Attachment 4 - PastPerformanceQuestionnaire.doc

DOC document 47 KB Posted

Attached to
Modify/Upgrade Industrial Wastewater Pretreatment System, Bldg 309 Federal contract opportunity
Solicitation number
FA6656-08-R-0004
Issued by
Department of the Air Force Reserve Command

About this file

FA6656-08-R-0004 Atch 4 Past Performance Questionnaire

View the file

Other files for this federal contract opportunity

Other files attached to Modify/Upgrade Industrial Wastewater Pretreatment System, Bldg 309, newest first.
File Type Posted
Q A as of 22 July 2009 B502.doc DOC document
RESPONSE TO CONTRACTOR QUESTIONS-Computer Interface Requirements.docx DOCX document
FA6656-08-R0004Prime SubsList- 13Aug 08.rtf RTF text file
FA6656-08-R0004Prime SubsList- 12Aug 08.rtf RTF text file
RESPONSE TO CONTRACTOR QUESTION-HMI SCREENS.docx DOCX document
FA6656-08-R0004 Amd 0003.doc DOC document
FA6656-08-R0004Prime SubsList- 8Aug 08.rtf RTF text file
RESPONSES TO CONTRACTOR QUESTIONS-Site Visit.docx DOCX document
FA6656-08-R0004 Amd 0002.doc DOC document
26 of 27-E4 Rev Electrical Site Plan B-309-Paper.pdf PDF
FA6656-08-R0004 Amd 0002 Atch 1 - Responsibility Questionnaire.doc DOC document
24 of 27-E2 Rev Electrical Power Lighting Plan-Paper.pdf PDF
site visit minutes.doc DOC document
RESPONSES TO CONTRACTOR QUESTIONS AS OF 7AUG 08.doc DOC document
RESPONSES TO CONTRACTOR QUESTIONS AS OF 4 AUG 08.docx DOCX document
SITEVISITINFOPOSTING.doc DOC document
18 of 27-M4 Deicing Manhole Site Plan.pdf PDF
14 of 27-P1 Plumbing Plan.pdf PDF
3 of 27-C2 Site Utility Plan.pdf PDF
27 of 27-E5 Elec Site Plan-Fire Training Facility.pdf PDF
17 of 27-M3 Carbon Tank Repair Coating Details.pdf PDF
FA6656-08-R0004 Atch 2 Specifications.doc DOC document
15 of 27-M1 Mechanical Plan.pdf PDF
11 of 27-S2 Roof Framing Plan Details.pdf PDF
21 of 27-M7 Flow Sensor-Monitor Modification.pdf PDF
16 of 27-M2 P I Diagram.pdf PDF
1 of 27-G1 Title Page.pdf PDF
8 of 27-A3 Sections and Details.pdf PDF
silt fence-002.tif TIF image
24 of 27-E2 Electrical Power Lighting Plan.pdf PDF
22 of 27-FP1 Fire Prot Plan.pdf PDF
2 of 27-C1 Demo Plan.pdf PDF
4 of 27-C3 Grading Plan.pdf PDF
25 of 27-E3 Fire Det Plan.pdf PDF
13 of 27-S4 Frame Sections and Details.pdf PDF
20 of 27-M6 Fire Training Deicing Manhole Site Plan.pdf PDF
23 of 27-E1 Electrical Legend Fixture Sch one Line Diagram.pdf PDF
12 of 27-S3 Foundation Section Detail.pdf PDF
5 of 27-C4 Details.pdf PDF
FA6656-08-R0004.doc DOC document
26 of 27-E4 Electrical Site Plan-B309.pdf PDF
19 of 27-M5 Deicing Collection Sys Details.pdf PDF
7 of 27-A2 Exterior Interior Elevations.pdf PDF
10 of 27-S1 Foundation Plan Detail.pdf PDF
FA6656-08-R0004 Atch 1 Gen Dec Mod 6.doc DOC document
6 of 27-A1 Flr Roof Reflected Ceiling Plans.pdf PDF
silt fence-001.tif TIF image
9 of 27-A4 Schedules and Details.pdf PDF
Show all 48

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation Nbr F33630-08-R-0004, Modify/Upgrade IWP System, Bldg 309, Atch 4 Page 1 of 5 Pages CONTRACTOR’S NAME: __________________________ CONTRACT NUMBER: _________________________

RESPONDER FIRM AND POC Names:______________________________________________________________

ATTACHMENT 4

FA6656-08-R0004

CONTRACTOR PAST PERFORMANCE QUESTIONNAIRE – CONSTRUCTION CONTRACTS

SECTION A: CONTRACTOR INFORMATION: (To be completed by the contractor prior to mailing to reference)

a. Contractor’s name and address: ____________________________

b. Point of Contact: ____________________________

c. Phone #: _______________________

d. Contract #: _____________________

Contract Type: _______________________

e. Project Title: ____________________________________________________________

f. Performance Period: ______________________

g. Authorization is hereby given to provide the information in SECTION B of this questionnaire.

(Signature of authorized contractor representative.)

(Date)

(Printed name and title of authorized contractor representative.)

SECTION B: PERFORMANCE INFORMATION: (To be completed by the Present/Past Evaluation Respondents)

a. Respondent’s name and address: ____________________________

b. Respondent’s Point of Contact: ________________________

c. Phone #: ___________________________

d. Contract #: _____________________

Contract Type: _______________________

e. Award Amount: _________________

Final Amount: _________________

f. Performance Period: ______________________ Date of Completion (If applicable): ____________

g. Authorization is hereby given to provide the information in SECTION B of this questionnaire.

Please mail, fax, or email the completed questionnaire to:

910 MSG/CONF

Attn: Helen Jordan

YOUNGSTOWN AIR RESERVE STATION

3976 KING GRAVES ROAD – UNIT 31

VIENNA OH 44473-5931

Phone: (330) 609-1306 DSN: 346-1306

FAX: (330) 609-1042 DSN: 346-1042

Email: helen.jordan@youngstown.af.mil

PERFORMANCE INFORMATION: Choose the appropriate letter on the scale (E, G, S, M, U, and N) that most accurately describes the contractor’s performance or situation. PLEASE PROVIDE A NARRATIVE EXPLANATION FOR ANY RATINGS OF M or U.

E
G
S
M
U
N
Exceptional
Good
Satisfactory
Marginal
Unsatisfactory
Neutral

Performance meets contractual requirements with many exceeded to the Government’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with no more than a few minor problems for which corrective actions taken by the contractor were highly effective.

Performance meets contractual requirements with some exceeded to the Government’s benefit. The contractual performance of the element or sub-element being assessed was accomplished with no more than some minor problems for which corrective actions taken by the contractor were effective.

Performance meets contractual requirements. The contractual performance of the element or sub-element contains some minor problems for which corrective actions taken by the contractor were satisfactory.

Performance does not meet some contractual requirements. The contractual performance of the element or sub-element being assessed reflects a serious problem for which the contractor has not yet identified corrective actions or the contractor’s proposed actions appear only marginally effective or were not fully implemented.

Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance of the element or sub-element contains a serious problem(s) for which the contractor’s corrective actions appear or were ineffective.

Performance was not observed or not applicable to the current effort being reported against.

Please provide explanatory comments for any area/factor/subfactor rated less than satisfactory.

1. QUALITY CONTROL: RATING

a. Quality of Workmanship

b. Proper provision, use and storage of materials

c. Adequacy of submittals

d. Adequacy of as-built drawings

e. Identification/correction of deficient work in a timely manner

f. Initiative to suggest and implement solutions

2. TIMELY PERFORMANCE

a. Provided submittals in a timely manner

b. Submittals were well researched and clearly identified the proposed item

c. Submittals accurately matched contract requirements

d. Developed realistic progress schedules

e. Complied with established/approved progress schedules

f. Submission of updated and revised progress schedules

g. Resolution of performance delays

h. Completion of work, including punchlist items within performance period

3. MANAGEMENT EFFECTIVENESS

1. Provided experienced project managers/supervisors with the technical and administrative abilities needed to ensure compliance with contract requirements and safety regulations.

2. Site Manager/Superintendent had sufficient authority to make decisions or take action during project performance. Superintendent was consistently present on site while work was being performed and acted promptly to resolve probems and ensure work quality.

3. Subcontracted with experienced, knowledgable subcontractors

4. Paid subcontractors/supliers in a timely manner.

5. Effectively managed subcontractors.

6. Provided accurate, complete, reasonable, well-substantiated pricing data for modifications (not over inflated or under estimated).

7. Received timely and satisfactory responses to warranty issues after project completion.

8. Cooperated to resolve problems, attended meetings as scheduled and maintained communication to assure satsifactory resolution.

9. Provided proposals that accurately represented the work required.

10. Completed all contract work prior to requesting final inspection. Left no major discrepancies.

11. Completed all contract requirements, including final site cleanup, submittal of O&M

Manuals and warranties, and punchlist items by the required completion date.

12. Promptly submitted closeout documentation and final invoice after completion and acceptance of the project/contract.

4. COMPLIANCE WITH LABOR STANDARDS

a. Submitted complete and correct prime contractor payroll reports in a timely manner.

b. Ensured subcontractor payrolls were complete, correct and submitted in a timely manner.

c. Complied with labor laws and regulations, with specific attention to the Davis-Bacon Act.

5. COMPLIANCE WITH SAFETY AND OTHER STANDARDS

a. Timely prepared, submitted and implemented/enforced an adequate Safety & Health Plan

b. Timely prepared, submitted and implemented/enforced an adequate Environment Protection Plan/Sediment & Erosion Control Plan.

c. Timely prepared, submitted and implemented/enforced an adequate Waste/Recyling Plan.

d. Timely prepared, submitted and implemented/adhered to an adequate Work Plan, including work schedule.

Other Past Performance Considerations:

1. Were liquidated damages assessed? (If so, describe the frequency, circumstances, severity of problem etc.)

(Yes No)

2. Based on the contractor's overall performance, would this contractor (Yes No) be re-hired?

3. Were there any indications of financial/bonding difficulties of this (Yes No)

Contractor?

4. Did the Contractor display any unique skills or accomplishments?

(Yes No)

5. Was this Contractor issued any provessional/industry awards, letters of (Yes No)

Appreciation/commendation, etc., by your agency?

6. Did this Contractor successfully submit any value engineering change

(Yes No) proposals? If yes, what was the impact on reducing cost or schedule, increasing efficiency or improving quality?

EXPLANATION OF RATINGS AND ADDITIONAL REMARKS/COMMENTS:

(utilize additonal pages, if needed) Name of Evaluator ________________________________________________________

Organization _____________________________________________________________

Phone Number ______________________________________

Date of Involvement in Contract ________________________

Date Questionnaire Completed _________________________

PAST AND PRESENT PERFORMANCE QUESTIONNAIRE

When Filled In This Document Is Source Selection Sensitive IAW FAR 2.101 and FAR 3.104

File details come from the government source that posted it. Updated .