RESPONSES TO CONTRACTOR QUESTIONS AS OF 7AUG 08.doc

DOC document 28 KB Posted

Attached to
Modify/Upgrade Industrial Wastewater Pretreatment System, Bldg 309
Solicitation number
FA6656-08-R-0004
Issued by

View the file

Other files

File Type Posted
Q A as of 22 July 2009 B502.doc DOC document
RESPONSE TO CONTRACTOR QUESTIONS-Computer Interface Requirements.docx DOCX document
FA6656-08-R0004Prime SubsList- 13Aug 08.rtf RTF text file
FA6656-08-R0004Prime SubsList- 12Aug 08.rtf RTF text file
RESPONSE TO CONTRACTOR QUESTION-HMI SCREENS.docx DOCX document
FA6656-08-R0004 Amd 0003.doc DOC document
FA6656-08-R0004Prime SubsList- 8Aug 08.rtf RTF text file
RESPONSES TO CONTRACTOR QUESTIONS-Site Visit.docx DOCX document
FA6656-08-R0004 Amd 0002.doc DOC document
FA6656-08-R0004 Amd 0002 Atch 1 - Responsibility Questionnaire.doc DOC document
24 of 27-E2 Rev Electrical Power Lighting Plan-Paper.pdf PDF
26 of 27-E4 Rev Electrical Site Plan B-309-Paper.pdf PDF
site visit minutes.doc DOC document
RESPONSES TO CONTRACTOR QUESTIONS AS OF 4 AUG 08.docx DOCX document
SITEVISITINFOPOSTING.doc DOC document
16 of 27-M2 P I Diagram.pdf PDF
Attachment 4 - PastPerformanceQuestionnaire.doc DOC document
1 of 27-G1 Title Page.pdf PDF
8 of 27-A3 Sections and Details.pdf PDF
silt fence-002.tif TIF image
18 of 27-M4 Deicing Manhole Site Plan.pdf PDF
14 of 27-P1 Plumbing Plan.pdf PDF
3 of 27-C2 Site Utility Plan.pdf PDF
27 of 27-E5 Elec Site Plan-Fire Training Facility.pdf PDF
17 of 27-M3 Carbon Tank Repair Coating Details.pdf PDF
FA6656-08-R0004 Atch 2 Specifications.doc DOC document
15 of 27-M1 Mechanical Plan.pdf PDF
11 of 27-S2 Roof Framing Plan Details.pdf PDF
21 of 27-M7 Flow Sensor-Monitor Modification.pdf PDF
19 of 27-M5 Deicing Collection Sys Details.pdf PDF
7 of 27-A2 Exterior Interior Elevations.pdf PDF
10 of 27-S1 Foundation Plan Detail.pdf PDF
FA6656-08-R0004 Atch 1 Gen Dec Mod 6.doc DOC document
6 of 27-A1 Flr Roof Reflected Ceiling Plans.pdf PDF
silt fence-001.tif TIF image
9 of 27-A4 Schedules and Details.pdf PDF
24 of 27-E2 Electrical Power Lighting Plan.pdf PDF
22 of 27-FP1 Fire Prot Plan.pdf PDF
2 of 27-C1 Demo Plan.pdf PDF
4 of 27-C3 Grading Plan.pdf PDF
25 of 27-E3 Fire Det Plan.pdf PDF
13 of 27-S4 Frame Sections and Details.pdf PDF
20 of 27-M6 Fire Training Deicing Manhole Site Plan.pdf PDF
23 of 27-E1 Electrical Legend Fixture Sch one Line Diagram.pdf PDF
12 of 27-S3 Foundation Section Detail.pdf PDF
5 of 27-C4 Details.pdf PDF
FA6656-08-R0004.doc DOC document
26 of 27-E4 Electrical Site Plan-B309.pdf PDF
Show all 48

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RESPONSES TO CONTRACTOR QUESTIONS AS OF 7 AUG 08

SOLICITATION NBR FA6656-08-R-0004

Modify/Upgrade Industrial Wastewater Pretreatment Facility, Bldg 309

1. On Drawing P-1 they are asking for 4” Power Vent Category III Stainless Steel Pipe that connects to the Gas Fired Water Heater. I didn’t find any spec on that pipe. Response: any 4” Category III stainless steel pipe for venting applications is acceptable. No minimum thiickness or schedule is required. PVC is not allowed.

2. Also, on Drawing M-2, the top of the page they have heavy outlines three (3) valves but they are not marked as to be removed and replace. Response: The three valves with heavy outlines designated SV-22, MV-5 and MV-6 will not be removed or replaced and are not involved in this project.

3. I would like to know what the specifications are for the Lavatory (Lav-1). There is nothing mentioned under Section 22 40 00. On the drawing (P1) it is listed as a wall hung and nothing more. Please advise. Response: The lavatory is integral with the countertop and is specified as an architectural product in Section 06 61 17, and it is shown on drawing A-1. The wall hung note on P1 is incorrect, as there is not a lavatory plumbing fixture. The faucet to be field mounted in the counter top should be equal to the following: Faucet shall be chrome plated combination supply fitting with grid strainer, 0.5 GPM flow device, aerator, loose key supplies, single lever handle, chrome plated 17 gauge brass P-trap with cleanout plug and arm with escutcheon. American Standard 2385.009 with grid strainer or equal. Amendment forthcoming changing the Plumbing Fixtue Schedule on Dwg P1 from “wall hung” to “counter mounted’ and adding the faucet description to Specification Section 22 40 00.