This is a Questions and Answers (Q&A) document for a federal contract opportunity for Integrated Munitions Protection System (IMPS) services at Misawa Air Base. The document addresses 23 clarification questions from prospective offerors regarding a new requirement to be awarded as a firm-fixed-price indefinite-delivery/indefinite-quantity (IDIQ) contract.

The contract requires a multi-disciplinary team including Site Security Managers (SSMs), Construction Security Technicians (CSTs), Construction Assessment Group personnel (CAGs), and Acoustical Engineers (AEs). Anticipated peak staffing levels are SSM (to be determined), 11 CSTs, 6 CAGs, and 1 AE if requested. All personnel require Top Secret clearances; the U.S. Government will not sponsor new clearance investigations or upgrades. The contractor must provide all equipment and materials for mobilization, including access control facilities and secure storage areas. Housing is the contractor's responsibility, with on-base housing unavailable. Housing costs should be embedded in labor rates. Surge support is not anticipated to occur. Task orders will remain within the IMPS scope and be driven by construction schedules. The Acoustical Engineer will be exercised on a task-order basis, anticipated for approximately three months at the project's end. The anticipated RFP release date is on or before March 1, 2011, with contract award anticipated August 1, 2026, and Notice to Proceed by September 12, 2026. Evaluation will be based on best value considering technical capability, past performance, and price, with award to the lowest-priced technically acceptable proposal. Post-award debriefings will be provided upon written request within three days of contract award notification.

View the file

Other files

File Type Posted
Solicitation Amendment - FA520526R00040004.pdf PDF
Attachment 8. B3267 Site Layout, dated 25 Mar 26, 1 page.pdf PDF
Attachment 7 - IMPS Amend 4 - Questions and Answers 24 Apr 26.xlsx XLSX spreadsheet
Attachment 10. Bldg 3267 Parking Area Underground Utilities - 21 Apr 26.pdf PDF
Solicitation Amendment 4 - FA520526R00040004 SF 30.pdf PDF
Attachment 1. IMPS PWS dated 24 Apr 26, 47 Pages.pdf PDF
Attachment 9. Boring Bldg 3267 - 21 Apr 26.pdf PDF
Solicitation Amendment 3 - FA520526R00040003 SF 30.pdf PDF
Attachment 3. IMPS Excel Equipment Price List, dated 24 Apr 26, 6 pages.xlsx XLSX spreadsheet
Solicitation Amendment - FA520526R00040004 (Editable 1449).pdf PDF
Attachment 11. IMPS Site Visit Notes - 2 Apr 26_Redacted.pdf PDF
Attachment 4. DD 254 Security Classification, dated 01 Apr 26, 3 pages.pdf PDF
Solicitation Amendment 2 - FA520526R00040002 SF 30.pdf PDF
Solicitation Amendment FA520526R00040003 SF 30.pdf PDF
Attachment 3. IMPS Excel Equipment Price List, dated 06 Apr 26, 6 pages.xlsx XLSX spreadsheet
Attachment 10. IMPS Site Visit Notes - 2 Apr 26_Redacted.pdf PDF
Attachment 5. DD 254 Instructions, dated 01 Apr 26, 12 pages.pdf PDF
Solicitation Amendment 1 - FA520526R00040001 SF 30.pdf PDF
Attachment 8 - IMPS Amend 2 - Q and A 29 Mar 26 FINAL.xlsx XLSX spreadsheet
Amendment 2 - FA520526R00040002 SF 30 FINAL (edit).pdf PDF
Solicitation Amendment - FA520526R00040002 FINAL.pdf PDF
Amendment 2 - Summary of Changes (editable).pdf PDF
Amendment 2 - FA520526R00040002 (Edit).pdf PDF
Attachment 5. DD 254 Instructions, dated 25 Mar 26, 12 pages.pdf PDF
Amend 2 Summary of changes - 26R00040002 SF 30 (Not Req with Quote).pdf PDF
Solicitation Amend 2 - FA520526R00040002 (editable).pdf PDF
Attachment 3. IMPS Excel Equipment Price List, dated 27 Mar 26, 6 pages.xlsx XLSX spreadsheet
Attachment 8 - IMPS Amend 2 - Q and A 29 Mar 26.xlsx XLSX spreadsheet
Attachment 4. DD 254 Security Classification, dated 25 Mar 26, 3 pages (NEW).pdf PDF
Attachment 5. DD 254 Instructions, dated 01 Apr 18, 12 pages.pdf PDF
Attachment 9. B3267 Site Layout, dated 25 Mar 26, 1 page (NEW).pdf PDF
Attachment 1. IMPS PWS dated 25 Mar 26, 38 Pages (NEW).pdf PDF
Summary of Changes - 26R00040002 SF 30.pdf PDF
Attachment 3. IMPS Excel Equipment Price List, dated 25 Mar 26, 6 pages (NEW).xlsx XLSX spreadsheet
Attachment 8 - IMPS Amend 2 - Q and A 25 Mar 26 (NEW).xlsx XLSX spreadsheet
Solicitation Amendment - FA520526R00040002.pdf PDF
Solicitation Amendment - FA520526R00040001 (editable).pdf PDF
Attachment 1. IMPS PWS dated 11 Mar 26 38 Pages.pdf PDF
Solicitation Amendment - FA520526R00040001.pdf PDF
Summary of Changes - Amendment 26R00040001 SF 30.pdf PDF
Attachment 4. DD 254 Security Classification, dated 04 Feb 26, 3 pages.pdf PDF
Attachment 5. DD 254 Instructions, dated 01 Apr 18, 12 pages.pdf PDF
Attachment 2. IMPS Excel Personnel Price List, dated 02 Mar 26, 2 pages.xlsx XLSX spreadsheet
Attachment 3. IMPS Excel Equipment Price List, dated 02 Mar 26, 6 pages.xlsx XLSX spreadsheet
Attachment 6. DCSA Field Office Locations, dated 7 Apr 21, 7 pages.pdf PDF
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Referenced Document

Page Number

Paragraph / Section Question Requested Clarification Response

1 PWS General 1.0Scope Isthisanewrequirementorafollow‐onrequirement?
Pleaseclarifywhetherthisrequirementisnewora
follow‐onandidentifyanychallengeswiththe
incumbentarrangement.

This is a new requirement.

2 Solicitation General 1.0Scope Isthereanincumbentcontractorcurrentlyperforming
IMPSservicesatMisawaAB?
Ifso,pleaseidentifytheincumbentcontractorand
contractnumber.
Sincethisisanewrequirement,thereisnoincumbemtcontractor.However,similarworkis
beingperformedonasmallerscopeunderthebelowcontracts:
FA520525F0123‐1eachSSM
FA520525P0071‐OnetimeCSTservice

3 Solicitation General 1.0 Scope Is a Facility Clearance (FCL) required for this contract?

Ifrequired,pleasespecifytheclearancelevel
(Secret,TS,TS/SCI).Additionally,ifaFacility
Clearanceisrequiredandthecontractor’sfacility
iscurrentlyclearedattheSecretlevel,willthe
Governmentsponsorthecontractorforthe
appropriateFacilityClearanceupgrade,if

necessary?

IAWthePWS:
2.3.2.1TheSSMmustpossessandmaintainaUSTOPSECRET(TS)clearance.
2.3.3TheCSTmustpossessandmaintainaUSTOPSECRET(TS)clearance.
2.3.4TheCAGsmustpossessandmaintainaminimumofaUSSECRETclearance.
2.3.5TheAEmustpossessandmaintainaUSTOPSECRETclearance.

Additionally see 5.4.8 Clearance Requirements in the PWS.

TheUSGovernmentwillnotsponsornewinvestigations.TheContractorisresponsibletopocess
andmaintainaTSfacilityclearancealongwithprovidepersonnelwithrequiredclearances.

4 PWS 5–6 2.1.2 What is the anticipated peak staffing level for CSTs and CAGs?

Pleaseconfirmexpectedstaffingrangesfornormal
andsurgeoperations.

The anticipated peak staffing levels are as follows:

SSM‐TBD
CST‐11
CAG‐6
A/E‐1(ifrequested)

5 PWS 6 2.1.3 How frequently does the Government anticipate surge requirements?

Pleaseclarifywhethersurgesupportisexpectedto
berecurringorinfrequent.
Surgesupportisnotanticipatedtooccurandifitshouldoccuritisanticipatedtobeinfrequent.
Thedemandforsupportisdrivenbyconstructionschedulewhichwilbeprovidedtocontractor.
WhatbaselevelofeffortdoestheGovernment
anticipate?Pleaseclarifythecontextoftheannualfirm‐
fixed‐pricestructure.
Forexample,thesolicitationallowsfortaskorders,
overlappingprojects,surgestaffing,andvariable
constructionschedulesbutdoesnotstatewhatthe
Governmentassumesasabaselineintermsofnumber
ofconcurrentprojects,typicalstaffinglevels(CAGs,
CSTs,andSSMs),orexpecteddutyhours.
TheUSGanticipatesawardingaFFPIDIQcontract.Thiswillallowfortaskordersforsupport
basedonConstructionschedule.TheContructionwillbethebaselineandisstillindevelopment,
butwillbesharedwithcontractor.
7 PWS 8–9 2.3.2 AreSiteSecurityManagersrequiredtobededicated
perproject?
PleaseclarifywhetheroneSSMmayoversee
multipleconcurrentprojects.
TheverbiageinthePWShasbeenchanged.SSMisnotcurrentlyexpected,butmayberequired.
Thiswillbeprojectdependent.However,theawardeewillberequiredtohavetheabilityto
hireanSSMifitisdeemednecessaryandwillprovidethewageratesfortheSSMtodetermine
fairandreasonablepricingandavialbility.
IfaSSMisrequiredthecontractorwillbegivenreasonaletimetosourcepersonnelandthatSSM
mayberequiredtoworkmorethanoneproejcts.

8 PWS 18 3.1 Are all inspection and surveillance tools contractor‐ furnished?

PleaseconfirmwhetheranyGovernment‐
furnishedequipmentwillbeprovided.

No Government‐furnished equipment will be provided.

2.1.1.2Themobilizationconsistsofprovidingallequipment,andmaterialsneededfor
performance,toincludetheAccessControlFacility(ACF)andSecureStorageArea(SSA).
9 PWS 10 2.3.5 HowwillAcousticalEngineerservicesbeexercised? PleaseclarifywhetherAEsupportwillbetask‐
orderspecificandestimateannualusage.
AEwillbeexercisedonataskorderbasis.Currently,weestimatethattheAEmayonlybe
neededforaboutthree(3)monthstowardtheendoftheoverallproject.

10 Solicitation When is the anticipated RFP release Anticipated solicitation date is on or before 01 Mar 2026.

11 Solicitation 7 Delivery Schedule What is the anticipated contract award date? Please provide an estimated award and Notice to

Proceed timeline. Anticipated award date is 01 Aug 2026. Anticipated Work start date is 01 Sep 2026.

12 Solicitation N/A Post‐Award Will debriefings be provided upon request? Please confirm availability of post‐award debriefings.

DebriefingswillbeprovideduponrequestIAWFAR15.506Postawarddebriefingofofferors.
(a)(1)Anofferor,uponitswrittenrequestreceivedbytheagencywithin3daysafterthedate
onwhichthatofferorhasreceivednotificationofcontractawardinaccordancewith15.503(b),
shallbedebriefedandfurnishedthebasisfortheselectiondecisionandcontractaward.
HousingResponsibility:CantheGovernmentconfirm
whetherthecontractorisresponsibleforhousing
contractorpersonnel,orifhousingwillbeGovernment‐

furnished?

The contractor will be responsible for housing

AvailabilityofOn‐BaseHousing:IfGovernment‐
furnishedhousingisavailable,willon‐basehousingat
MisawaAirBasebemadeavailabletocontractor

personnel?

Government‐furnished housing is not available

PricingofHousingCosts:Ifcontractor‐provided
housingisrequired,cantheGovernmentclarifywhere
housing‐relatedcostsshouldbereflectedwithinthe
twopricingworksheets,includingwhethersuchcosts
shouldbeembeddedinlaborratesorpricedasa
separatecostelement?

Housing‐related costs should be embedded in labor rates

16 Solicitation

Under“PastPerformance”,thedraftsolicitation
documentcurrentlystatesthefollowing“Offerorshall
providealistingofanyrecentandrelevantcontractsof
similarscope.Listshallconsistofthefollowingformat
projecttitle,contractnumber,contractdollarvalue,
location,ifworkwasdonewithacertifiedKardex
installerandifanyqualityissues.Thisistheminimum

requirement.

Itisunclear,basedonthecurrentwording,ifOfferors
arerequiredtohaveexperiencewithacertified
Kardexinstallerinordertoqualifyunderthebid
evaluationcriteria.Asthisisaveryspecific
requirementthatmanyotherwisequalifiedOfferors
mightnothave,werespectfullyaskthatyouremove
thislanguagefromthefinalRFP.

Is the verbiage in red necessary for evaluation?

If yes, why?

If no, the verbiage should be deleted.

This verbiage was not necessary and has been removed.

17 Solicitation Arethereanyadditionaldetailsonsurveillance
requirementsunderICD‐705? Noadditionaldetailsonsurvelliance

18 Solicitation Whether further industry engagement is planned. At this time, additional industry engagement is not planned unless requested by interested parties.

Aretaskordersintendedtostaystrictlywithinthe
IMPSscopedescribedintheDraftPWS?Orwill
additionalfacilities,expandedtechnicalsecurity
functions,oraddedconstruction/infrastructure
requirementsbeintroducedwithoutcontract
modifications?Thetaskorderscopeboundariesmay
benefitfromadditionalclarity.
Taskordersareexpectedtostaywithinthescopeofthisrequirement.Thetypeofwork
requiredwillremainthesame.However,IMPSservicemayberequestedforotherfacilities
basedontheconstructionscheduleofperformance.
TheDraftPWSreferencesacousticengineering,
TEMPEST,andTSCMactivities,butitisunclear
whethercontractorresponsibilityislimitedtotesting
andreportingorifremediationsupport,coordination
withconstructionteams,orretestingisexpectedwhen
issuesareidentified.Thedepthoftechnicalsecurity
responsibilitymaybenefitfromfurtherdefinition.
AE'sresponsibilitieshavebeenupdatedthroughoutPWS:
•Testingandreporting.Ifremediationsupportisnecessary,coordinatewithSSMtocorrectany
founddiscrepancies.Retestingisrequireduntilthediscrepanciesareresolvedandisinfull
compliancewithICD‐705.
•ReportanydiscrepancieswithintheirareasofresponsibilitytotheSSM.
•Retestingisexpectedtobeperformedwhenissuesareidentiϐieduntiltheyareresolved.
PleaseconfirmwhethertheSSMhasstop‐work
authorityforsecurityviolationsorreportingauthority
only,withdirectioncomingfromtheCORorother
Governmentofficials.TheSiteSecurityManager’s
authoritymaybenefitfromfurtherclarity.
SSMhasauthoritytoimmediatelyintervenetopreventanincidentorsecurityviolations.They
alsohavereportingauthorityandmustnotifyappointUSGrepsimmediately.

22 SOLICITATI

ON page 39

Evaluationcriteriastats"TheGovernmentwillawarda
contractresultingfromthissolicitationtothe
responsibleofferorwhoseofferconformingtothe
solicitation,willbethemostadvantageoustothe
Governmentandrepresentsthebestvaluetothe
Governmentintermsoftechnicalcapability,past
performanceandprice.”
However,allevaluationswillbeeitheracceptableor
unacceptable,whichisusedforLowestPrice
TechnicallyAcceptable(LPTA).FAR12.602states
"Fullydocumenttherationaleforselectionofthe
successfulofferorincludingdiscussionofanytrade‐

offs considered.”

Willthegovernmentpleaseconfirmisthisisabest
valuationorLPTAevaluation?
Ifbestvalue,willthegovernmentpleaseidentify
howthegovernmentwillselectthesuccessful
offerorincludingdiscussionofanytrade‐offs

considered?

ThisisnotanLPTAevaluation.EvaluationwillbebasedonbestvalueasstatedinFA52.212‐2.TheUSG
doesnotanticipateconductingdiscussionsatthistime.
TheDraftSolicitationstates,“TechnicalCapabilityand
PastPerformancehavebeendeterminedtobeofequal
importancetoprice.TheGovernmentwillawarda
contractresultingfromthissolicitationtothe
responsibleofferorwhoseofferconformingtothe
solicitation,willbethemostadvantageoustothe
Governmentandrepresentsthebestvaluetothe
Governmentintermsoftechnicalcapability,past
performanceandprice.”
HowwilltheGovernmentrankpricespecifically?
Forexample,willtheGovernmentrankall
technicallyacceptableproposalsinorderofprice
andchoosethelowestpricethatistechnically

acceptable?

TheUSGwillrankalltechnicallyacceptableoffersbypriceandevaluateforfairandreasonabless.
Awardcanbeanticipatedtoaproposalthatconformstoandmeetsallthetechnicalandpast
performancerequirementsatthelowestfairandresonablepricethatprovidestheUSGthebestvalue.

File details come from the government source that posted it. Updated .