DRAFT ITO Attachment 1.6- (NTE Coefficient Pricing Matrix)
View the file
Other files for this federal contract opportunity
Show all 50
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| ITO Attachment 1.6- NTE Coefficient Pricing Matrix | ||||
| Basic Year | ||||
| Item No. | Average Annual Cost | NTE Coefficient | Extended Price | |
| A0001 | Normal Work Hours | $ 14,000,000.00 | $ - 0 | |
| A0002 | Other than Normal Work Hours | $ 4,000,000.00 | $ - 0 | |
| A0003 | Emergency/Time Critical | $ 1,500,000.00 | $ - 0 | |
| A0004 | Shutdown of operations pull off when working in aircraft movement areas | $ 1,500,000.00 | $ - 0 | |
| A0005 | Architechture-Engineering | $ 750,000.00 | $ - 0 | |
| Estimated Evaluated Price for Basic Year: | $ - 0 | |||
| Option Year I | ||||
| Item No. | Average Annual Cost | NTE Coefficient | Extended Price | |
| A0101 | Normal Work Hours | $ 14,000,000.00 | $ - 0 | |
| A0102 | Other than Normal Work Hours | $ 4,000,000.00 | $ - 0 | |
| A0103 | Emergency/Time Critical | $ 1,500,000.00 | $ - 0 | |
| A0104 | Shutdown of operations pull off when working in aircraft movement areas | $ 2,000,000.00 | $ - 0 | |
| A0105 | Architechture-Engineering | $ 750,000.00 | $ - 0 | |
| Estimated Evaluated Price for OptionYear I: | $ - 0 | |||
| Option Year II | ||||
| Item No. | Average Annual Cost | NTE Coefficient | Extended Price | |
| A0201 | Normal Work Hours | $ 14,000,000.00 | $ - 0 | |
| A0202 | Other than Normal Work Hours | $ 4,000,000.00 | $ - 0 | |
| A0203 | Emergency/Time Critical | $ 1,500,000.00 | $ - 0 | |
| A0204 | Shutdown of operations pull off when working in aircraft movement areas | $ 1,500,000.00 | $ - 0 | |
| A0205 | Architechture-Engineering | $ 750,000.00 | $ - 0 | |
| Estimated Evaluated Price for OptionYear II: | $ - 0 | |||
| Option Year III | ||||
| Item No. | Average Annual Cost | NTE Coefficient | Extended Price | |
| A0301 | Normal Work Hours | $ 14,000,000.00 | $ - 0 | |
| A0302 | Other than Normal Work Hours | $ 4,000,000.00 | $ - 0 | |
| A0303 | Emergency/Time Critical | $ 1,500,000.00 | $ - 0 | |
| A0304 | Shutdown of operations pull off when working in aircraft movement areas | $ 1,500,000.00 | $ - 0 | |
| A0305 | Architechture-Engineering | $ 750,000.00 | $ - 0 | |
| Estimated Evaluated Price for OptionYear III: | $ - 0 |
| Extension of Services (6mo) | ||||
| Item No. | Average Annual Cost | NTE Coefficient | Extended Price | |
| A0301 | Normal Work Hours | $ 7,000,000.00 | 0.000 | $ - 0 |
| A0302 | Other than Normal Work Hours | $ 2,000,000.00 | 0.000 | $ - 0 |
| A0303 | Emergency/Time Critical | $ 750,000.00 | 0.000 | $ - 0 |
| A0304 | Shutdown of operations pull off when working in aircraft movement areas | $ 750,000.00 | 0.00 | $ - 0 |
| A0305 | Architechture-Engineering | $ 375,000.00 | 0.00 | $ - 0 |
| Estimated Evaluated Price for Extension of Services: | $ - 0 | |||
| Note: Extension of Services NTE Coefficinet must remain the same as Option Year III IAW FAR 52.217-8 | ||||
| PROPOSAL SUMMARRY | ||||
| Basic Year | $ - 0 | |||
| Option Year I | $ - 0 | |||
| Option Year II | $ - 0 | |||
| Option Year IIII | $ - 0 | |||
| Extension of Services | $ - 0 | |||
| TOTAL EVALUATED PRICE | $ - 0 | |||
| Printed Name/Title:___________________________________________________ | ||||
| Signature:____________________________________________________________ | ||||
| Note: By signing this document I acknowledge that the coefficients proposed are | ||||
| inclusive of all cost elements in Statement of Work para. 1.8.4.10 |