JA-27_EAFB_Seed_Project_Statement_of_Work.pdf

PDF 79 KB Posted

Attached to
Paving MACC Federal contract opportunity
Solicitation number
FA5004-15-R-C001
Issued by
Department of the Air Force Pacific Air Forces

About this file

JA-27 EAFB Seed Project Statement of Work

View the file

Other files for this federal contract opportunity

Other files attached to Paving MACC, newest first.
File Type Posted
FA5004-15-R-C001_Amendment_0005.pdf PDF
Question_and_Answer_MACC_-_11_May_15.pdf PDF
JA-28_Seed_Project_Pricing_Data_Sheet_-_28_Apr_15.xlsx XLSX spreadsheet
JA-27_EAFB_Seed_Project_Statement_of_Work_-_Updated_28_Apr_15.pdf PDF
FA5004-15-R-C001-0004_-_Amendment_0004.pdf PDF
JA-31_Questions_and_Answers.pdf PDF
JA-29_Repair_North_Street_Map.pdf PDF
JA-30_Site_Visit_Sign_In_Sheet.pdf PDF
FA5004-15-R-C001-0003_Amendment_0003.pdf PDF
JA-29_Repair_North_Street_Map.pdf PDF
Questions_and_Answers_1_-_Amendment_0002.pdf PDF
FA5004-15-R-C001-0002_Amendment_0002.pdf PDF
JA-27_Seed_Project_Statement_of_Work.pdf PDF
JA-28_Seed_Project_Pricing_Data_Sheet.xlsx XLSX spreadsheet
FA5004-15-R-C001-0001_Amendment_0001.pdf PDF
JA-26_FWW_Installation_Fast_Access_Program.pdf PDF
JA-17_Past_Performance_Worksheet.pdf PDF
JA-14_AF_Form_103.pdf PDF
JA-8_Section_670_Pavement_Markings.pdf PDF
JA-3_EAFB_Project_Pricing_Data_Sheet.xlsx XLSX spreadsheet
JA-24_ETL_04-2.pdf PDF
JA-13_Sidewalk_Ramp_Detail.pdf PDF
JA-20_FWW_Appendix_K.pdf PDF
JA-16_Past_Performance_Questionnaire.pdf PDF
JA-10_AC_Joint_Detail.pdf PDF
JA-9_Appendix_B_-_AK_DOT PF_Maintenance_Spec_for_Pavement_Marking.pdf PDF
FA5004-15-R-C001_Eielson_AFB_ _Ft_Wainwright_Paving_MACC.pdf PDF
JA-12_Sidewalk_Scupper_Detail.pdf PDF
JA-11_Curb_and_Gutter_Detail.pdf PDF
JA-7_AKDOT_Standard_Aggregates_Specs.pdf PDF
JA-15_Financial_Reference_Sheet.pdf PDF
JA-19_FFW_Historic_Properties.jpg JPG image
JA-25_Wage_Determination.pdf PDF
JA-18_FWW_Environmental_Concerns-FWA.pdf PDF
JA-22_EAFB_AF_Form_3000.pdf PDF
JA-2_FWW_Paving_Specifications.pdf PDF
JA-6_FWW_Work_Items_and_Definitions.pdf PDF
JA-21_EAFB_Historical_Projects.pdf PDF
JA-4_EAFB_Work_Items_and_Definitions.pdf PDF
JA-23_EAFB_AFI_32-1042.pdf PDF
JA-28_EAFB_Seed_Project_Pricing_Data_Sheet.xlsx XLSX spreadsheet
JA-1_EAFB_Paving_Specifications.pdf PDF
JA-5_FWW_Project_Pricing_Data_Sheet.xls XLS spreadsheet
Show all 43

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

FOR

PROJECT FTQW 16-2001

Repair North St. (Central to RR tracks)

1.0 SCOPE: Furnish all labor, supplies, parts, transportation, tools, equipment, and facilities necessary to perform work required to complete project FTQW 16-2001 in strict accordance with this Statement of Work and IDIQ contract specifications.

2.0 DESCRIPTION OF WORK: This project consists of curb & gutter repair, sidewalk repair, adding new sidewalk, asphalt repair and pavement markings along North Street. Contaminated soil may be encountered because work for this project lies within the SS62 contaminated zone and ST59 buffer zone.

3.0 SIDEWALK AND CURB/GUTTER REPLACEMENT

3.1 Sawcut (est. 325 IN-FT), remove and replace curb/gutter and sidewalks unless otherwise annotated on map, from Central Ave to Railroad tracks. (est 600 SF sidewalk/1100 LF curb) Excavate as necessary behind sidewalks for formwork. (est. 160 CY) Where

California style curb exists, demolish transition portions from California curb to high-profile curb and continue California style curb. Install transition to high-profile curb at project limits.

3.2 Scarify, grade and compact existing base.

3.3 Add RAP as needed to establish grade (sub-base for curbs & sidewalks).

3.4 Install California style curb profile.(est. 1100 LF) Pour new 4’ wide sidewalk. (est. 1200

SF) Add new sidewalk where none exists. (See Map, Tab 5)

3.5 Backfill excavation for sidewalk formwork with 6” topsoil and hydroseed.

4.0 ASPHALT PATCHING

4.1 Sawcut and remove asphalt as shown on map. (est. 10,000 SY)

4.2 Scarify, grade and compact existing base course. Cut ditch and grade so drainage flows into the slough. Meet a minimum of 1% slope for all surfaces. (see map for drainage plan)(est. 2210 SY)

4.3 Add RAP as needed to establish grade (base course for roadways). (est. 200 CY)

4.4 In low lying area near slough crossing place sub base structural fill and top with 6” D-1 base course. (est. 185 CY)

4.4 Place and compact 3” HMA.(est. 325 Ton)

4.5 Paint new asphalt with MMA, 4” lines in accordance with the Manual for Uniform

Traffic Control Devices. (est. 2200 LF)

5.0 SUBMITTALS: As indicated in the attached AF Form 66, Schedule of Material Submittals.

6.0 GOVERNMENT FURNISHED MATERIALS: None.

18 Mar 2015

END OF STATEMENT