This document is a special provisions section detailing requirements for working on or near the airfield at Tinker Air Force Base. The document outlines critical safety, access, and operational guidelines for contractors performing work within active airfield areas, clear zones, and primary surfaces. Key requirements include:

Contractors must submit detailed written requests for runway/taxiway closures at least 45 calendar days in advance, specifying work details, equipment, personnel, and duration. Strict safety protocols are mandated, such as maintaining a clean work site, preventing foreign object debris (FOD), using approved low-intensity amber flashing lights on vehicles, and obtaining control tower clearance before crossing active runways. Personnel must wear hearing protection due to high noise levels, and contractors must be prepared to immediately evacuate work areas during aircraft emergencies. Height restrictions are imposed, requiring government approval for any temporary structures or equipment exceeding 12 feet near runways or 50 feet elsewhere on the base.

View the file

Other files

File Type Posted
Solicitation Amendment FA813725R00350006 SF 30.pdf PDF
Capsol LED Text Displays - Capsol.pdf PDF
WWYK190068_RFI_23-24-25 SEP24.pdf PDF
RFI 26 zl1d.pdf_safe.pdf PDF
RFI 26 Fixture with Joist.pdf PDF
190068_Attch04_Revised_Design_Analysis.pdf PDF
190068_PreBid RFI GOVT RESPONSE.pdf PDF
190068_TAFB_IFC_FINAL_SPECIFICATIONS.pdf PDF
190068_DD100_Appendix B.pdf PDF
190068_IFC_Design Analysis_Final.pdf PDF
190068_DD100_Appendix A.pdf PDF
Solicitation - FA813725R0035 for WWYK190068.pdf PDF
01 33 00.pdf PDF
01 32 16.00 20.pdf PDF
00 80 00.pdf PDF
ERDCITL_TR12-1_r2.pdf PDF
EM_385-1-1.pdf PDF
dafi21-101_afmcsup_afmcgm2023-01.pdf PDF
dafi13-213.pdf PDF
afman40-201.pdf PDF
afman91-203_oc-alcsup.pdf PDF
afi48-104.pdf PDF
Staging Request Form.pdf PDF
EAL Template.pdf PDF
007200_Attch14_Information for New Boilers.pdf PDF
007200_Attch7b_Monthly Hazardous Usage Report.pdf PDF
007000_Attch1_TAFB Outage Request Form.pdf PDF
EMS General Awareness Training for Contractors Aug 2018 PDF.pdf PDF
00 70 00.pdf PDF
tinkerafb_INRMP.pdf PDF
dafman91-203.pdf PDF
ufc_3_260_04_2018.pdf PDF
afi91-202_afmcsup.pdf PDF
ufc_3_601_02_2021.pdf PDF
dafi91-202.pdf PDF
tinkerafbi21-100.pdf PDF
tinkerafb_INRMP_App E.pdf PDF
017800_Attch1_DD1354.pdf PDF
00 72 00.pdf PDF
00 71 00.pdf PDF
01 78 00.pdf PDF
01 45 00.00 10.pdf PDF
01 78 23.pdf PDF
000_TABLE OF CONTENTS.pdf PDF
ERDCITL_TR12-6_r6.pdf PDF
WWYK190068 Canceled SiteVisit Signin 12JUN25.pdf PDF
190068_ATT11_Revised_Drawings.pdf PDF
190068_ATT10_Submittal_Register.pdf PDF
190068_ATT9_SOW.pdf PDF
EAL List - 190068.xlsx XLSX spreadsheet
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Tinker AFB Tinker General Requirements

SECTION 00 80 05

SPECIAL PROVISIONS FOR WORKING ON OR NEAR THE AIRFIELD ON TINKER AFB

PART 1 GENERAL

The following provisions shall apply when work is required to take place on the active airfield, within the clear zones, or in the primary surfaces as defined by Unified Facilities Criteria 3- 260-1, Airfield and Heliport Planning and Design.

1.1 CLOSURES

a. All runway and taxiway closures require coordination and scheduling with Base Operations. Written requests for closures shall be submitted to the Contracting Officer no less than 45 calendar days prior to the requested date of closure. The request shall include:

1. The nomenclature of the runway/taxiway to be closed

2. The area of the runway/taxiway where the work is to take place

3. The requested date of closure

4. The estimated duration of closure

5. A detailed description of the work to be performed

6. A list of the equipment required to perform the work

7. An estimate of the personnel required to perform the work

b. The Contracting Officer shall coordinate with Base Ops to close the requested runway/taxiway on or as close as possible to the date requested and for the length of time requested. The Contracting Officer shall notify the contractor, in writing, of the date and length of time approved for closure.

c. It is the responsibility of the contractor to have the necessary personnel, materials, and equipment ready to start work on the approved date of closure and to complete the work in the time requested. Under most circumstances, Base Operations will be unable to adjust flight and runway/taxiway utilization schedules to accommodate extensions to closures.

d. The contractor shall notify the Contracting Officer, in writing, when the work on the closed runway/taxiway is complete.

1.2 SAFETY

1.2.1 Personnel

The contractor shall provide all of his personnel ear plugs and/or ear muffs to prevent injury to their auditory systems while working on the Airfield. Jet aircraft operating on the runways, taxiways, and aprons make these areas zones of high-level noise. The government will not be held liable for auditory system damage due to non or improper use of noise protection equipment.

This requirement is in addition to the contractor providing his personnel with safety equipment required by OSHA for the work to be performed.

January 2022 Page 1 Section 00 80 05

1.2.2 Aircraft

The contractor shall maintain a clean work site and shall implement all measures necessary to insure that material and equipment do not interfere with or damage aircraft operating or parked in areas of the airfield that are not closed. NO FOD.

1.3 ACCESS RESTRICTIONS

No unescorted contractor vehicles, equipment, or personnel shall be on or cross any active runway or taxiway unless clearance is requested from, and granted by, the control tower. All contractor vehicles and mechanized equipment operating on the landing areas (the first 1,000 feet from either end of the runway) will be identified by approved, mounted, low intensity, amber flashing lights. When contractor operations require repeated vehicle or personnel crossing of an active runway, taxiway, or other controlled area, a two-way radio, furnished by the Government, will be used to maintain contact with the control tower. Use of the radio for other purposes will be strictly prohibited. The radio will be returned to the Government at the end of each workday, and will be reacquired as necessary.

1.4 HEIGHT RESTRICTIONS

The construction of any temporary structure or the use of any equipment that extends more than 12 feet above the ground within 1000 feet of a runway or that extends 50 feet above the ground elsewhere on Tinker AFB shall be approved by the Government prior to installation or use. Written request for approval shall be submitted to the Contracting Officer no later than 21 calendar days prior to the date needed.

1.5 CLEANLINESS

The contractor shall maintain the cleanliness of his work site and all traversed runways, taxiways, aprons, and ramps at all times. He shall utilize methods and equipment to prevent spilling or dropping materials in these areas and shall utilize whatever method or equipment necessary to insure the removal of loose materials from these areas. The contractor shall remove all material and equipment to his staging area at the end of each work day. No material is to be stockpiled nor equipment stored within 1000 feet of the centerline of a runway.

1.6 EMERGENCIES

1.6.1 Evacuation Area

On the first day of work on the airfield, the contractor, a representative of the Contracting Officer, and a representative of Base Ops shall identify an area a safe distance from the runway where the contractor is to move his personnel and equipment during an aircraft emergency.

1.6.2 Evacuation

During an aircraft emergency, the contractor shall vacate the work site.

He shall move all personnel and equipment to the designated evacuation area. Evacuation orders will be given on short notice and will require expeditious action by the contractor.

January 2022 Page 2 Section 00 80 05

1.7 INSPECTION AND CLEANING

The contractor shall maintain, on site and in good working order, equipment capable of cleaning loose materials from the runway, taxiway, ramp, or apron. The contractor, accompanied by a Government representative, may be required to inspect the entire length of the runway and taxiway to insure that all personnel, debris, material, equipment, and tools have been removed from these areas.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

January 2022 Page 3 Section 00 80 05