| USAMS II MILESTONES V2 (ESTIMATE) | |||
| FA4600-07-R-0005 | |||
| Estimated Scope: $900M | |||
| Program Manager: JoAnn Murtha | |||
| Contracting Officer: Debra Simons | 23-Jul-08 | ||
| MILESTONE EVENT | BASELINE | SCHEDULE | COMPLETED DATE |
| Date Prepared | 6-Nov-06 | 6-Nov-06 | |
| Start Date | 6-Nov-06 | 6-Nov-06 | |
| GROUNDWORK | |||
| Engage w/PEO/CM | 0 | 6-Nov-06 | 6-Nov-06 |
| USSTRATCOM Approval to Proceed | 1 | 7-Nov-06 | 7-Nov-06 |
| PRE-SOLICITATION PHASE: | |||
| Begin Market Research | 0 | ||
| Sources Sought Synopsis | 0 | ||
| Sources Sought Capabilities Criteria Develop | 3 | 10-Nov-06 | 10-Nov-06 |
| Write Announcement | 5 | 15-Nov-06 | 15-Nov-06 |
| Post Sources Sought Synopsis | 2 | 17-Nov-06 | 17-Nov-06 |
| Industry Response | 25 | 12-Dec-06 | 12-Dec-06 |
| Start Capability Pkg Evaluations | 55 | 5-Feb-07 | 5-Feb-07 |
| Risk Analysis | 6 | 11-Feb-07 | 11-Feb-07 |
| Identify/Assess Risks | 1 | 12-Feb-07 | 12-Feb-07 |
| Determine Risk Strategy | 1 | 13-Feb-07 | 13-Feb-07 |
| Define Requirements | 15 | 28-Feb-07 | 28-Feb-07 |
| Draft PWS - Section 1 | 60 | 27-Apr-07 | 27-Apr-07 |
| Service Summary - Section 2 | 0 | 27-Apr-07 | 27-Apr-07 |
| CDRLs - Section 4 | 0 | 27-Apr-07 | 27-Apr-07 |
| QA Performance Plan | 0 | 27-Apr-07 | 27-Apr-07 |
| Draft Performance Work Statement Posted | 0 | 27-Apr-07 | 27-Apr-07 |
| Industry Day Preparation | 0 | 27-Apr-07 | 27-Apr-07 |
| Post Announcement to FedBizOpps | 0 | 27-Apr-07 | 27-Apr-07 |
| Hold Industry Day | 10 | 9-May-07 | 9-May-07 |
| Post Attendee Lists/Slides to FedBizOpps | 1 | 10-May-07 | 10-May-07 |
| Post Q&As to FedBizOpps | 14 | 24-May-07 | 24-May-07 |
| Labor Category Matrix | 3 | 27-May-07 | 27-May-07 |
| In House Review & Approval | 0 | 27-May-07 | 27-May-07 |
| Government Estimate | 10 | 7-Jun-07 | 7-Jun-07 |
| Draft Gov't Est | 0 | 7-Jun-07 | 7-Jun-07 |
| Review & Update | 22 | 25-Jun-07 | 25-Jun-07 |
| Acquisition Strategy Panel (ASP) | 0 | 25-Jun-07 | 25-Jun-07 |
| Draft ASP Slides | 6 | 1-Jul-07 | 1-Jul-07 |
| Murder Board | 4 | 5-Jul-07 | 5-Jul-07 |
| Update & Review | 10 | 16-Jul-07 | 16-Jul-07 |
| Forward Draft ASP Slides to PEO & HQ ACC | 0 | 16-Jul-07 | 16-Jul-07 |
| Update & Review | 5 | 20-Jul-07 | 20-Jul-07 |
| ASP Dry-Run Briefing to PEO/CM | 3 | 23-Jul-07 | 23-Jul-07 |
| ASP Brief to PEO/CM | 14 | 7-Aug-07 | 7-Aug-07 |
| Develop ASP Minutes | 14 | 21-Aug-07 | 21-Aug-07 |
| Acquisition Strategy Plan (ACQ Plan) | 0 | 21-Aug-07 | 21-Aug-07 |
| Draft ACQ Plan | 14 | 4-Sep-07 | 4-Sep-07 |
| Murder Board | 7 | 11-Sep-07 | 12-Sep-07 |
| Update & Review | 40 | 22-Oct-07 | 22-Oct-07 |
| HQ ACC Coordinated | 15 | 6-Nov-07 | 26-Nov-07 |
| Acquisition Plan Approved | 14 | 20-Nov-07 | 7-Dec-07 |
| Source Selection Plan (AFI 63.124) | 0 | 20-Nov-07 | 5-Nov-07 |
| Draft SSP | 0 | 20-Nov-07 | 5-Nov-07 |
| Murder Board | 0 | 20-Nov-07 | 16-Nov-07 |
| Update & Review | 2 | 22-Nov-07 | 10-Dec-07 |
| HQ ACC Coordinate | 7 | 29-Nov-07 | 18-Dec-07 |
| SSA (PEO/CM) Review & Approval of SSP | 14 | 13-Dec-07 | 11-Jan-08 |
| DRAFT RFP Development | 0 | 13-Dec-07 | 13-Dec-07 |
| CLIN Structure | 0 | 13-Dec-07 | 7-Nov-07 |
| Sections H & I Clauses | 0 | 13-Dec-07 | 17-Dec-07 |
| Sections L&M (Source Selection Criteria) | 0 | 13-Dec-07 | 11-Oct-07 |
| CDRL Requirements & DD Form 254 | 0 | 13-Dec-07 | 22-Jan-08 |
| PEO/CM Approval to Release Draft RFP | 14 | 27-Dec-07 | 22-Jan-08 |
| Post Draft RFP | 0 | 27-Dec-07 | 22-Jan-08 |
| Synopsis (15-days prior to RFP release) | 3 | 14-Jan-08 | 23-Jan-08 |
| SOLICITATION PHASE: | |||
| Business Clearance | 5 | 28-Jan-08 | 28-Jan-08 |
| Finalize RFP Package | 1 | 29-Jan-08 | 29-Jan-08 |
| Committee Review | 2 | 31-Jan-08 | 31-Jan-08 |
| Legal Review | 1 | 31-Jan-08 | 31-Jan-08 |
| HQ ACC Review & Approval to Synopsis | 7 | 6-Feb-08 | 6-Feb-08 |
| Resolution of Review Comments | 8 | 14-Feb-08 | 7-Feb-08 |
| PEO/CM Approval to Release RFP | 4 | 18-Feb-08 | 14-Apr-08 |
| RFP Release | 0 | 18-Feb-08 | 15-Feb-08 |
| Post RFP & Notify Major Cmds | 0 | 18-Feb-08 | 15-Feb-08 |
| PPT EVALUATION PHASE: | |||
| Proposals Due | 45 | 4-Apr-08 | 4-Apr-08 |
| Begin PPT Evaluations | 3 | 7-Apr-08 | 7-Apr-08 |
| Initial Evaluation | 0 | 7-Apr-08 | 7-Apr-08 |
| Rank by Price | 1 | 8-Apr-08 | 8-Apr-08 |
| Technical Evaluation | 6 | 14-Apr-08 | 14-Apr-08 |
| Past Performance Evaluation | 25 | 9-May-08 | 9-May-08 |
| Draft Initial Evaluation Briefing | 5 | 14-May-08 | 14-May-08 |
| Dry-Run Briefing | 7 | 15-May-08 | 22-May-08 |
| Update Briefing | 0 | 15-May-08 | 22-May-08 |
| Initial Evaluation Board (PEO/CM) | 4 | 26-May-08 | 28-May-08 |
| SSA Brief/Decision Document | 50 | 15-Jul-08 | 15-Jul-08 |
| PEO/CM Approval to Award | 7 | 22-Jul-08 | 22-Jul-08 |
| AWARD PHASE: | 0 | 22-Jul-08 | 22-Jul-08 |
| Contract Clearance | 0 | 22-Jul-08 | 22-Jul-08 |
| Legal Review | 0 | 22-Jul-08 | 22-Jul-08 |
| HQ ACC Review | 0 | 22-Jul-08 | 22-Jul-08 |
| Congressional Notification of Award | 0 | 22-Jul-08 | 22-Jul-08 |
| CONTRACT AWARD ANNOUNCEMENT | 3 | 25 Jul 08 (PM) | |
| DEBRIEFINGS | 4 | 29 Jul-6 Aug 08 | |
| Total Acquisition Time | 608 |