This is an Exterior Pressure Vessel Inspection Report documenting the condition of a horizontal pressure vessel located at Space Launch Complex 4 (SLC-4) at the High Pressure Gas Storage Area (HPGSA). The inspection was conducted on January 24, 2024, by Brett Strickland (Level II Inspector) on behalf of Call Henry Inc. for vessel PV-229 (Serial Number 750400-1V7), manufactured by Taylor Forge. The vessel stores gaseous nitrogen at a maximum allowable working pressure (MAWP) of 6,000 PSI within a temperature range of -25 to 140°F. The inspection employed standard external examination techniques using ladder, flashlight, mirror, bubble leak detector, picks, hammer, ruler, and camera.

The inspection identified multiple deficiencies requiring remediation. Critical findings include a leak at the top head nozzle flange (rated "Other"), dissimilar metals on bolt/flange assemblies without proper isolation—specifically galvanized steel washers in contact with stainless steel studs and nuts in violation of AFSPCMAN 91-710 11.3.1.5.6 (rated "Rejectable")—and missing system reference designators on relief valves in violation of AFSPCMAN 91-710 LOSC Tailored 11.2.1.7.6.7 (rated "Rejectable"). Additional concerns include moderate corrosion on the isolation valve, an offset of 7/8" and gap of 1.25"-1.5" between concrete foundations requiring continued monitoring, gauges lacking "No Calibration Required" (NCR) stickers, relief valves outside the one-year calibration period, and vegetation growth around foundation gaps. All weld inspections, support structures, and most attachments were rated as acceptable. Access to the facility requires advance coordination with Space X facility operators.

View the file

Other files

File Type Posted
Attch 3 CDRL A020 Asbestos Lead Abate Draftv2.pdf PDF
Attch 3 CDRL A014 PE Resp List Draftv2.pdf PDF
TL 20250624 VSFB CCCPM for Submittal to DDWv2.pdf PDF
TL PM Workload Matrix CLINv2.xlsx XLSX spreadsheet
Attch 3 CDRL A016 Daily MR Schdle Draftv2.pdf PDF
Attch 8 Cost Price Workbook-draftv2.xlsx XLSX spreadsheet
Attch 3 CDRL A023 Emission Equp Usage Draftv2.pdf PDF
TL Launch Slips Liftoffs by OYs total hrsv2.xlsx XLSX spreadsheet
Attch 3 CDRL A024 Facility Asses Rpt Draftv2.pdf PDF
Attch 3 CDRL A011 Sys Safety Pgm Plan Draftv2.pdf PDF
Attch 3 CDRL A021 Cathodic Prot Bklet Draftv2.pdf PDF
Attch 2 Apdx J Antenna Twr Resp List draftv2.docx DOCX document
TL ISWMP Final Sept 2026v2.pdf PDF
Attch 3 CDRL A018 Solid Waste Rpt Draftv2.pdf PDF
Attch 3 CDRL A004 Program Mgmt Plan Draftv2.pdf PDF
Attch 3 CDRL A003 Data Mgmt Plan Draftv2.pdf PDF
Attch 4 FRAME Incentive Plan - draftv2.docx DOCX document
Attch 11 GFP TRACKER - 2026 - draftv2.xlsx XLSX spreadsheet
Attch 2 Apdx K L M N FRAME- draftv2.xlsx XLSX spreadsheet
Attch 6 DB WD CA20260014 (Mod 5)v2.pdf PDF
Attch 7 SCA WD 2015-5647 (Rev 29)v2.pdf PDF
Attch 3 CDRL A030 Maintenance Data Draftv2.pdf PDF
Attch 10 CRM Template - draftv2.xlsx XLSX spreadsheet
Attch 5 CBA IBEW 2024 12949 redactedv2.pdf PDF
Attch 3 CDRL A001 Phase-In Plan Draftv2.pdf PDF
TL CDRL A015 Work Order Status Rpt Samplev2.xlsx XLSX spreadsheet
TL CDRL A021 Cathodic Prot Bklet Samplev2.pdf PDF
Attch 3 Consolidated DID Files draftv2.pdf PDF
TL Pillar Point Outfall Drain Insp examplev2.pdf PDF
TL CDRL A014 PE Responsibility List Samplev2.xlsx XLSX spreadsheet
Attch 3 CDRL A025 RCM Plan Draftv2.pdf PDF
TL Service call historical datav2.xlsx XLSX spreadsheet
TL PTO 13968R4 and Part 70 Dec 2025v2.pdf PDF
TL HPGSA-PV-230-VTE-01242024v2.pdf PDF
Attch 9 Section M - draftv2.docx DOCX document
Attch 5 Appdx B Wage Rate Tables redactedv2.pdf PDF
TL CDRL A026 Corr Prev Ctrl Rpt Samplev2.pdf PDF
Attch 3 CDRL A027 Test Insp Rpt Draftv2.pdf PDF
Attch 6 DB WD CA20260018 (Mod 6)v2.pdf PDF
Attch 13 FRAME DD254_RFP - draftv2.pdf PDF
TL CDRL A022 Backflow Prev Sys Rpt Samplev2.pdf PDF
Attch 3 CDRL A005 Program Mgmt Rev Draftv2.pdf PDF
TL Pillar Point Launches or Sys Tests draftv2.pdf PDF
Attch 12 Workload Factors - draftv2.xlsx XLSX spreadsheet
Attch 2 Apdx I PE Inventory - draftv2.xlsx XLSX spreadsheet
TL CES Launch Operations Support Templatev2.pdf PDF
Attch 3 CDRL A022 Backflow Prev Rpt Draftv2.pdf PDF
TL CDRL A016 Daily Main Rpr Schdle Samplev2.pdf PDF
TL CDRL A018 Solid Waste Report Samplev2.pdf PDF
Attch 3 CDRL A006 Intg Cst Lbr Reimb Draftv2.pdf PDF
Show 40 more

Latest 50 of 124 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LOSC ISI Program

Bld. Number

N/A

A/R/F/O

Acceptable

Acceptable

Other

Acceptable

N/A

Acceptable

A/R/F/O

Acceptable

Acceptable

Acceptable

Acceptable

Acceptable

Acceptable

A/R/F/O

Rejectable

Acceptable

N/A

Other

Drain

Other Moderate corrosion on isolation valve

No Comments

Evidence of Leakage

Dents/Deformations

Insulation/CUI

Paint

Condition of Shell No Comments

Comments

No Comments

Welds

Head to Shell Welds

No Comments

Areas of minor corrosion, cracked/chipped

No Comments

No Comments

No Comments

No Comments

No CommentsGrayloc Connection

Skirt/Band Welds

Additional Component Welds

Bolts/Flanges

No Comments

No Comments

Comments

Dissimilar metals, leak at top head nozzle flange

Attachments

Longitudinal Weld(s)

Nozzle Welds

Support/Saddle Welds

The vessel was located at the High Pressure Gas Storage Area (HPGSA) on SLC-4. Access must be set up in advance with the facility operator, Space X.

Previous Inspection Documentation

Manufacturer & Year Built

Taylor Forge

Inspector/Level

Brett Strickland / II

Client

Call Henry Inc.

National Board Number

N/A

MAWP Temp. Range

6,000 PSI

Vessel ID

Location/Area

SLC-4/HPGSA

Commodity

Gaseous Nitrogen

Required Equipment

Exterior Pressure Vessel Inspection Report Number: CHI-PV-229-VTE-2024

Leak at top head nozzle flange

No Comments

Date

1/24/2024

Serial Number

750400-1V7

PV-229

Vessel Type

Horizontal Pressure Vessel

Exam Type

External

Ladder, flashlight, mirror, bubble leak, picks, hammer, ruler, camera

Condition of Heads

Room Number

-25 to 140 °F

VTE: 2023

GP-R-142002 (2010)

Access Notes

Vessel Inspection

CommentsPrimary

N/A

A/R/F/O

Acceptable

Acceptable

Acceptable

Acceptable

N/A

Other

Acceptable

N/A

N/A

N/A

N/A

A/R/F/O

Other

N/A

N/A

Rejectable

Acceptable

N/A

Inspection Findings/Code Violations

No Comments

No Comments

Additional Notes/Recommendations

The vessel isolation valve has areas of moderate corrosion. This item should be addressed before the corrosion impacts the function of the valve. The gauges on the panel were replaces and no longer have "No Calibration Required" (NCR) stickers on them. As these gauges are identical and serving an identical function as the previous gauges that had NCR this item has been listed as "Other". It is still recommended that the site owner register these new gauges as NCR and affix the NCR stickers to them. There was a fair amount of vegetation growing around and in the gaps of the vessel foundations. It is recommended that this be removed and controled as plant life/growth can cause damage to foundations.

Other

There was a slight offset of 7/8" between the concrete foundations and a gap of 1.25"-1.5". It is recommended that this continue to be monitored. There was not notable change in the offset severity from the previous years inspection. The relief valves were missing system reference designators. This is a violation of AFSPCMAN 91-710 LOSC Tailored

11.2.1.7.6.7. There were dissimilar metals on the bolt\flange assemblies that were not mutually isolated from each other.

It appeared that galvanized steel washers were in contact with stainless steel studs and nuts. This is a violation of

AFSPCMAN 91-710 11.3.1.5.6. There was a small leak at the top head nozzle flange (see pictures). The relief valves are outside the traditional one year calibration period.

Comments

Missing NCR sticker, @ 4,700 PSI

No Comments

No Comments

Vessel Inspection Cont. Vessel SN: 750400-1V7

Missing system designators

Comments

No Comments

No Comments

No Comments

Gauges

Sensors/Transducer

Sight Glass/Liquid Level

Relief Valve

Grounding

Anchor Bolting

Saddle/Steel Support Structure

Supports

Platforms

Grating

Handrails/Kickplates

Auxiliary Equipment

Pedestal/Grouting

Concrete Pad

Foundation

Containment

Ladders/Stairs

No Comments

No Comments

Offset/gap between foundations

No Comments

No Comments

No Comments

No Comments

No Comments

Skirts/Bands

Area Overview Vessel Overview

Nameplate Pressure Gauges/Relief Valves

External Pressure Vessel Inspection

External Photographs Vessel SN: 750400-1V7

Dissimilar Metals/Damaged Paint Leak on Head Flange

External Pressure Vessel Inspection

External Photographs Vessel SN: 750400-1V7

Offset Between Foundations Corrosion on Valve