Attachment_21_-_Solicitation_Questions_ _Answers_2.pdf

PDF 161 KB Posted

Attached to
LRAFB Multiple Award Construction Contract (MACC) Federal contract opportunity
Solicitation number
FA4460-16-R-0002
Issued by
Department of the Air Force Air Mobility Command

About this file

Attachment 21 Questions Answers 2

View the file

Other files for this federal contract opportunity

Other files attached to LRAFB Multiple Award Construction Contract (MACC), newest first.
File Type Posted
Attachment_25_-_NKAK_15-1088_Rpr_Sus_Aircraft_MX_Shop_Restroom_Bldg_364_Revised_24_June_2016.pdf PDF
Attachment_27_-_ADA_Clarification.pdf PDF
FA4460-16-R-0002-0006.pdf PDF
Attachment_26_-_08_71_00_Door_Hardware.pdf PDF
Attachment_23_-_LRAFB_MACC_Site_Visit_Questions_ _Answers.pdf PDF
FA4460-16-R-0002-0005.pdf PDF
Attachment_24_-_B-364_Floorplans.pdf PDF
FA4460-16-R-0002-0004.pdf PDF
Attachment_22_-_Site_Visit_Attendance_Rosters.pdf PDF
FA4460-16-R-0002-0003.pdf PDF
Attachment_20_-_Solicitation_Questions_ _Answers.pdf PDF
NKAK_15-1088_Rpr_Acft_Mx_Shop_Restroom_B-364.pdf PDF
FA4460-16-R-0002-0002.pdf PDF
Attachment_19_-_Site_Visit_Attendee_Information.xlsx XLSX spreadsheet
FA4460-16-R-0002-U0001.pdf PDF
Attachment_18_-_LRAFB_Architectural_Compatibility_Guide.pdf PDF
Attachment_7_-_LRAFB_Architectural_Design_Guide_Supplement.pdf PDF
Attachment_6_-_Seed_Project_Package.zip ZIP file
Attachment_4_-_Past_Performance_Package.docx DOCX document
Attachment_12_-_LRAFB_Fire_Detection_and_Alarm_Systems.pdf PDF
FA4460-16-R-0002.pdf PDF
Attachment_15_-_LRAFB_Section_26_05_04_Raceways.pdf PDF
Attachment_14_-_LRAFB_Section_09_06_89_Typical_Finish_Schedule.pdf PDF
Attachment_13_-_LRAFB_Mechanical_Design_Criteria.pdf PDF
Attachment_3_-_C D_Report.doc DOC document
Attachment_5_-_Financial_Institution_Reference_Sheet.docx DOCX document
Attachment_1_-_EMIS_Instruction_Guide.doc DOC document
Attachment_8_-_LRAFB_Civil_Design_Criteria.pdf PDF
Attachment_16_-_LRAFB_Information.pdf PDF
Attachment_17_-_Scheduled_Government_Furnished_Property.pdf PDF
MACC_Statement_of_Work.pdf PDF
Attachment_2_-_Environmental_MOA.doc DOC document
Attachment_10_-_LRAFB_Computer_Telephone_Systems.pdf PDF
Attachment_11_-_LRAFB_Building_Mass_Notification_System.pdf PDF
Attachment_7_-_LRAFB_Architectural_Design_Guide_Supplement.pdf PDF
Attachment_9_-_LRAFB_Electrical_Design_Standards.pdf PDF
Show all 36

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No.: FA4460-16-R-0002

Attachment 21

LRAFB MACC Solicitation Questions & Answers 2

26 May 2016

Q1: Project Team. We are a GC/CM firm and will be leading the Design/Build team with others on our team, such as Architect, Engineers, Survey and Testing, Fire Protection, Utilities, among others, as our sub-consultants. May we include an Organizational Chart along with brief resumes about our structure and team, and if so, in which Volume should we include this information?

A: Such documents were not requested or required and will not be considered.

Q2: Proprietary Vendors. Since we’ll likely be involved with construction and/or renovation of sensitive areas on Little Rock AFB if awarded this project; who are the proprietary

IT/Telco/Mass Communication and Testing Consultants for Little Rock AFB?

A: This information will be provided if a contract is awarded.

Q3: Would you be willing to provide clarity around the various yellow highlighted areas in the Seed Project SOW document? Are we to assume these are the elements that will be considered for this Seed Project, and which will help to inform Volume 1 Pricing Proposal?

A: Please ignore the highlighting.

Q4: Are we expected to complete any other forms included in this Seed Project, such as, Page

4 Information sheet, or LRAFB ENVIRONMENTAL MANAGEMENT SYSTEM (EMS)

AWARENESS AND DOCUMENTATION in order to be deemed in Compliance with the

Overall MACC Submittal?

A: This document will only need to be completed if awarded the seed project.

Q5: May we include a Sample schedule in our Submission for the Seed Project, based on the

120 day Performance Period described in Seed Project SOW? And if so, in which Volume should we include this information?

A: You can but it will not be evaluated or considered.

Q6: Management Plan. Since the MACC is likely to involve a significant amount of organization, among other important key factors, will you want to hear from us at this time about how we intend to manage and deliver this work? And if so, in which Volume should we include this information?

A: See answer to question 5.

Solicitation No.: FA4460-16-R-0002

Attachment 21

Q7: Section L – General Instructions - 2.0.d: “The proposal acceptance period is specified in

Section A of the model contract/solicitation. The offeror shall make a clear statement in Section

A of the proposal documentation volume that the proposal is valid through this date.” Where should this statement be included? May we include this statement as part of a Cover Letter, or an Introduction/Statement of Qualifications in Volume 2?

A: See Section A block 17 of the solicitation FA4460-16-R-0002.

Q8: Question 9 of Attachment 20, Solicitation_Questions_Answers, references the fact that offerors are to "complete the necessary fill-ins and certifications in Sections C through K," then goes on to ask for confirmation that Sections C, D, and H do not exist. The answer given states that "these sections still exist in the solicitation." However, the original solicitation goes from

Section B - Supplies or Services and Prices (pp. 3-38) to Section E - Inspection and Acceptance

(pp. 39-40); Section G - Contract Administration Data begins on page 45, and Section I -

Contract Clauses begins on page 48 with no interruption from Section H; the sections also do not appear in the original solicitation nor in any of the amendments to date (0001, 0002, or

0003).Where are Sections C, D, and H?

A: Since these sections do not have anything in them they did not generate in the solicitation. Do not be concerned with these sections.

Q9: Per Section L of the subject referenced solicitation, in item 2.J, Teaming/Partners

Offerors, is it the Government’s intention that we submit a teaming agreement and letter of intent with our design firm with this submission, or is that to be submitted at a later date with subsequent task order proposals? In other words, do we have to submit teaming agreements for all parties we foresee utilizing in the future with this submission, or will we have the opportunity to do so per each task order solicitation issuance under this proposed MACC?

A: If teaming with another company a teaming agreement will be required. If the company is only being utilized as a subcontractor a teaming agreement is not required.

Q10: There seems to be some confusion with the PPQ’s. In Amendment 3, Q4, the

Government stated that the PPQ’s where not mandatory and are not required. Can you please confirm that if PPQ’s are not received by the deadline that our submission will not be rated less due to the short time frame for the deadline of June 3rd with the holiday as long as the CCASS reports are available on the past performance projects?

A: If no PPQs are received the past performance evaluation will be based upon the past performance submitted and information in PPIRS.

Q11: It is not specified in Section L where you wish for the bid bonds to be included, please advise?

A: See the answer to question 10 in attachment 20.