ATCH 9-AF66 Schedule of Material Submittals.xls

XLS spreadsheet 98 KB Posted

Attached to
Award Notice for Andrews AFB & Bolling AFB Simplified Acquisition of Base Engineering Requirements (SABER)
Solicitation number
FA4416-08-R0010
Issued by

About this file

Attachment 9 - Schedule of Material Submittals - 13 May 2008

View the file

Other files

File Type Posted
Amendment 04 FA4416-08-R-0010 —
Amendment 03 FA4416-08-R-0010 —
Contractor Questions and Government Answers —
1245.2.pdf PDF
Existing Utilities As Builts.pdf PDF
ETL Engineering Technical Letter 12-02.pdf PDF
1245.3.pdf PDF
1245.6.pdf PDF
1245.1.pdf PDF
1245.5.pdf PDF
1245.4.pdf PDF
Contractor Questions and Government Answers.doc DOC document
Amendment 02 FA4416-08-R-0010.doc DOC document
Amendment 01 FA4416-08-R-0010.doc DOC document
ATCH 5-Past Performance Questionnaire.doc DOC document
ATCH 8-Drawings BLDG 1245 Passenger Terminal.doc DOC document
ATCH 4b-MD080016.doc DOC document
ATCH 4c-MD080048.doc DOC document
ATCH 3b-MD080022.doc DOC document
ATCH 1-BAFB-AAFB SABER Specs —
ATCH 2b-DC080001.doc DOC document
ATCH 3a-MD080021.doc DOC document
ATCH 7-SOW Bldg 1245.doc DOC document
ATCH 2a-DC080003.doc DOC document
ATCH 3c-MD080035.doc DOC document
ATCH 6-Past Performance Reference List.doc DOC document
ATCH 4a-MD080057.doc DOC document
BAFB-AAFB SABER Solicitation —
Industry Day QA's.doc DOC document
Industry Day Attendees by Company Name.xls XLS spreadsheet
Industry Day Slides —
BAFB-AAFB SABER Specs —
DRAFT BAFB-AAFB SABER Solicitation —
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Material Submittals Schedule

SCHEDULE OF MATERIAL SUBMITTALSPROJECT NUMBERPROJECT TITLESOLICITATION / CONTRACT NO.
(To be completed by Project Engineer)(To be completed by Contract Administrator)
NUMBER OF COPIES REQUIRED
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALCERTIFICATION OF COMPLIANCESHOP DRAWINGSSAMPLESCOLOR SELECTIONMANUFACTURER'S RECOMMENDATIONMANUFACTURER'S WARRANTYCATALOG DATAOPERATING INSTRUCTIONSSCHEDULES, LISTINGS, REPORTS, PLANSTECHNICAL DATATEST REPORTSFIELD REPORTSREQUIRED SUBMISSION DATEDATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS
APPROVEDDISAPPROVED
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
Schedule of Material Submittals Template, Feb 05 (SAF/AQCP)

&RAttachment 9

FA4416-08-R-0010

Enter the due date from the Contractor (MM/DD/YY) Enter the date received from the Contractor. (MM/DD/YY) Enter the date submittal was given to CE for review. (MM/DD/YY) Enter the date the submittal is due back from CE

(MM/DD/YY)

Enter the Submittal Number Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

Enter date the Contractor was notified of submittal disapproval

(MM/DD/YY)

Enter Resubmittal Number Enter the submittal final approval date

(MM/DD/YY)

Enter any comments pertaining to the submittal