This is a pricing template for an IDIQ contract that requires offerors to propose Other Direct Costs (ODC) indirect burden and handling rates.
Solicitation FA2396-26-R-B008 requires offerors to submit maximum not-to-exceed (NTE) Total ODC Indirect Burden and Handling Rates to be applied to ODC (CLIN 0008) for each year of the Period of Performance (POP). The proposed rates must be inclusive of all General & Administrative (G&A), material handling, overhead, indirect burdens, and any profit or fee applied to ODC, with no additional rates or fees permitted on ODC during contract performance. The rates cover seven contract periods: Year 1 (12/1/26–11/30/27), Year 2 (12/1/27–11/30/28), Year 3 (12/1/28–11/30/29), Year 4 (12/1/29–11/30/30), Year 5 (12/1/30–11/30/31), Year 6 (12/1/31–11/30/32), and a 6-month period (12/1/32–5/31/33). These rates will be incorporated into the basic IDIQ contract as binding ceilings that cannot be exceeded in future task orders, though contractors may propose lower rates. While required for contract incorporation, the rates will not be evaluated for realism or reasonableness at the IDIQ level or factor into the IDIQ award decision; however, price with applied capped rates will be evaluated during fair opportunity decisions for individual task orders.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 12 — Other Direct Costs (ODC) Burden and Handling Rate Matrix
Solicitation Number: FA2396-26-R-B008
Offeror Name: [Insert Offeror Name]
Instructions
Offerors shall propose a maximum not-to-exceed (NTE) Total ODC Indirect Burden and Handling Rate to be applied to ODC (CLIN 0008) for each year of the POP. This rate must be inclusive of all General & Administrative (G&A), material handling, overhead, indirect burdens, and any profit or fee applied to ODC. No other rates or fees of any kind shall be applied to ODC (CLIN 0008) during the life of the contract.
These rates will be incorporated into the resulting basic IDIQ contract as binding ceilings. For all future task orders, the contractor shall propose a rate equal to or lower than this ceiling, but shall not exceed it. While these rates are required for contract incorporation purposes, they will not be evaluated for realism or reasonableness at the IDIQ level, nor will they factor into the IDIQ award decision. Price, including the application of the capped rates on ODC (CLIN 0008), will be evaluated as a factor in the fair opportunity decision for each individual task order.
Please enter the proposed NTE Total ODC Indirect Burden and Handling Rate for each year of the POP below.
POP Proposed NTE Total ODC Indirect Burden and Handling Rate for ODC (CLIN 0008)
Year 1 (12/1/26 – 11/30/27) ____________________ %
Year 2 (12/1/27 – 11/30/28) ____________________ %
Year 3 (12/1/28 – 11/30/29) ____________________ %
Year 4 (12/1/29 – 11/30/30) ____________________ %
Year 5 (12/1/30 – 11/30/31) ____________________ %
Year 6 (12/1/31 – 11/30/32) ____________________ %
6 month (12/1/32 – 5/31/33) ____________________ %
| Attachment 12 — Other Direct Costs (ODC) Burden and Handling Rate Matrix |
| Instructions |
File details come from the government source that posted it. Updated .