Query No. Target Document Reference Question Submitted by Prospective Offerors Gov't Response / Clarification
1 General About warranty. Does warranty covers each individual parts and equipment? Or it should cover the entire plant system?
Any equipment warranty requirements, beyond those required for the project as a whole, are included in the individual equipment specification sections.
2 General
What is the base of calculation? Need to know the Max water amount per day, Max water amount per hour, average water amount per day.
The design flows and loadings are included in the DA, in Section II, Paragraph C. The process treatment tankage and equipment are already sized for the design flows and loadings. We will provide a separate document with the wastewater loading and sizing information that government can provide to bidders in Bid Addendum 02.
Current Avarage flow Main Base 0.681 MSD North Base 0.165 MSD Current Maximum Month Flows Main Base 0.737 MGD North Base 0.229 MGD Current WWTP Design Flows Main Bsae 1.3MGD North Base 0.43 MGD Design Peak Hour Flow 3.9 MGD
3 General
Upgrading the system,. Does this mean upgrading the quality of water? If so, we need to know the current quality and condition of the system regarding water treatment.
The system is designed to meet JEGS permit requirements. Should the Offeror want to see the permit, the base would need to make that available. The process treatment tankage and equipment are already sized for the design flows and loadings. Also, the additional information Addendum 02 should address this.
4 General
Production of Existing System. Understand that we need to replace 4 units. How many unit can we shut down at a time do to the work. That changes our work procedure. In order for us to work without interruption, we need to know capacity and ability of each current unit. Especially the flow load.
Section 01 11 00 Summary of Work, suggests a viable construction sequence, and which treament units may be taken off line and shut down at any given time. Shut down will be one unit by one unit. Needs to be clarified by Waste Water Treatment Plant Manager ( Officially).
During contractor's development of Construction Schedule, WWTP Manager will need to approve construction sequence schedule.
Verification from WWTP Manager will come during proposal/construction schedule review.
5 General
Japanese Waste Water Treatment Plant Law. Japanese Waste Water Treatment System Law. We believe that this will not match the Japanese law once we upgrade the system as described. Should we not to follow the Japanese Law? ①There is no Primary Conditioning Tank ②There is no Third Chemical Sedimentation Process * We need the third process if we need to do the nitrogen removal.
The proposed treatment system will meet JEGS permit requirements.
Microscreens are designed to replace the primary clarifier. Nitrogen removal is accomplished with the use of a pre-denitrification single sludge nitrification/denitrification system, incorporating Anoxic Zones and an internal recyle system, reducing the reliance on chemicals and eliminating the need for separate nitrification/denitrification stages.
6 Specifications 01 11 00, para. 1.1.1 About the Bid Option. Should we include this option plan into the cost? Is this up to us to determine which option we select.
Addendum 01 removes Bid Options
7 Specifications 22 00 00 Rating for Plumbling. Please tell us the standard for flange. Can we use JIS standard for flanges and nut and bolt?
Yes, JIS standards for flanges, nuts and bolts are acceptable. Need to be selected by CE Operation
RFP No. FA5205-15-R-0007, Repair Main Wastewater Treatment Plant, B1190, Misawa AB, Japan Consolidated List of Prospective Offerors' Submitted Questionnaire and U.S. Government Response / Clarification
Attachment 3 to FA5205-15-R-0007-0003 dated 26 Jun 15
Query No. Target Document Reference Question Submitted by Prospective Offerors Gov't Response / Clarification
RFP No. FA5205-15-R-0007, Repair Main Wastewater Treatment Plant, B1190, Misawa AB, Japan Consolidated List of Prospective Offerors' Submitted Questionnaire and U.S. Government Response / Clarification
8 Specifications 43 11 33.10
46 76 33 00
Designation of Vender and Specification. Under the “ACCEPTABLE MANUFACTUREER/MODEL” , if it doesn’t say “OR EQUAL”, are we not allowed to use other manufacturer? For example, it says; Rotary Lobe Blowers: Aerzen/Model GM25S under 43 11 33.10
Section 43 11 33.10 states :"The product brand is for informational purposes only and shall not be construed as the only product available." Therefore, any "OR EQUAL" product is acceptable, as long as it meets the requirements of the specifications. Performance of the equipment must be equal, and it is agreed that there is no parallel JIS to ASTM standards. Materials should be meeting a similar type of JIS standard, when compared to ASTM requiments.
9 Specifications 43 11 33.10
46 76 33 00
Designation of Vender and Specification. If it says “OR EQUAL”, we need to know detail specification of each equipment. Considering maintenance in the future, we intend to use Japan made manufacturer as much possible. We need detail description of each item, so that we can research for the item to match the current description.
Japanese manufacturers are not excluded, provided the equipment is equal to the specified equipment. A detailed description is provided in the individual specification section.
10 Specifications 43 22 56.20 Designation of Vender and Specification. What is the flow speed of the bottom (cm/Sec)when using the HYPERBOLIC MIXERS?
The Hyperbolic mixers are a slow speed mixer, operating at 18 rpm, to completely mix the tank contents while not damaging MLSS floc.
11 Drawings D-613
Descrepancy of description. At the site visit, we were told that sludge dehydrator will be replaced with new screw press type, but on the drawing, it says replace with new centrifugal extractor. Which is correct?
A centrifuge is included in the design.
12 Drawings D-621 Descrepancy of description. At the site visit, we were told to remove the methanol tank, but on drawing, it says to reuse the existing one.
The existing methanol tank and pumps will remain.
13 Drawings D-604 and Others Material for Piping. About CLDI (Mortar lining duck tile), can we use polyethylene lining duck tile instead?
Provide cement lined ductile iron pipe, NOT polyethelyene which can delaminate, and may not be suitable at higher temperatures.
14 General
Items not identified on Documentation. At the current third treatment process, we will remove the filler equipment. What is the model, size, load amount? ①Current condition of this equipment. ②What is inside and how much of sludge left?
Regarding sludge in tanks, refer to Section 01 11 00, Paragraph 1.1.1.1.C.1.h : "Contractor shall be responsible for all bypass pumping required, tank draining, cleaning, and disposal of all settled solids and grit from treatment tankage."
15 General
Due date for submitting. We will need at least 2 months to gather all the information and calculate once we receive the answers. Information provided to us was not enough to cover the knowledge for us to do the cost estimation.
Solicitation submission due date was changed from "12 Jun 15" to "31 Jul 15" with Amendment No. 0001 issued on 4 Jun 15, and it is posted on the FedBizOpps.
Drawings and Specifications
The Bid Option is indicated both on contract drawings and specifications.
However, only Base Bid is provided at Section B of the Solicitation. Please clarify.
Addendum 01 removes Bid Options
17 Drawings F-001
The item No. 6 of notes for NEW WORK indicates that “Obtain approval from structural engineer before making any penetration through structural members, walls and slabs.” Please advise the procedure for obtaining approval from structural engineer.
As this is an existing building, the design intent is to not penetrate any structural members unless physically impossible to install the fire sprinkler piping. Should a penetration be required, the contractor is responsible for submitting an RFI to the government who will forward it on to the structural designer of record .
Query No. Target Document Reference Question Submitted by Prospective Offerors Gov't Response / Clarification
RFP No. FA5205-15-R-0007, Repair Main Wastewater Treatment Plant, B1190, Misawa AB, Japan Consolidated List of Prospective Offerors' Submitted Questionnaire and U.S. Government Response / Clarification
Drawings and Specifications
F-001 21 13 17.00 10
From the drawings and specification for Fire Protection works, such as dry pipe sprinkler system installation and Mass Notification System, we assume that these works shall be designed by the Contractor and these drawings shall be endorsed and approved by the registered Fire Protection Engineer under NFPA. Please confirm.
Contractor is responsible for final fire sprinkler shop drawings in accordance with NFPA 13 and shall be approved by the Fire Protection Specialist.
19 Specifications 21 13 17.00 10 Para. 1.4.1 and 1.4.2
Para. 1.4.1, Section 21 13 17.00 10 of the contract specification indicates that the Fire Protection Specialist (FPS) should be appointed and he should be a registered professional engineer and Full Member of the Society of Fire Protection Engineer or Level III Technician under NICET. Please advise whether this requirement is mandatory or not.
In papa. 1.4.2 of the same section, we assume that the Sprinkler System Installer should be approved by the Government. Please advise whether experienced Japanese Sprinkler System Installer is acceptable or not.
It is manditory that the FPS meet the requirements of the specifications. A Japanese contractor meeting the requirements of paragraph 1.4.2 is acceptable.
Specifications and Drawings General
There are lot of material, equipment, machineries and devices are indicated and specified in the contract drawings and specification. Can we prepare the bid price based on the Japanese material, equipment, machineries and devices, if the quality of these are equal or exceed the specified material, equipment, machineries and devices?
Yes. Japanese manufactured equipment and materials that meet the specifications are acceptable. Performance of the equipment must be equal, and it is agreed that there is no parallel JIS to ASTM standards.
Materials should be meeting a similar type of JIS standard, when compared to ASTM requiments.
21 Specifications 01 33 29
IAW para. 1.3, Section 01 33 29, USGBC LEED-NC rating system will be utilized and LEED Sustainability coordinator is required to be employed.
However, LEED is not so familiar and common in Japanese construction market and almost of Japanese engineer has no experience in LEED certified or registered project. Please advise whether LEED requirement under this section is mandatory or some sort of relaxation will be considered by the Government.
LEED certification is preferred but not mandatory.
22 Specifications 01 11 00 01 35 29
We understand the SSHO will be acceptable if he has a certificate issued by JCSHA. However, Master Entry Plan (MEP) should be approved prior to commencement of the work under confined space and this Plan should be prepared to comply with US safety regulation such as Air Force Occupational Safety and Health Standard (AFOSH) and MEP prepared based only on Japanese Safety Regulation will not be acceptable.
Please advise.
MEP must comply with AFOSH standards. MEP is subject to approval by Bio Environmental, 35 CES/CEF, and review of 35 CES/CEOIE and 35 CES/CEOIU. There will be no further special requirements outside of specifications.