FA6656-08-R0004 Amd 0002.doc

DOC document 69 KB Posted

Attached to
Modify/Upgrade Industrial Wastewater Pretreatment System, Bldg 309 Federal contract opportunity
Solicitation number
FA6656-08-R-0004
Issued by
Department of the Air Force Reserve Command

About this file

FA6656-08-R0004 Amendment 0002

View the file

Other files for this federal contract opportunity

Other files attached to Modify/Upgrade Industrial Wastewater Pretreatment System, Bldg 309, newest first.
File Type Posted
Q A as of 22 July 2009 B502.doc DOC document
RESPONSE TO CONTRACTOR QUESTIONS-Computer Interface Requirements.docx DOCX document
FA6656-08-R0004Prime SubsList- 13Aug 08.rtf RTF text file
FA6656-08-R0004Prime SubsList- 12Aug 08.rtf RTF text file
RESPONSE TO CONTRACTOR QUESTION-HMI SCREENS.docx DOCX document
FA6656-08-R0004 Amd 0003.doc DOC document
FA6656-08-R0004Prime SubsList- 8Aug 08.rtf RTF text file
RESPONSES TO CONTRACTOR QUESTIONS-Site Visit.docx DOCX document
26 of 27-E4 Rev Electrical Site Plan B-309-Paper.pdf PDF
FA6656-08-R0004 Amd 0002 Atch 1 - Responsibility Questionnaire.doc DOC document
24 of 27-E2 Rev Electrical Power Lighting Plan-Paper.pdf PDF
site visit minutes.doc DOC document
RESPONSES TO CONTRACTOR QUESTIONS AS OF 7AUG 08.doc DOC document
RESPONSES TO CONTRACTOR QUESTIONS AS OF 4 AUG 08.docx DOCX document
SITEVISITINFOPOSTING.doc DOC document
18 of 27-M4 Deicing Manhole Site Plan.pdf PDF
14 of 27-P1 Plumbing Plan.pdf PDF
3 of 27-C2 Site Utility Plan.pdf PDF
27 of 27-E5 Elec Site Plan-Fire Training Facility.pdf PDF
17 of 27-M3 Carbon Tank Repair Coating Details.pdf PDF
FA6656-08-R0004 Atch 2 Specifications.doc DOC document
15 of 27-M1 Mechanical Plan.pdf PDF
11 of 27-S2 Roof Framing Plan Details.pdf PDF
21 of 27-M7 Flow Sensor-Monitor Modification.pdf PDF
16 of 27-M2 P I Diagram.pdf PDF
Attachment 4 - PastPerformanceQuestionnaire.doc DOC document
1 of 27-G1 Title Page.pdf PDF
8 of 27-A3 Sections and Details.pdf PDF
silt fence-002.tif TIF image
24 of 27-E2 Electrical Power Lighting Plan.pdf PDF
22 of 27-FP1 Fire Prot Plan.pdf PDF
2 of 27-C1 Demo Plan.pdf PDF
4 of 27-C3 Grading Plan.pdf PDF
25 of 27-E3 Fire Det Plan.pdf PDF
13 of 27-S4 Frame Sections and Details.pdf PDF
20 of 27-M6 Fire Training Deicing Manhole Site Plan.pdf PDF
23 of 27-E1 Electrical Legend Fixture Sch one Line Diagram.pdf PDF
12 of 27-S3 Foundation Section Detail.pdf PDF
5 of 27-C4 Details.pdf PDF
FA6656-08-R0004.doc DOC document
26 of 27-E4 Electrical Site Plan-B309.pdf PDF
19 of 27-M5 Deicing Collection Sys Details.pdf PDF
7 of 27-A2 Exterior Interior Elevations.pdf PDF
10 of 27-S1 Foundation Plan Detail.pdf PDF
FA6656-08-R0004 Atch 1 Gen Dec Mod 6.doc DOC document
6 of 27-A1 Flr Roof Reflected Ceiling Plans.pdf PDF
silt fence-001.tif TIF image
9 of 27-A4 Schedules and Details.pdf PDF
Show all 48

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

f

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

a. SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS – Add the following attachment to the list of Documents, Exhibits and Other Attachments :

“Attachment 5 – FINANCIAL INSTITUTION REFERENCE SHEET” ( Amd 002, Atch 1)

b. SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS – Paragraph L-003,2.b.(1)(d) - Change to read as follows: “Financial Resources: Offerors shall submit a financial capability letter from their financial institution (Atch 5), and a letter from the bonding company confirming bonding capability and maximum dollar threshold. This letter will be used in the Contracting Officer’s determination of responsibility.”

c. SECTION M – EVALUTION FACTORS FOR AWARD – 1.) Paragraph M-002.2.a – Change to read as follows: “Current contracts or subcontract completed within the past three (3) years will be considered RECENT. RELEVANT contracts are contracts of similar size and complexity and have a logical connection with the work being acquired, whether or not it was government work or commercial work. The following relevancy definitions shall apply: Very Relevant – Past/present performance effort involved essentially the same magnitude of effort and complexities this solicitation requires; Relevant – Past/present performance effort involved much of the magnitude of effort and complexities this solicitation requires; Somewhat Relevant – Past/present performance effort involved some of the magnitude of effort and complexities this solicitation requires; and Not Relevant – Past/present performance effort did not evolve any of the magnitude of effort and complexities this solicitation requires.

2.) Paragraph M-002.2.c. and d. – Change Performance Confidence Rating Table to read as follows:

Substantial Confidence
Satisfactory Confidence
Limited Confidence
No Confidence
Unknown Confidence

Based on the Offeror’s performance record, the government has a high expectation that the offeror willl successfully perform the required effort.

Based on the offeror’s performance record, the government has an expectation that he offeror will successfully perform the required effort.
Based on the Offeror’s performance record, the government has a low expectation that the offeror will successfully perform the required effort.

Based on the Offeror’s performance record, the government has no expectation that the offeror will be able to successfully perform the required effort.

No performance record is identifiable or the offeror’s performance record is so sparse that no confidence assessment rating can be reasonably assigned.

d. SPECIFICATION SECTION 22 40 00

1.) Paragraph 1.02 Related Sections – Add the following to the list of related sections:

“Section 06 61 17 – Solid Surface Countertops.”

2.) Add paragraph 2.13 as follows:

“2.13 COUNTERTOP SINK (LAV-1)

A. Lavatory is integral with the countertop and is specified as an architectural product in Specification Section 06 6117.

B. Faucet shall be chrome plated combination supply fitting with grid strainer, 0.5 GPM flow device, aerator, loose key supplies, single lever handle, chrome plated 17 gauge brass P-trap with cleanout plug and arm with escutcheon. American Standard 2385.009 with grid strainer or equal.”

e. SPECIFICATION SECTION 31 23 00 – 1.) Paragraph 3.01 – Change to read as follows:

“The Base will mark the location of the Air Force-owned utilities; the Contractor shall contact OUPS (1-800-362-2764) for the location of all other underground utilities. The Government will provide a general map. Work shall not commence until the Contractor receives a completed AF Form 103 from Base Engineering and has notified the Contracting Officer at least 48 hours prior to excavating, fencing, planting, or other work.”

2.) Paragraph 3.01 E – Change to read as follows:

“If conditions are encountered that are different from those shown on the Drawings, notify the Contracting Officer per the terms of the contract. Discontinue affected work in the area until notified to resume work.”

f. DRAWINGS THROUGHOUT – Any/all references to equipment being ‘FURN BY OTHERS” is changed to “FURN BY CONTRACTOR.” There is no Government-furnished property included in this contract.

g. DRAWING C-4 , Sheet 5 of 27, G ENERAL NOTE 7 – Add the following requirement: “Any/all restoration of excavation on the flightline side of the building/inside the flightline fence shall be accomplished via hydro-mulching/seeding.”

h. DRAWING P-1 Sheet 14 of 27, PLUMBING FIXTURE SCHEDLE – Change LAV1 Remarks from “wall hung” to “integral w/countertop.”

i. DRAWINGS E-2, Sheet 24 of 27 and E-4, Sheet 26 of 27 – Replace existing drawings with attached revised drawings. (Atch 2, two sheets)

j. REVISED DRAWING E-2 Sheet 24 of 27- 1.) Electrical Coded Note 1 – Change to read as follows: “EXISTING 480/277 VOLT, 3-PHASE, 4-WIRE DISTRIBUTION PANEL DP1. REMOVE EXISTING 20 AMP, 3-POLE CIRCUIT BREAKER FOR THE AIR COMPRESSOR AND SET ASIDE TO LATER INSTALL INTO EXISTING PANEL LCP (SEE CODED NOTE #9). FURNISH AND INSTALL ONE (1) NEW 40 AMP, 3-POLE CIRCUIT BREAKER. MATCH EXISTING BREAKER SIZE AND TYPE.”

2.) Detail 1 Electrical Power Plan, Existing Warehouse Room 102 – Change from “2 4/0 #16 SHIELDED CABLE…” to “2 4/c #16 SHIELDED CABLE…”

k. DRAWING E-5, Sheet 27 of 27 - Add GENERAL ELECTRICAL NOTE as follows:

“2. Contractor shall coordinate connection to Flow Meter Control Panel. Meter to be field located near manhole.”

(End of Summary of Changes)

F5Q3378133A001

ZQEL 06-0003

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04

EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

See pages 2 and 3 with attachments.

1. CONTRACT ID CODE

PAGE OF PAGES

J

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

08-Aug-2008

16B. UNITED STATES OF AMERICA

15C. DATE SIGNED

15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)

(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code)

X

FA6656-08-R-0004

9B. DATED (SEE ITEM 11)

18-Jul-2008

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

08-Aug-2008

CODE

910 MSG/CONF OPERATIONAL CONRACTING OFF

YOUNGSTOWN ARS

3976 KING GRAVES RD UNIT 31

VIENNA OH 44473-5931

FA6656

7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

See Item 6

FACILITY CODE

EMAIL:

TEL:

File details come from the government source that posted it. Updated .