USSF-SPOC Buckley 442 Utility (29 Apr 22).docx

DOCX document 25 KB Posted

Attached to
Power Conditioning and Continuation Interfacing Equipment RFP Federal contract opportunity
Solicitation number
FA821723R5000
Issued by
Department of the Air Force Materiel Command Lifecycle Management Center Hill Air Force Base

View the file

Other files for this federal contract opportunity

Other files attached to Power Conditioning and Continuation Interfacing Equipment RFP, newest first.
File Type Posted
01 Amendment.docx DOCX document
USSF-SPOC Buckley 444 (1 Apr 22).docx DOCX document
USSF-SPOC Buckley 731 (28 Oct 22).docx DOCX document
Additional Questions.xlsx XLSX spreadsheet
USSF-SPOC Buckley 1030 (19 Oct 22).docx DOCX document
USSF-SPOC Buckley 442 Tech (1 Apr 22).docx DOCX document
USSF-SPOC Buckley 433 (6 Oct 22).docx DOCX document
USSF-SPOC Buckley 1028 (21 Nov 22).docx DOCX document
USSF-SPOC Buckley 445 (1 Apr 22).docx DOCX document
00 Amendment.docx DOCX document
FA821723R5000_15June2023.pdf PDF
REVISED_PCCIE II_TEP Matrix_15June23_Final.xlsx XLSX spreadsheet
REVISED_PCCIE_PWS_15June23_Final.pdf PDF
REVISED_Section L_PCCIE 15June2023_Final.pdf PDF
EMPM Questions_PCCIE Answers.xlsx XLSX spreadsheet
CDRL-0015 Inventory Spare Part Kits.pdf PDF
CDRL-0022 EM Extended Repair Notice-Parts....pdf PDF
CDRL-0023 Extenuating Circumstances-Delay.pdf PDF
CDRL-0013 Plan of Action-Escalation Plan.pdf PDF
CDRL-0001 Associate Contractor Agreements.pdf PDF
CDRL-0020 Strength of Support Report.pdf PDF
CDRL-0004 Workers Health and Safety.pdf PDF
CDRL-0008-UPS Service Report.pdf PDF
CDRL-0017 Emergency Telephone Assist.pdf PDF
CDRL-0012 Service Reports and Delivery.pdf PDF
CDRL-0010-Program Management Reviews.pdf PDF
CDRL-0016-UPS Service Report.pdf PDF
CDRL-0005 Key Personnel.pdf PDF
CDRL-0007-Progress Status Internet Database.pdf PDF
CDRL-0002 Quality Control Program.pdf PDF
CDRL-0009-Monthly Conference Report.pdf PDF
CDRL-0025-Contractors status and managemnt report-PM.pdf PDF
CDRL-0027-Small Business Subcontracting Plan.pdf PDF
CDRL-0011 Emergency Telephone Number Identification.pdf PDF
CDRL-0006 Overseas and identified OCONUS Travel.pdf PDF
CDRL-0014 Contract Exit Criteria.pdf PDF
CDRL-0024 Repair and Sustainment Services.pdf PDF
CDRL-0026-Contractors status and managemnt report-EM.pdf PDF
CDRL-0019 Repair Proposal.pdf PDF
CDRL-0021 Summary of Repair Efforts.pdf PDF
CDRL-0018 EM Notification Content.pdf PDF
PCCIE_PWS_May 2023 Final.pdf PDF
Section L_PCCIE 20Dec2022.pdf PDF
Appendix C -SAFETY 05Aug22 Final.pdf PDF
SOFA Clause 2022.pdf PDF
FA821723R5000_15May2023.pdf PDF
PCCIE_QASP_02June2022_Final.pdf PDF
CDRL Package.pdf PDF
PCCIE II_TEP Matrix_04April23_Final.xlsx XLSX spreadsheet
Section M_PCCIE_20Dec2022.pdf PDF
Show all 50

Power Conditioning and Continuation Interfacing Equipment RFP has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USSF/SPOC Uninterruptible Power Supply (UPS) Site Information Sheet

29 April 2022
Buckley SFB, CO
Bldg. 442

1. POINTS OF CONTACT

Primary: Mr. Kevin Purdue
Alternate: Mr. Mitchell Cuthbert
Additional: Mr. Patrick Holder
Utilities Plant Supervisor
Utilities Plant Lead
Facilities Superintendent
Kevin.perdue.2@spaceforce.mil
Mitchell.cuthbert@spaceforce.mil
Patrick.holder.1@spaceforce.mil
(720) 847-5794/5; (720) 847-9893
(720) 847-6153 (720) 847-5794/5
(720) 847-9916
DSN 847-9916

24-Hour Work Center: Power Plant Control Room, (720) 847-5794/5, DSN 847-5794/5

SPOC POC: Mr. Aller Delarosa; aller.delarosa.1@spaceforce.mil; (719) 554-2906; DSN 692-2906

Security Management Office (SMO) Code:

Installation/Restricted Area/Facility Access Requirements: Contact Mr. Patrick Holder

2. ORGANIZATION, MISSION, & LOCATION

Organization: USSF; SPOC; Delta 4

UNCLASS Mission Supported by UPS: SBIRS (Utility Bus)
UPS Room #: 191
Street Address Where UPS is Located: 18079 E. Buttermilk Ave.
Battery Rm #: 193
Installation: Buckley SFB
State: CO
Zip: 80011
DoDAAC: F03000

3. UPS MODULE

Configuration: Two parallel redundant systems
Configuration/CTO #: 9PL13C0009C00R2
Manufacturer: Eaton
Series: 93PM
Model: 110-150
kVA: 130
kW: 130
Input/output Voltage: 480 / 480
System Load: ____ kVA

Module Serial #: 1. EK481UXX03 (3A) 2. EK481UXX02 (3B) 3. EK481UXX01 (4A) 4. EK474UXX01 (4B)

Date Manufactured: Nov 2016
Date Installed: 26 Jan 17
Caps Date Code:

4. ANCILLARY EQUIPMENT (i.e. Parallel Cabinet, Maintenance Bypass Cabinet, etc.)

Manufacturer:
Type:
Serial #:
Type:
Serial #
Eaton
Parallel Cabinet (3AB)
No Serial Number
Maintenance Bypass 3
No Serial Number
Eaton
Parallel Cabinet (4AB)
No Serial Number
Maintenance Bypass 4
No Serial Number
Square D
Manual Hot Tie (3,4)
No Serial Number
Remote Monitor: Yes, Ctrl. Rm; Sense a Phone
Emergency Power Off: No
Spares Kit: Yes

5. BATTERIES

Configuration: (2) strings per S/N, (8) strings total; (40) jars in series per string; (320) total jars

Manufacturer: Enersys
Series: DataSafe
Model: 12HX300FR
Watts/Cell: 284
Type (Flooded/Sealed): Sealed
# Volts per Cell/Jar: 2 / 12
DC Float: 540 VDC
# Strings / Unit: 2
# Jars / String: 40
# Cells / Jar: 6
# Jars / Unit: 80
Total Jars / System: 320
Date Code: 0222
Date Installed: 27 Apr 22
Installed By: Pergravis
Warranty: 3 years
Battery Monitor: No
Spare Batteries: No

6. PREVENTIVE MAINTENANCE DUE

Modules, integral equipment, and sealed batteries are semi-annual (every 6 mos.); flooded batteries are quarterly (every 3 mos.)

7. ADDITIONAL DATA

Laptop Computer Permitted in UPS Room: Yes (Submit attached Laptop Authorization Letter, Wi-Fi deactivated)

Mobile Telephones Permitted in UPS Room: No (Not permitted in Restricted Area)