This document contains amended questions and responses regarding a solicitation for fire protection, emergency management, and emergency medical services. The solicitation seeks these services on a 24/7 basis for Cape Canaveral Space Force Station to ensure continuous mission support. Eligible small businesses are invited to propose with the understanding that approved subcontractors without facility clearances can be sponsored. Concurrence statements will be provided for vetted critical subcontractors to allow requirements flow down.
View the file
Other files
Show 40 more
Latest 50 of 56 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Source Selection Information -- See FAR 2.101 and 3.104 – Controlled Unclassified Information
Source Selection Information -- See FAR 2.101 and 3.104 – Controlled Unclassified Information
FA252122R0001 FEMS IV
Question and Answer
Q1
SOW: 1.1.4____________
Question: As a prime contractor proposing for this effort, who holds an active FCL, we are assuming that at award any participating subcontractors that do not hold an FCL can be sponsored for a Facility Clearance. Will the Government please confirm this assumption?
Answer: Yes. Refer to Attachment 47, DD Form 254 Instructions: pg.1 paragraph 1a.(4), pg.2 paragraph 2b.; pg.3 Item 7. Subcontractor(s); for instructions and guidance concerning sponsoring subcontractors.
Pg 2 paragraph 2.b Subcontract Number. Used by the prime contractor when there is a prime/subcontractor relationship. He prime contractor issuing the subcontract enters the subcontract number. The prime contractor’s number must also be entered in item 2a. (1) The applicable GCA determines whether there are any restriction or pre-approval requirement for subcontracting. (2) An individual DD Form would ordinarily be issued for each subcontract, even when there may be a string of subcontracts flowing from a prime contract.
*Attachment 43, Contractor Questions Government Responses question 32 has been amended.
Q2
SOW: 1.1.4____________
Question: Will the Government provide a concurrence statement for subcontractors without a current Facility Clearance that will allow the prime contractor to flow down the DD254?
Answer: Yes. Refer to Attachment 47, DD Form 254 Instructions: pg.1 paragraph 1a.(4), pg.2 paragraph 2b.; pg.3 Item 7. Subcontractor(s); for instructions and guidance concerning sponsoring subcontractors.
Pg 2 paragraph 2.b Subcontract Number. Used by the prime contractor when there is a prime/subcontractor relationship. He prime contractor issuing the subcontract enters the subcontract number. The prime contractor’s number must also be entered in item 2a. (1) The applicable GCA determines whether there are any restriction or pre-approval requirement for subcontracting. (2) An individual DD Form would ordinarily be issued for each subcontract, even when there may be a string of subcontracts flowing from a prime contract. A concurrence statement will be provided upon request and vetting subcontractor is eligible and a critical subcontractor performing on the contract.
*Attachment 43, Contractor Questions Government Responses question 33 has been amended.