the necessary paper work for a security clearance, through prescribed channels. If additional information is necessary contact your Contracting Officer for further guidance.
2.5.1.2 In order to gain access to controlled area contractors must undergo a local files check as a minimum. Some areas will require more stringent checks. Request for access should be submitted through the Contracting Officer or Air Force Project manager who will forward it on to 75 SFS/S5.
2.5.2 All privately owned vehicles entering the installation must comply with State of Utah inspection, emission standards, and insurance requirements.
2.5.3 Any proposed work affecting communication lines or security systems, must be reviewed and approved by 75th CES Electric/Electronic Shop, Base Civil Engineering, 777-0075 and 75 SFS/S4E, Security Forces, 777-5532.
2.5.4 All renovations and new construction of must be designed to adhere to current standards set forth for resource protection, antiterrorism, information security and industrial security requirements in:
a. AFI 31-101, Integrated Defense, (OPR: 75 SFS/S5)
b. AFI 10-245, Antiterrorism, which references UFC 4-010-01, DoD Minimum Antiterrorism Standards for Buildings, (OPR: 75 ABW/AT)
c. AFI 31-401, Information Security Program Regulations, (OPR: 75 ABW/IPI)
d. AFI 31-601, Industrial Security Program Management respectively, (OPR: 75 ABW/IPD)
e. Military Handbook 1013/1A, Design Guidelines for Physical Security of Fixed Land-Based Facilities or the Civil Engineering Facility Manuals (OPR: 75 Security Forces and Civil Engineering)
f. Department of Defense Manual 5205.07v3/Air Force Manual 16-703V3, Special Access Program (SAP) Security Manual: Physical Security
g. IC Tech Spec‐For ICD/ICS 705, Technical Specifications for Construction and Management of Sensitive Compartmented Information Facilities
2.5.5 Any buildings, which will house assets which are classified, contain funds, Arms, Ammunition or Explosives or controlled substances must have an initial and follow-up security standard inspection by the applicable Government office prior to operation. (Resource Protection: 75 SFS/S5SR, 777-6155; Physical Security: 75 CEG/CEPM, 777-0584 or 777-4235; Information Security: 75 ABW/IPI, 777-7811; Industrial Security: 75 ABW/IPD, 777-6617)
2.5.6 If the project will be inside of or on the boundary of a restricted or controlled area, a free zone may be necessary. Contact with the 75 SFS Resource Protection Office during the initial design phase is critical to ensure proper design, execution, and approval of the free zone. Free zones will be established and approved IAW AFI 31-101 as supplemented and a copy of the free zone security procedures provided to the contractor prior to beginning work.
2.5.7 Any special security requirements needed for the contractor should be coordinated through 75 SFS/S5, 777-6155.
2.5.8 Foreign Nationals employed by the contractor must obtain clearance through the Foreign Disclosure Office, ext. 7-6858 before being allowed access to the installation. Foreign Nationals are not allowed to work in Controlled or Restricted areas.
2.5.9 Locks and Hasps:
| Padlocks: Key Actuated | |
| Low Security: MIL SPEC P-17802 | |
| Medium Security: MIL SPEC 43951 | |
| High Security: MILSPEC MIL-P-43607 | |
| Hasp: | High Security Hasp, MILSPEC MIL-H-29181 |
Built In Combination Locks, Authorized Group 1R:
Mas-Hamilton, Electronic Lock (For doors: CDX-10; For safes: X-10)
NOTE: Built in combination locks and mechanical/digital cipher locks shall not be installed on any doors.
2.5.10 Intrusion Detection & Access Control Systems: See section 14.12 and 14.13 for further guidance.
2.6 Construction Permits:
2.6.1 No excavation shall be done prior to receiving a Base Civil Engineering Excavation Permit. If excavation is started without obtaining a permit, the Contractor shall be held liable for repairs to any broken utility lines and for other damage resulting from the broken lines. The Contractor shall request a permit 14 calendar days prior to scheduled start of digging. Hand digging shall be required to locate utilities shown on the contract drawings, Excavation Permit or 3 feet (1 meter) on either side of locations identified by Base Maintenance Shops.
2.6.2 Contractors must obtain a Utah Pollutant Discharge Elimination System (UPDES) storm water permit or waiver if the project disturbs more than 1 acre of soil surface area. To obtain the permit a contractor must prepare a Storm Water Pollution Prevention Plan and then submit a Notice of Intent (NOI), and the required fee to the State of Utah, Department of Environmental Quality, Division of Water Quality. Contractor shall submit and receive approval of the UPDES permit before starting construction.
2.6.2.1 Projects disturbing a soil surface area greater than one acre will require submission of a sediment and erosion control plan to the project manager for subsequent review and approval by the Environmental Compliance Office 75 CEG/CEIE. The contractor must receive approval of the plan and implement approved best management practices before starting construction.
2.6.2.2 Projects disturbing more than one acre of soil surface area will also submit a plan for permanent stabilization of disturbed area to the project manager for subsequent review and approval by the Environmental Compliance Office 75 CEG/CEIE. The contractor shall receive approval of the plan and implement approved best management practices before contract closeout. Examples of best management practices are available at the following web sites:
http://cfpub.epa.gov/npdes/stormwater/menuofbmps/con_site.cfm http://cfpub.epa.gov/npdes/stormwater/menuofbmps/post.cfm
2.6.2.3 Projects with a footprint greater than 5,000 square feet must maintain or restore, to the maximum extent technically feasible, the predevelopment hydrology of the property with regard to the temperature, rate, volume, and duration of flow. Use of LID techniques in accordance with EISA Section 438 Guidance shall be implemented. Comply with UFC 3-210-10.
2.7 Borrow and Disposal:
Unless otherwise designated, all borrow shall be obtained off base at the contractor’s expense. Clean excavation including soil/concrete, asphalt and wood may be separated and disposed of in one of the appropriate cells in the Government landfill at the north end of Hill AFB. All other building demolition materials shall be legally disposed of by the contractor at an off-base landfill.
2.8 Utility Line Identification:
2.8.1 Contractor shall provide and install a tracer wire of 10 gage insulated copper within one foot of all new utilities (except metallic or electrical lines) placed underground at Hill Air Force Base. Utility shall be defined as, but not limited to: electric systems; storm, sanitary and subsurface drainage systems including French drains, rain gutter collection and distribution systems, and other water collection systems; potable and non-potable water systems; natural gas systems; industrial waste systems; fuel systems; communication systems; street lighting systems; heating and cooling systems; airfield associated systems; environmental systems; other objects designed for future use such as buried conduits and pipes; and other comparable items, objects or systems. The determination and definition of a utility requiring tracer wire shall be at the sole discretion of the United States Air Force. The contractor may be required to place tracer wire on other utility items and systems at the request of the US Air Force.
2.8.2 If length of new utility is 500 feet or less contractor shall install one terminal box of 2” diameter pipe at each end of the wire marking the utility location.
2.8.3 If length of new utility is greater than 500 feet, contractor shall place terminal boxes at 500 feet intervals.
2.8.4 Terminal boxes shall have a metal screw-on type lid mounted flush with pavement or raised above the existing ground elevation, as determined by the project manager. (Handley Industries or approved equal).
2.8.5 Contractor shall provide a 21-day notice to the Civil Engineering project manager of all utility line installations to allow the Air Force to survey and map all new utility lines. Contractor shall not backfill utility trenches until the lines have been surveyed and approval given.
2.12 Testing:
Contractor is required to engage an independent testing for all testing that is required including soils, asphalt, concrete, welding, etc. unless such testing is required by regulation to be performed by the Government.
3. CIVIL ENGINEERING CONSIDERATIONS:
3.0 Applicable Standards: Comply with applicable DoD and Base Standards and American Public Works Association (APWA) Manual of Standard Plan and Specifications. If these standards conflict, then the Government standards will take precedence. However, water and sanitary sewer segments/appurtenances which become ownership of the system owner, American Water, shall comply with their design guide, specifications and details for Hill AFB available at their web site http://www.amwater.com/products-and-services/Military-Services/Bases-we-serve/Hill-Air-Force-Base/. These specifications generally take precedence over other standards. It is recommended that prime contractor contract with American Water to construct sewer and water lines that will be owned by them. If not constructed by American Water then the contractor will have to transfer the real property via the DD1354 to the Government. Furthermore, if the applicable utility is not constructed by the system owner then the contractor will have to pay for compliance inspections, connection fees, etc as required by the system owner.
Utility line placement in new roads shall comply with the Base standard utility corridor detail currently on file.
3.2 Roads and Parking Lots:
3.2.1 Typical Maintenance Work:
3.2.1.1 Crack Filling: Rubberized asphalt crack sealing will normally be accomplished by in house forces.
3.2.1.2 Cold planning: Cold planning shall be used to correct surface irregularities and to match curb and gutter elevations prior to overlaying.
3.2.1.3 Heat scarifications: Heat scarification will be used to insure bonding of bituminous overlays where considered necessary by the Pavements Engineer, especially for thin overlays.
3.2.1.4 Slurry seals: Slurry seals will be used as one option to seal low volume surface roads after sealing all cracks.
3.2.1.5 Open graded plant mix seal coat: This seal coat will be used as one option to seal all roads and parking lots.
3.2.1.6 Coal tar treatment: Coal tar seals will be used to seal bituminous concrete in fuel spillage areas.
3.2.1.7 Overlays: Bituminous overlays will be used to rehabilitate bituminous concrete. It will normally be placed a minimum of 1 inch thick. It will be the option of the Government’s pavement Engineer as to whether any existing bituminous concrete will be removed prior to placing the overlay.
3.2.1.8 Traffic control in construction areas: The contractor shall provide and maintain all construction traffic control devices. These devises and their layout shall conform to Part VI of the Manual of Uniform Traffic Control Devises or the Utah State Department of Transportation equivalent. The traffic control plan shall be submitted to the Base Traffic Engineer prior to implementation.
3.3 Potable Water:
3.3.1 Well drilling: All future wells shall be drilled by using the reverse rotary drilling method.
3.3.2 Pipe: Water pipe 4inch through 12 inch diameter shall be PVC AWWA C 900. All pipe 12 inch diameter and greater shall be AWWA C 901. Tracer wire and warning tape shall accompany any new water pipe installed.
3.3.3 Pipe depth: Water piping shall be installed a minimum of 4 feet below grade. Fire protection lines shall be installed a minimum of 5 feet below grade.
3.3.4 Pressure gages: Pressure gages shall be placed at the outlet of all well pumps; at the inlet and outlet of all pressure reducing valves, pressure sustaining valves and altitude valves; and at any other location where knowledge of pressure would be beneficial.
3.3.5 Valves: Valves shall be placed at all locations where it would be desirable to isolate the system for maintenance and repair. The number of valves shall not be kept to a minimum as a cost cutting measure. Valves will be placed in conjunction with fire hydrants. Air release valves shall be used at high points to allow the discharge of air in the water distribution system.
3.3.6 Standards: All new water lines and appurtenances shall comply with the standards set forward in the Utah Safe Drinking Water Regulations.
3.3.7 Connections: To avoid pipe shaving residue in building and water distribution systems all connections to existing lines shall be accomplished with a standard tee fitting. Hot tap connections are prohibited unless special permission is granted by the Civil Engineering water shop.
3.7 Structural:
3.7.1. Soil Bearing Capacity: Major structures at Hill Air Force Base, Little Mountain Test Facility, or the Utah Test and Training Range shall have specific foundation studies performed. Minor structures at Hill AFB may use an allowable soil bearing pressure of 3000 psf. Check with the Base Civil Engineer for allowable pressures at Little Mountain Test Facility or Utah Test and Training Range.
3.7.2. Stair Tread Minimum Live Loads: The minimum live loads shall be 100 psf and a 300 lb concentrated load at the location of maximum stress (not simultaneous with the uniform live load.) The minimum concrete depth shall be 2 inches if filled pans are used. Design of metal stairs shall conform to the Metal Stair Manual published by the National Association of Architectural Metal Manufacturers.
3.7.3. Design Frost Penetration: The design frost penetration shall be 36 inches for structures unless a geotechnical report allows for a more shallow depth.
3.7.4. Concrete compressive strength: A minimum concrete compressive strength of 3000 psi at 28 days shall be for all applications except exterior slabs, which shall have a minimum compressive strength of 4000 psi at 28 days.
3.7.5. Reinforcing Steel Strength: A minimum yield strength (Fy) of 60,000 psi shall be used for reinforcing steel.
3.7.6. Floor slab joints: Joints for slabs on grade shall be located so that the area between joints is square. If a square area between contraction joints is not possible, the length of the rectangular area shall not exceed one and one fourth (1-1/4) times the width. The saw depth for the contraction joints shall be as recommended by ACI standards but in no case less than one-fourth (1/4) of the slab thickness. For reinforced slabs the reinforcement bars shall be discontinued through slab joints and not used for load transfer. Load transfer shall be accomplished with dowel bars, keyed joints, thickened edge, or a combination thereof.
3.7.7. Procedure for attaching equipment and other objects to existing roof trusses, joints, beams, and other members of the roof structure: Use clamps instead of drilling or welding. The Base Structural Engineer prior to installation of these loads will give approval for attachment of equipment or other object from the existing roof structures.
3.7.8. Compaction: For cohesive soil under structures, building slabs, steps and paved areas, compact to a minimum of 95% of maximum density determined in accordance with Method 106 of MIL-STD-621 using CE55 compaction effort. For cohesion less soil, compact to a minimum of 100% of maximum density.
3.7.9. Steel Fabrication and Erection: Drill or punch all holes in steel members. Never allow holes to be burned with a torch.
3.7.10. Structural design loads for buildings and other structures shall be developed using Unified Facilities Criteria (UFC) 1-200-01 General Building Requirements and the International Building Code (IBC) Chapter 16 as modified by UFC 3-301-01, Structural Engineering. Use IBC Chapter 16 and UFC 3-310-04 for seismic design.
3.8 Traffic Engineering:
3.8.1 Speed Limit: The Base Speed limit is set at 25 mph on the main arteries unless otherwise noted.
3.8.2 Lane Widths: All traveled lanes will be 12 feet in width. Where curb and gutter is not provided, a 3 foot wide paved shoulder will be provided. Storm drain grates will be selected to avoid presenting a hazard to narrow tires. Car pool and bus stop drop off lanes will be included were needed.
3.8.3 Parking: Parking stalls will be 9 feet wide measured normal to the vehicle and 13 feet wide for a handicapped stall. Allow 30 feet of road width between rows of parking stalls and 18 feet for stall depth. All new parking lots shall have curb and gutter placed around the perimeter. A 30-inch wide curb and gutter section will be used. Curbed islands and landscape planters will not be used if they make snow removal too difficult.
3.8.4 Traffic signs and striping: All traffic signs and striping shall conform to the standards contained in the Manual of Uniform Traffic Control Devises. Striping will be included in all new projects and included when restriping is required. Signposts will be constructed of a 2-inch by 2-inch Dakota Brown steel tube section. The tubing will be mated with steel tube section that is driven into the ground. This will allow for the rapid repair of damaged signposts. The backside of all signs shall be Dakota Brown.
4.1 Architectural Compatibility:
4.1.1 General: The Hill Air Force Base Architectural Compatibility Standards Brochure shall be followed as a guide.
4.1.2 Colors: All exterior building finish colors shall conform to the above standard. The colors are taken from the Federal Standard 595B, Colors Used In Government Procurement. All exteriors shall be Federal Paint number 30099, Dakota Brown; or 23617, Greystone. No building shall have more than one color trim unless allowed by the Architectural Compatibility Officer. Factory pre-finished siding and roofing can match the manufacturer’s standard, available color selection as longs as the color matches the above colors as closely as possible. All selections are subject to the approval of the Base Architectural Compatibility Officer.
4.1.3 Facades: The majority of the permanent facilities at Hill AFB are brick. This standard should be maintained. Any other materials used shall complement the brick in making an aesthetically pleasing, traditional statement. Choices should conform to the Base Architectural Compatibility Standards. All new and remodeled facades shall blend with and complement the permanent construction of the installation.
4.2 Definitive Design:
Refer to the AFMC Facility Quality Program Manual as a guideline for Air Force Standards.
4.3 Interior Design:
4.3.1 Carpets: Comply with AF ETL 07-4. Carpets will contain a definite pattern and shall be suitable to the function area. All carpeting will meet the flame spread rating required in the Life Safety Code.
4.3.2 Sound Attenuation: Any building design requiring reduction of exterior generated noises shall be done in accordance with the Uniform Building Code, Chapter 35. Also consult the Hill Air Force Base Air Installation Compatible Use Zone Report, amended April 1982, for further sound attenuation guidance. Any penetrations through an STC rated wall shall utilize flexible couplings within 12" of each side of the wall.
4.3.3 Noncombustible material: The installation of exterior finish material shall comply with the requirement that at least 75 percent of the total interior wall surface of any one room must be of non-combustible material, Class B. This material must have a flame spread of 75 or less. Wood paneling will not be used. Wall carpeting will have a smoke development rating of 25 or less.
4.3.4 Concealment: All wiring, piping, and ductwork will be concealed whenever possible.
4.3.5 Interior Graphics Systems: An interior graphics system will be used where appropriate to control message size and complexity, to establish a specific lettering style, establish a color scheme, and enhance the overall interior environment.
4.3.6 Systems Furniture: Systems furniture should be considered for installation in large open areas to condense personnel and optimize space utilization. It should not be used to cover window spaces or exterior fin tube heating. For Right-Sizing requirements comply with AFH 32-1084. The cubicles should be appropriately for the use intended but under no circumstances should be less than 48 square feet. The electrical designer, the architect, and the interior designer must coordinate during the design process. Systems furniture is typically specified and ordered when construction is nearing completion; therefore, if proper coordination has not occurred earlier in the design process, field interface problems will occur. Specify an 8-wire harness consisting of 4 circuit conductors, 1 oversized neutral conductor, 1 full sized neutral conductor and 2 separate equipment grounding conductors. Provide oversized neutrals to match the harness configuration and balance loads between circuits and phases. A single circuit must not serve more than 4 cubicles under any circumstances.
4.3.7 All suspended acoustical ceilings shall have a recessed-grid with drop (regular) edge tile. Tile shall be a 2 by 2 grid or 2x4 grid scored in the center so the 2x4 appears like a 2x2 grid."
4.3.8 All paper towel and toilet paper dispensers shall comply with the Custodial Contractor requirements. Use Georgia-Pacific model numbers 52109 or 58201 for paper towel dispensers and model numbers 56783 or 56784 for toilet paper dispensers.
4.4 Accessibility design:
ABA Accessibility Standard for Department of Defense Facilities. Any new building, addition or major renovation shall comply with this new Standard. Hill Air Force Base Point of Contact is Richard Nehring. (801) 775-3369.
4.5 Keying and Hardware:
| 4.5.1 | Padlocks: Key Actuated | |
| Low Security: MIL SPEC P-17802 | ||
| Medium Security: MIL SPEC 43951 | ||
| High Security: MILSPEC MIL-P-43607 | ||
| Hasp: | High Security Hasp, MILSPEC MIL-H-29181 |
Built In Combination Locks, Authorized Group 1R:
Mas-Hamilton, Electronic Lock (For doors: CDX-10; for safes: X-10) NOTE: Built In Combination Locks shall not be installed on exterior doors.
4.5.2 Card Access: Manufacturer of Hill AFB card access system is Vindicator utilizing the V5 Network Security Appliance with the Access Control Server w/ UHS/TDEA. The system server terminal (SST) will either be the WYSE terminal or Security Archive Workstation (SAW)
4.5.2.1 All exterior doors will be equipped with electronic strikes that fail safe “locked” upon extended power failures that exceed the battery backup capability; no magnetic locks will be allowed on exterior doors. Interior doors can/may be equipped with strikes as long as the means of egress utilize a “crash bar.”
4.5.2.2 Hill AFB utilizes standards for all Card Access components and this list is made available by the 75 CES Electronics Flight.
4.5.3 Keying: Master keying shall be ASSA model # V80600IC-626 SUB 595-95 Yale with 1210 core. All locks shall be furnished with removable core cylinders. The cylinder will be capable of being removed through the face of the knob by means of a control key. All cores and keys will be purchased by the contractor but must be shipped either through Clark Security Products Inc or directly to HAFB Lock Shop. A key schedule and plan is required. The purchasing contractor must allow 6 weeks for shipment. All cores will be pinned by the Base Lock Shop. All locks will be grand master keyed into the base system and shall be sub-mastered by the BCE locksmith.
4.5.4 Hardware: Locksets and latches shall comply with (ANSI/BHMA A156.13, Series 1000, Operational Grade 1, Security Grade (l) (2) (and) (ANSI/BHMA A156.2, Series 4000, Grade l). Latches shall be Yale lever arm, Model 5407-LN, 626 finish, with 2 ¾ backset, and Augusta handles that accept ASSA removable core #V-80600. Provide trim of wrought construction and of commercial plain design.
4.6 Sign Policy:
All signs shall be in accordance with UFC 3-120-01 Air Force Sign Standard and the base Architectural Compatibility Standards. All parking and traffic signs must be installed on a 2 by 2 quick punch type signpost installed in sleeves. All sign posts must be finished Dakota Brown. The back of all signs must be painted or covered Dakota Brown.
SECTIONS 5 DOES NOT APPLY
6. ENERGY AND WATER CONSERVATION REQUIREMENTS.
6.5 Meters:
6.5.1 All new construction and all major renovations or additions to existing buildings shall include utility meters for each utility serving the building. Design and installation of all meters shall be capable of communicating with the Energy Management Control System (EMCS).
6.5.2 All utility meters shall comply with the EPACT 2005 requirements for advanced metering, be capable of 15 minute interval measurements, 30 days of internal parameter storage, and be 100% compatible with existing systems for remote collection of data. Recorded values for Electricity (kWh consumption, kW demand, kVAR reactive power, PF power factor), Natural Gas (cubic feet), Steam (klbs), Water (kgal). Memory for recording interval readings shall be ANSI C12.19 compliant. Meter shall provide time-stamped readings for every measured parameter.
6.5.3 The data shall be transmitted to the EMCS system in Building 593. All communication connections will be made by the Contractor to include all wiring, conduit, radios, and/or antennae required to support transmission of data to the EMCS server interface.
6.5.4 The EMCS integration shall include complete installation of all hardware, connection to system, and verification of pulse weight or meter multiplier. Each meter point shall record all relevant parameters with time-date stamp.
6.5.5 The Contractor must be required to perform a complete point-to-point test of the completed meter Installation. The test shall be conducted by validating the readings measured at the meter and those transmitted to and received by the EMCS server.
6.5.6 Questions regarding the AMS installation should be directed to the Base Utility Manager (Mr. Dave Abbott). He can be reached at (801) 777-5944.
6.5.7 Steam distribution and condensate lines shall be located above ground when possible. When the lines must be placed in an underground system, they should be installed in a utility trench.
6.5.8 AMR compatible gas meters and pressure regulators shall be installed for all new and renovated facilities or when gas service to existing facilities is installed, replaced, or upgraded and connected to the EMCS system. Meters shall be Dresser Roots rotary style meter or equivalent and meet the requirements of UFGS 33 51 13.00 30, Natural Gas Metering.
6.5.9 AMR compatible watt hour meters shall be installed on all facilities requiring new electric service or modifications to existing service and facility power requirements and connected to the EMCS system. Meter shall be a Shark 200 v2 or equivalent and meet the requirements of UFGS 26 27 13.10 30, Electric Meters.
6.5.10 AMR compatible water meters shall be provided for potable water entry/service points and base water well facilities.
SECTION 7 DOES NOT APPLY
8. PLUMBING:
8.1 Plumbing Design General:
Comply with UFC 3-420-01FA, Plumbing Systems. The International Plumbing Code and other Federal, State and local regulations pertaining to safe drinking water laws also apply where they are more stringent. A back-flow preventer shall be installed on all systems where cross contamination is possible, and before any industrial process plumbing except for non-potable water systems. Water lines shall be inside the buildings thermal envelope. Piping and drinking fountains shall not be placed in or on outside walls to prevent freezing. Avoid placement near outside air vent opening.
8.5 Clearance:
Provide sufficient space and access, 24 inches where possible, for maintenance of fixtures, valves, and piping.
8.7 Plumbing Basis of Design:
Address the following:
8.7.1 Design Criteria. Identify the governing codes and criteria, including federal and military handbooks, utilized for the design. Include the titles and the date of the latest edition or publication. References to codes and criteria should be made in the narratives of the Basis of Design.
8.7.2 Estimated Water Demand. Estimate the water demand in L/s (gpm) based on the type and number of fixtures required for each building.
8.7.3 Water Pressure. Indicate the minimum and maximum water pressure in kPa (psi) at each building. Indicate if booster pumping will be required.
8.7.4 Domestic Hot Water. Indicate the type, size and design water temperature of the domestic water heater and the distribution system. Indicate the extent of domestic hot water recirculation within the building. If shown economically feasible by life cycle cost analysis, state whether heat recovery will be utilized.
8.7.6 Backflow Prevention. Identify the systems and fixtures requiring backflow preventers.
9. FIRE PROTECTION:
9.1 Fire Suppression Systems:
9.1.1 All sprinkler systems shall be hydraulically designed. Pipe sizes, sprinkler locations, and data for hydraulic calculation sign shall be shown on the drawings.
9.1.2 The design shall be in compliance with Unified Facilities Criteria UFC 3-600-01, Fire Protection Engineering for Facilities, Engineering Technical Letter (AF ETL) 02-15; Fire Protection Engineering Criteria - Electronic Equipment Installations, AF ETL 01-18; Backflow Prevention Program; and National Fire Protection Association (NFPA 13) Installation of Sprinkler Systems.
9.1.3 The project specifications shall include a copy of the appropriate UFGS. The UFGS needs to be edited and modified, by the designer, to meet the specific local requirements found in this design guide.
9.1.4 All new dry/wet fire suppression systems connected to potable water supplies and using water only as a fire suppressant shall have an approved double check valve backflow preventer and test station. All new dry/wet fire suppression systems connected to potable water supplies and using water with antifreeze or other chemical as a fire suppressant shall have an approved reduced pressure principle backflow preventer and test station. Installation of a backflow preventer in a vertical position shall be approved by the by the State of Utah. Install valves and piping as needed to allow the backflow preventer to be forward flow tested (piping sized for sprinkler system demand flow) on a periodic basis. Piping shall be directed to the building exterior in an area where pavement exists to minimize erosion during flow testing. Piping at the exterior wall shall terminate with a threaded hose connection(s) and a threaded cap that has labeling to identify the port function as flow testing of the backflow assembly.
9.1.5 All aboveground sprinkler piping shall be Schedule 40 black steel pipe or Type “K” copper tubing. All trim on alarm valves will be Type “K” copper tubing only.
PART 1 - Delete two paragraphs and associated subparagraphs below if system designs have been approved by authorities having jurisdiction.
PART 2 - Revise first 20 subparagraphs below to suit authorities having jurisdiction. See Appendix A in NFPA 13 for recommended hazard classifications.
PART 3 - Revise paragraph below to indicate specific loads determined by Project's structural engineer or refer to loads indicated on Drawings. Model building codes and ASCE 7 establish criteria for buildings subject to earthquake motions. Verify requirements of authorities having jurisdiction.
PART 4 - Retain first paragraph below if procedures for welder certification are retained in "Quality Assurance" Article.
Coordinate subparagraph and list below with Part 2 "Manufacturers" Article. Retain "Available" for nonproprietary and delete for semi-proprietary specifications.
Coordinate below with Part 2 "Manufacturers" Article. Retain "Available" for nonproprietary and delete for semi-proprietary specifications.
9.1.6 All fire suppression control valves including post indicator valves (PIV’s) require tamper switches. Control valves associated with the riser shall be butterfly type with integral tamper switch; OS & Y type valves are not to be used at the riser. Fire suppression risers located in a suppression room having direct exterior access shall not have a PIV unless specifically required by code. Fire riser valves will work as control valves. Riser rooms that do not have a direct access exterior door, but are located adjacent to an exterior wall, shall use a wall mounted indicating valve if the wall will support it. PIVs shall only be used when the other options are not available.
PIVs shall only be used when the other options are not available
9.1.7 Each riser shall have a separate flow switch for each floor level and each riser.
9.1.8 Fire sprinkler piping shall be located in a heated area or in an insulated attic where temperatures are assumed not to drop below 40 degrees F.
9.1.10 Location of inspector test valves, as required by NFPA 13, shall be coordinated with the architectural requirements of the building including but not limited to concealed access boxes of adequate size with cover plates painted to match surroundings and located in a manner compatible with the architectural and furniture configuration of the building. Code required signage shall be provided. Additional piping and finishes on both the exterior and interior may be required. Details shall be coordinated through the shop drawing process. Wet-type sprinkler systems shall have the inspector test valves installed at the riser, downstream of the flow switch.
9.1.11 Fire Extinguishers shall only be installed when required by Air Force Instruction, National Fire Protection Association (NFPA) 101 Life Safety Code; Unified Facilities Criteria (UFC) or Engineering Technical Letter (ETL). If required, NFPA STD 10 will be enforced for spacing, height and location. Semi-recessed fire extinguisher cabinets are required for all required fire extinguishers except in Industrial, storage occupancies and were authorized by the fire department.
9.1.12 High Expansion Foam Generator systems require inspection or maintenance to be performed IAW UFC 3-601-02. Systems shall be equipped with platforms, walkways, or access ways as applicable to facilitate this requirement.
9.2 Water Supply:
9.2.1 Install a 5 inch Storz type adaptor and cap on the 4-1/2 inch steamer port of every new fire hydrant installed. Bollards are required to protect hydrants from vehicle and aircraft traffic.
9.2.2 Buried fire protection water service lines shall be buried at least 5 1/2-feet below grade.
9.3 Fire Alarm Detection System:
9.3.1 Fire Alarm system designs shall be in compliance with UFC 3-600-01, UFC 4-021-01, NFPA 72, AF ETL 01-18 & 02-15, ADA and this Base Facility Design Standard. The system designer shall be a certified NICET level III/IV. New fire alarm systems with less than 25 devices and appliances shall include an analysis per UFC 3-600-01, Para 1-4. A Fire Protection Engineer shall provide an analysis per UFC 3-600-01 Para 1-5 and shall sign and stamp construction/shop drawings when the new system includes 25 or more devices and appliances. Determination of required acoustically distinguishable spaces (ADS) shall be determined by this analysis and shall be approved by the fire department. Designs shall be submitted to the CE project manager for review by the 75th CES Electric/Electronic Shop and fire department prior to construction notice to proceed. The installation and programming shall be accomplished by a factory certified fire alarm system installer and be at least a NICET level II or higher.
9.3.2 All new systems shall use Class B initiating device circuits, signaling line circuits and notification circuits.
9.3.3 New systems shall be analog-intelligent only. Where a mass notification system is supervised and/or functions as the fire alarm occupant notification, the mass notification system shall be considered to be a part of the facility fire alarm system.
9.3.4 The contractor shall provide all new wiring, conduit, and devices. All devices and ancillary panels shall be monitored separately. All Fire Alarm conduit shall be properly identified by a continuous red coating or properly spaced labeling. Exposed fire alarm cable (rope) shall not be used.
9.3.5 Install relays and system controls for Monaco interface, maintenance bypass switches for Fan Shutdown, NAC, and SLC circuits were required. All devices and ancillary panels shall be monitored separately.
9.3.6 The contractor shall provide a lockable disconnecting means along with surge protection on all separate power circuits at or within a reasonable distance of the equipment that it services. The preferred Surge Protection model is Ditek DTK-120HW. Dedicated circuits are required and shall not be shared with other general purpose equipment.
9.3.7 Audio notification appliances shall have a 3 pulse temporal pattern (90-99dB), or voice speaker systems in accordance with NFPA 72. Visual notification appliances shall be capable of providing 75-100 candelas. All visual appliances in a single room shall be synchronized. The preferred method of installation is ceiling mount only.
9.3.8 Install addressable duct detectors with sample tubes, visual indicator lights and fan shutdowns “ONLY” were required per current Base, NFPA 72 and NFPA 90A guidelines. Detectors shall be resettable via the fire alarm panel. Remote test switches shall be installed if detectors are not readily accessible.
9.3.11 Provide digital and hard copies of panel programming, system installation drawings and O&M manuals to the Project Manager and 75th CES Electric/Electronic Shop upon final inspection. A hard copy set shall be placed at the FACP in an approved documentation cabinet. Provide also an additional 10% of devices used during project (minimum of 1 each type) for spare equipment.
9.4 Fire Alarm and Ancillary Control Panels:
9.4.1 Fire Alarm Control Panels, ancillary control panels and Monaco Transceivers will only be installed in dry, temperature controlled environments such as communications rooms or electrical rooms. Under no circumstances will they be installed in mechanical rooms with a chance of exposure to steam, condensation, etc.
The following Control Panels by distributor are approved for installation at Hill AFB:
· Fire Control Instruments (FCI) Model E3
· Siemens Model XLS
· Edwards Systems Technologies (EST) Model III
· Notifier Model NFS2-640
· Det-tronics Eagle Quantum Premier high expansion foam releasing panel
· Det-tronics X3301 triple IR flame detector
· Monaco BT2-8NBTransceiver
9.4.2 Panel and remote annunciator locations shall be coordinated with 75th CES Electric/Electronic Shop during site walk. All user accessible panels with pre-recorded messages and microphones shall have thumb latches vise a key lock.
9.5 Fire Alarm Reporting Systems:
9.5.1 The radio fire alarm transceiver shall be a Monaco BT2-8NB (16/32 zone) compatible with the existing Monaco D-21 Radio Fire Alarm Monitoring Systems. The transceivers shall operate on a frequency of 141.000 MHz for HAFB. The contractor shall provide and install a new antenna system per manufactures recommendations. Antenna location shall be approved by the 75th CES Electric/Electronic Shop. Request for Unit number and Position descriptors shall be routed thru 75th CES Electric/Electronic Shop for approval. The installed system must communicate to the appropriate central receiving station with zero faults for a minimum of 7 days before being accepted. At Hill AFB the Monaco D-21 central receiving stations are located in Bldg. 408 & Bldg. 1151.
SECTIONS 10 THRU 13 DO NOT APPLY
14. ELECTRICAL:
14.1 General:
14.1.1 Applicable Design Criteria: All installations shall comply with all applicable criteria including but not limited to UFC 3-501-01, Electrical Engineering which provides minimum requirements for design analyses and calculations, UFC 3-550-01 Exterior Electrical Power Distribution which provides minimum requirements for underground distribution system design (AF ETL 11-10: Electrical Manhole Design Considerations clarifies these requirements and provides additional recommendations), NFPA 70 National Electric Code (NEC), NFPA 70E Standard for Electrical Safety in the Work Place, and the Lineman’s and Cableman’s Handbook.
14.1.2 Coordination Requirements: Prior to the installation or modification of any existing exterior electrical service the system owner, City Light & Power (CLP), and75th CES Exterior Electrical shop shall be consulted. CLP will also be the authority having jurisdiction (AHJ) on all exterior/outdoor electrical installations. All temporary power will be run at the expense of the contractor that is performing the work. CLP will be notified by the project manager and a location will be determined. When required by the 75th Exterior Electrical section, bollards will be installed to protect exterior electrical services. It is recommended that prime contractor contract with CLP to construct transformers, switches, electrical lines, etc. that will be owned by them. If not constructed by CLP then the contractor will have to transfer the real property via the DD1354 to the Government. Furthermore, if the applicable utility is not constructed by the CLP then the contractor will have to pay for compliance inspections and other fees as required by the CLP.
14.2 Hill AFB Exterior Distribution:
14.2.1 Primary Voltage: The Primary voltage at Hill AFB is 12,470 volts.
14.2.2 Transformers: Shall comply with the following City Light & Power Requirements as follows:
14.2.3 High Voltage Conductors: All high voltage primary and secondary conductors will be copper only.
14.2.4 Buried High Voltage Cable: All buried high voltage cable (over 600 volts) shall be placed in conduit with a minimum of 3-inches of concrete encasing around the conduit. Depth of burial shall be 36 inches below grade. All high voltage conductor installations will be 36 inches deep minimum to the top of the conduit and they will be encased in concrete to include airfield runway lighting circuits. A 6-inch wide, red plastic marker tape with the words "Danger-Buried High Voltage Cable" shall be placed directly over the high voltage line at a depth of 12 inches below finished grade or 6 inches below the top of sub grade whichever is deeper. Any change of direction that is more than 5 degrees will require the installation of a manhole. Maximum spacing between manholes or equipment shall not exceed 500 feet.
14.2.5 Buried Conductors Below Traffic: All conduit containing conductors of any voltage including communication circuits that run under streets or parking lots shall be concrete encased 3 inches thick on all sides.
14.2.6 Only Rigid Galvanized Steel ( RGS) 90 degree elbows and Rigid Galvanized Steel (RGS) conduit or fiberglass sweeps for high voltage shall be used when making the transition from underground to overhead high voltage power lines. Only one high voltage riser in rigid galvanized steel per utility pole will be installed.
14.2.7 Support Structures: All power poles, steel support structures and their foundations shall be rated for a 100 mph wind load. The minimum dimensions for crossarms will be 8-ft long by 3 ¼-inchs wide by 4 ½-inches deep.
14.2.8 All new high voltage cable shall be 15 KV, 133 percent insulation, shielded, with E P insulation.
14.2.9 Watt-hour meters shall be installed on all facilities requiring new service and modifications to existing facility power requirements. AMR compatible watt hour meters shall be used and be connected to the EMCS system. Meter shall be a Shark 200 v2 or equivalent and meet the requirements of UFGS 26 27 13.10 30, Electric Meters and ASHRAE Standard 90.1.
14.2.10 Exterior equipment shall not be placed-near the drip lines of roof overhangs or rain gutters.
14.3 Hill AFB Interior Distribution: Do not use aluminum conductors or bus bars inside any facility at Hill AFB. Only copper conductors and bus bars should be used. All dry type transformers shall have copper windings.
14.3.1 All new building wiring systems shall be designed using 277/480 volts unless uneconomical to accomplish and shall be in rigid conduit or central open raceways.
14.3.2 Lighting shall be installed using 277 volts if available.
14.3.3 Do not use any polystyrene lenses in light fixtures.
14.3.4 Comply with federal energy requirements when designing lighting systems. See section 5 Mandatory Energy and Water Conservation Requirements above.
| 14.2.5 | In office buildings or other buildings that will have a considerable amount of computer equipment installed, or will have systems furniture: |
| a. | Run oversized neutral conductors from the transformer to service equipment, and from service equipment through the distribution panels to the branch circuit panels (double sized neutral conductors are recommended). |
| b. | From the branch circuit panel boards, run eight conductor circuits (three hot conductors, three neutral conductors one ground conductor, and one isolated ground conductor) to all receptacle outlets, including those receptacle outlets in pre-wired systems furniture. |
| c. | Run all other circuits as per the National Electric Code requirements. |
14.3.6 All installed electrical gear placed on mechanical room floors will be placed on a 4-inch tall concrete maintenance pad.
14.4 Exterior Lighting:
14.4.1 Light Poles: All light poles and foundations shall be rated for a 100 mph wind load.
14.4.2 Comply with federal energy requirements when designing lighting systems. See Section 6, Mandatory Energy and Water Conservation Requirements above. Use white LED lights for exterior lighting when economically viable.
14.4.3 Photoelectric Controls: Use photoelectric controls on exterior lighting where possible to save energy. Where practical fixtures shall be grouped together using contactors, which are controlled by a single photocell.
14.5 Interior Lighting:
14.5.1 Lighting power levels shall comply with ANSI/ASHRAE/IESNA Standard 90.1
14.5.2 Interior Lighting Calculations: Computer-generated photometric plans for each space are required to verify proposed luminaires and locations meet the required performance criteria of the design using a light loss factor (LLF) of 0.7. Photometric plan submittals must include:
· Horizontal illuminance measurements at workplane or other designated height above finished floor.
· Minimum and maximum illuminance levels.
· Average maintained illuminance level.
· Average to minimum and maximum to minimum ratios for horizontal illuminance
· Lighting power density (Watts per square foot or per square meter)
14.5.3 Use a color rendering index (CRI) of no less than 80 for interior applications.
14.5.4 Use a correlated color temperature (CCT) of no greater than 4100K as stated on the manufacturer’s cut sheet for all interior spaces.
14.5.5 Do not mix source CCTs within a single building with the purpose of minimizing maintenance staff from having to keep track of specific CCTs.
14.5.6 Daylighting Controls- Control the electric lighting in response to daylight.
· Continuously dim electric light in task oriented areas such as offices, conference rooms, classrooms, or turning it off in non-task areas such as circulation and lounge areas.
· Control primary and secondary daylight zones separately. Refer to Daylighting Best Practices in APPENDIX C of UFC 3-530 for additional information
14.6 Permitted Lighting Technology:
14.6.1 Solid State Lighting (SSL):
· LED luminaires must be dimmable or capable of multi-level control according to the control strategy.
· LED light source replacements (screw base) are only permitted for the replacement of incandescent or compact fluorescent light sources.
· IES LM-79, LM-80, and TM-21 testing reports must be supplied from manufacturer and include all relevant information.
· Consistent with industry standard, all LED luminaires require a 10-year warranty.
· Ballasts, Drivers, Generators and Power Supplies
· Total current harmonic distortion (THD) less than or equal to 20%.
· Power factor (PF) greater than or equal to 0.9
· For current and future dimming requirements (i.e. smart grid, curfew, adaptive), use dimmable or bi-level…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it.