Additional Questions.xlsx
XLSX spreadsheet 77 KB Posted
- Attached to
- Power Conditioning and Continuation Interfacing Equipment RFP Federal contract opportunity
- Solicitation number
- FA821723R5000
View the file
Other files for this federal contract opportunity
Show all 50
Power Conditioning and Continuation Interfacing Equipment RFP has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Question No. | RFP Attachment | Section | QUESTION FOR SUBMISSION | |
| 1 | REVISED_Cross+Reference+Matrix_PCCIE_2023 | Contract Documentation | Please confirm that the items listed under the "Contract Documentation" section should be acknowledged as received by offerors, but that we are not to submit these items with our proposal. | Contractor does not need to submit back the Contract Documentation on the Cross Reference Matrix |
| 2 | PWS | Contract Clauses, pg 19 of 52 | Considering that not all repair / replacement parts and/or batteries may be BAA or TAA compliant, and since there is a 30 day repair or replenishments requirement in the PWS, will there be an accelerated process for obtaining waivers from BAA/TAA when those instances arise? | This will be addressed on a case-by-case basis |
| 3 | PWS | 12.3.3 | Root Cause Analysis (RCA) is the process of discovering the root causes of problems in order to identify appropriate solutions. RCA assumes that it is much more effective to systematically prevent and solve for underlying issues rather than just treating the evident problem or symptom. Root cause analysis can be performed with a collection of principles, techniques, and methodologies that can all be leveraged to identify the root causes of an event or trend. Looking beyond superficial cause and effect, RCA can show where processes or systems failed or caused an issue in the first place. Unless obvious external issues are the cause this may require an indepth review of trend analysis of events leading up to, at the point of an event and the time that followed to properly diagnose the true Root Cause. PWS 12.3.3 (g.) requires a one sentence summary of the failure's root cause. Can you please clarify this requirement is for a short summary of the work performed and the technician's suspected Root Cause for the failure and not a complete RCA? | Root Cause is in Section 12.4.3 i. |
We corrected the PWS to state. A summary of the failure's etc….
| 4 | PWS | 15.7.d | Please confirm that per PWS 15.7.d, if the PM visit requires the UPS to go into bypass, the contractor shall communicate with the site POC that a government employee will place the UPS into bypass mode prior to the technician arriving to the site. It is our assumption that the DOD customer does not have any experience or knowledge in the area and shall not have that duty placed upon them. | The PWS was updated to state: a. | The contractor shall manipulate the switchgear and they will not be held liable for any downstream damage assuming correct procedures are followed. The contractor may require the site to fill out a release of liability form for any downstream equipment damage. Regardless of who manipulates the switchgear, there is risk of damage to critical equipment downstream. There is no increase in risk regarding who performs the switchgear manipulation, however, it is a risk that we as the government must assume. |
| 5 | Section L | C.2.4 | Can you provide the make, model and quantity for all connected batteries in the awarded task section of the PWS? Without this information, we will have to make assumptions, such as Quantity, make, model and process for completing the response. | Will attach site sheets | |
| 6 | Section L | C.2.4 | Can the serial, model #'s, and Quantity be provided for all Auxiliary / Ancillary equipment in the awardable task section of the PWS? Without this information, we will have to make assumptions, such as Quantity, make, model and process for completing the response. | Will attach site sheets |
SOLICITATION NO. N40084-12-R-6500 PROJECT TITLE/LOCATION: GOVERNMENT PRE PROPOSAL INQUIRY FORM