Attach_5_L-2_PPQ.docx

DOCX document 34 KB Posted

Attached to
25 AF DCGS IDIQ Federal contract opportunity
Solicitation number
FA7037-15-R-0001
Issued by
Department of the Air Force Air Combat Command

About this file

Attach 5 L-2 PPQ

View the file

Other files for this federal contract opportunity

Other files attached to 25 AF DCGS IDIQ, newest first.
File Type Posted
Solicitation_Amend_06_Released.pdf PDF
Attach_11_L-7_DCGS_Cost_Model_REV_02Apr15.xls XLS spreadsheet
Solicitation_Amend_06.pdf PDF
Solicitation_Amendment_05.pdf PDF
Solicitation_Amendment_04.pdf PDF
Attach_11_L-7_DCGS_Cost_Model_REV_30Mar15B.xls XLS spreadsheet
Solicitation_Amendment_03.pdf PDF
Attach_11_L-7_DCGS_Cost_Model_REV_27Mar15.xls XLS spreadsheet
Solicitation_Amend_02.pdf PDF
Attach_11_L-7_DCGS_Cost_Model_REV_25Mar15.xls XLS spreadsheet
Attach_10_L-6b_Sample_TO_Pricing_Sheet_REV_25Mar15.xls XLS spreadsheet
Solicitation_Q As.pdf PDF
Attach_11_L-7_DCGS_Cost_Model_REV_11Mar15.xls XLS spreadsheet
Attach_2-PWS_Appendix_A_Job_Desc_REV_11Mar15.xls XLS spreadsheet
Attach_3-PWS_Appendix_B_Mission_Essential_Personnel_REV_11Mar15.pdf PDF
Attach_7_L-4_Consent_Form_REV_11Mar2015.pdf PDF
Attach_13_L-9_Risk_Assessment_Template.pdf PDF
Attach_9_L-6a_DCGS_Sample_TO_REV_11Mar15.pdf PDF
Attach_1-DCGS_PWS_REV_11Mar15.pdf PDF
Amendment_01.pdf PDF
Attach_12_L-8_Matrix_REV_11Mar15.pdf PDF
Attach_10_L-6b_Sample_TO_Pricing_Sheet_REV_11Mar15.xls XLS spreadsheet
Attach_6_L-3_PPQ_Cover_Sheet.docx DOCX document
Attach_1-PWS.pdf PDF
Exhibit_B-DD254.pdf PDF
Attach_7_L-4_Consent_Form.doc DOC document
Attach_11_L-7_DCGS_Cost_Model.xls XLS spreadsheet
Attach_2-PWS_Appendix_A_Job_Desc_9Dec14.xlsx XLSX spreadsheet
Attach_12_L-8_Matrix_REV_7Jan15.docx DOCX document
Attach_10_L-6b_Sample_TO_Pricing_Sheet.xlsx.xls XLS spreadsheet
Attach_3-PWS_Appendix_B_Mission_Essential_Personnel.pdf PDF
Attach_8_L-5_Client_Author.docx DOCX document
Exhibit_A-CDRL.pdf PDF
Attach_4_L-1_PP_Info_Sheet.docx DOCX document
FA7037-15-R-0001_Solicitation.pdf PDF
Attach_9_L-6a_DCGS_Sample_TO.pdf PDF
Draft_Docs_Q A.pdf PDF
Attach_L-3_PPQ_Cover_Sheet_07Oct14.docx DOCX document
Attach_L-2_PPQ_26Mar2014.docx DOCX document
Attach_L-8_Matrix.docx DOCX document
Attach_L-6a_DCGS_Sample_TO.pdf PDF
Attach_L-1_PP_Info_Sheet.pdf PDF
Attach_3-Sect_L.pdf PDF
Attach_L-5_Client_Author_26Mar2014.docx DOCX document
Attach_L-7_DCGS_Cost_Model_REV_19Sep14.xls XLS spreadsheet
Attach_1b-PWS_Appendix_A_Job_Desc.pdf PDF
Attach_4-Sect_M.pdf PDF
Attach_1-DCGS_PWS.pdf PDF
Attach_L-6b_DCGS_Sample_TO_Pricing_Sheet_219Sep14.xlsx.xls XLS spreadsheet
Attach_L-4_Consent_Form_26Mar2014.doc DOC document
Show all 50

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA7037-15-R-0001

Attachment L-2

Instructions for Sending Past Performance Questionnaire Forms

Offeror shall prepare and send a reference questionnaire package for each customer listed on the Previous Contracts List. It is the Offeror’s responsibility to follow-up and to encourage their references to send in their questionnaire. It is suggested that Offerors send their identified customer points of contact a Client Authorization letter requesting that past performance information be provided directly to the Contracting Officer. Each questionnaire package should contain the following.

· Client Authorization Letter Concerning Offeror Performance

· Past Performance Questionnaire Form

· Complete Part 1 (to be completed by firm requesting reference) of each Questionnaire before sending it to the individual who will be providing the reference

OFFEROR SHOULD DELETE THESE INSTRUCTIONS BEFORE SENDING OUT QUESTIONNAIRES

PAST PERFORMANCE QUESTIONNAIRE FORM

SECTION 1: OFFEROR INFORMATION (completed by the Offeror requesting evaluation prior to mailing)

Offeror’s name and address:

Point of Contact:

Phone Number

Contract Number:

Project Title/Description of Work performed under this project:

Contract Type
|_| Firm Fixed Price

|_| Cost Reimbursement

Project Award Date:

Schedule Completion Date:

Current/Final Completion Date:

Project Award Amount:

Current/Final Project Amount:

Contractor being evaluated performed as the
|_| Prime Contractor

|_| Sub-contractor

(Signature)

(Name and Title of Authorized Official)

(Date)

SECTION 2: RESPONDENT INFORMATION (completed by Respondent)

The questionnaire may be filled out electronically or by hand and emailed to Ms. Yvonne Camarce at yvonne.camarce@us.af.mil. For questions, you may call Ms. Camarce at 210-977-2038 (DSN 969-2038).

EVALUATED BY:

(Signature)

(Date)

(Typed or Printed Name)

(Title)

(Phone Number Commercial/DSN)

SECTION 3: PERFORMANCE INFORMATION: Choose the number on the scale of 1 to 5 (or N/A) that most accurately describes the Contractor’s performance or situation. For the “Customer Satisfaction” section only, please provide a narrative explanation for any ratings of 1, 2, and 5.

(5) Exceptional
Performance meets contractual requirements and exceeds many to the Government/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with few minor problems for which corrective actions taken by the contractor was highly effective
An Exceptional rating is appropriate when the Contractor successfully performed multiple significant events that were of benefit to the Government/Owner. A singular benefit, however, could be of such magnitude that it alone constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified
(4) Very Good
Performance meets contractual requirements and exceeds some to the Government’s/Owner’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective
A Very Good rating is appropriate when the Contractor successfully performed a significant event that was a benefit to the Government/Owner. There should have been no significant weaknesses identified
(3) Satisfactory
Performance meets minimum contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
A Satisfactory rating is appropriate when there were only minor problems, or major problems that the contractor recovered from without impact to the contract. There should have been NO significant weaknesses identified Per DOD policy, a fundamental principle of assigning ratings is that contractors will not be assessed a rating lower than Satisfactory solely for not performing beyond the requirements of the contract.
(2) Marginal
Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions. The contractor's proposed actions appear only marginally effective or were not fully implemented
A Marginal is appropriate when a significant event occurred that the contractor had trouble overcoming which impacted the Government/Owner.
(1) Unsatisfactory
Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains serious problem(s) for which the contractor's corrective actions appear or were ineffective
An Unsatisfactory rating is appropriate when multiple significant events occurred that the contractor had trouble overcoming and which impacted the Government/Owner. A singular problem, however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating.
(N/A) Not Applicable
No information or did not apply to your contract
Rating will be neither positive nor negative

1. CUSTOMER SATISFACTION

(For this section, please provide a narrative explanation for any ratings of 1, 2, and 5)

Provide an overall rating for the work performed by this contractor.
1
2
3
4
5
N/A
Customer would have no reservations in awarding another contract to the Contractor.
1
2
3
4
5
N/A

2. QUALITY

Quality of technical data/report preparation efforts (CDRLs)
1
2
3
4
5
N/A
Ability to meet quality standards specified for technical performance
1
2
3
4
5
N/A
Timeliness/effectiveness of contract problem resolution without extensive customer guidance
1
2
3
4
5
N/A

3. TIMELINESS

Contractor adhered to/met established schedules to complete projects/tasks on time
1
2
3
4
5
N/A
Contractor provided adhered to/timely cost/design proposals.
1
2
3
4
5
N/A
Contractor provided on-time CDRLs as required
1
2
3
4
5
N/A

4. RESPONSIVENESS

Contractor acted promptly to resolve problems, ensuring compliance with contract requirements and safety regulations.
1
2
3
4
5
N/A
Contractor was reasonable and cooperated to resolve problems, attended meetings as needed and maintained communication with the government to keep projects/tasks on schedule.
1
2
3
4
5
N/A

5. MANAGEMENT/ PERSONNEL/LABOR

(For this section, please provide a narrative explanation for any ratings of 1, 2, and 5)

Effectiveness of on-site management, including management of subcontractors and/or labor force
1
2
3
4
5
N/A
Ability to meet minimum hire requirements for TS/SCI cleared personnel at start of contract
1
2
3
4
5
N/A
Ability to retain experienced personnel with the required TS/SCI clearances in order to maintain continuity of critical positions to ensure contract performance
1
2
3
4
5
N/A
Ability to retain experienced personnel with the required Counter Intelligence (CI) Polygraph in order to maintain continuity of critical positions to ensure contract performance
1
2
3
4
5
N/A
Ability to minimize employee turnover/absences with personnel that meet requirements and clearance levels upon start of work.
1
2
3
4
5
N/A
Knowledge/expertise demonstrated by contractor personnel
1
2
3
4
5
N/A
Effectiveness of overall management (including ability to effectively lead, manage and control the program)
1
2
3
4
5
N/A

6. COST/FINANCIAL MANAGEMENT

Contractor was timely and accurate in submitting monthly invoices with appropriate back-up documentation, monthly status reports/budget variance reports, compliance with established budgets and avoidance of significant and/or unexplained variances (under runs or overruns)
1
2
3
4
5
N/A

7. GENERAL

Ability to successfully respond to emergency and/or surge situations (including notifying COR, PM or Contracting Officer in a timely manner regarding urgent contractual issues).
1
2
3
4
5
N/A
Compliance with contractual terms/provisions (explain any specific issues in the Remarks section)
Yes
No

8. SECURITY COMPLIANCE

Ability to follow Government mandated security governances and guidance (explain any specific issues in the Remarks section)
1
2
3
4
5
N/A
Ability to mitigate security incidents
1
2
3
4
5
N/A

SECTION 4: NARRATIVE SUMMARY:

1. What were the Contractor’s greatest strengths in the performance of the contract? (response is not limited to area provided)

2. What were the Contractor’s greatest weaknesses in the performance of the contract? (response is not limited to area provided)

3. Please provide any additional comment concerning the Contractor’s performance (response is not limited to area provided)

4. GOVERNMENT CONTRACTS ONLY: Has or was this contract partially or completely terminated for default or convenience, or is there any pending termination?

|_| Yes |_| No |_| Default |_| Convenience |_| Pending Termination

If yes, please explain.

5. Were there any performance issues regarding the Contractor’s work? If yes, please explain.

REMARKS:

File details come from the government source that posted it. Updated .