Section F – 0200000 Management and Administration Section F 0200000 Deliveries or Performance
DELIVERABLES
| Spec Item |
| Form Attachment Number |
| Deliverable Title |
| Date (s) of Submission |
| Distribution |
| Frequency |
| Original |
| Copies (including original) |
| 2.2.1 |
| N/A |
| Request to Work Outside Government’s Regular Working Hours |
| At least seven calendar days prior to requested day. |
| KO and COR |
| 1 |
| As required |
| 2.3.1 |
| N/A |
| Sign-in Sheets and Minutes for Review and Comments |
| Within two working days |
| KO, COR and all attendees |
| 1 |
| As Required |
| 2.3.3.1-2.3.3.3 |
| N/A |
| Sign-in Sheets and Minutes Final Revision |
| Within two working days |
| KO, COR and all attendees |
| 1 |
| As Required |
| 2.3.4 |
| N/A |
| Permits and Licenses |
| Before work commences and as requested by the KO. |
| KO and COR |
| 2 |
| As specified |
| 2.3.5 |
| N/A |
| Certificate of Insurance |
| Within 15 calendar days prior to contract start. |
| KO and COR |
| 2 |
| As specified |
| 2.3.5.1 |
| N/A |
| Written Notice of cancellation or material change in policy coverage |
| At least 30 calendar days prior to cancellation or material change in policy coverage |
| KO and COR |
| 1 |
| As required |
| 2.6.2 |
| N/A |
| Status Updates |
| Within 2 hours of the inquiry during regular working hours, and by 0800 the following work day for inquiries after regular working hours |
| KO and COR |
| 1 |
| As required |
| 2.6.4 |
| N/A |
| Status of Deliverables |
| Within 2 hours of the inquiry during regular working hours, and by 0800 the following work day for inquiries after regular working hours |
| KO and COR |
| 1 |
| As required |
| 2.6.5 |
| N/A |
| Service Interruptions |
| At least five working days in advance |
| KO and COR |
| 1 |
| As required |
| 2.6.7.1 |
| N/A |
| Quality Management Plan |
| Within 15 calendar days prior to contract start and within seven calendar days of changes. |
| KO and COR |
| 2 |
| As specified |
| 2.6.7.2 |
| N/A |
| QC Inspection File |
| Within five calendar days of completion/ termination of the contract. |
| KO and COR |
| 2 |
| As specified |
| 2.6.7.3 |
| N/A |
| Contractor Quality Inspection and Surveillance Report |
| First work day of each month. |
| KO and COR |
| 2 |
| Monthly |
| 2.7.1 |
| N/A |
| List of Key Personnel and Qualifications |
| Within 15 calendar days prior to contract start |
| KO and COR |
| 2 |
| As specified |
| 2.7.1 |
| N/A |
| Organizational Chart |
| Within 15 calendar days prior to contract start |
| KO and COR |
| 2 |
| As specified |
| 2.7.2.6 |
| N/A |
| Proof of Legal Residency |
| Prior to be admitted to site of work. |
| KO and COR |
| 1 |
| As specified |
| 2.8.1 |
| N/A |
| Employee List |
| Within 15 calendar days prior to contract start and within one calendar day of changes. |
| KO and COR |
| 2 |
| Maintain Current |
| 2.8.4.2 |
| N/A |
| DBIDs Credential |
| As Specified |
| KO and COR |
| 1 |
| As required |
| 2.9.1 |
| N/A |
| Accident Prevention Plan |
| Within 15 calendar days prior to contract start and within seven calendar days of changes. |
| KO and COR |
| 2 |
| As specified |
| 2.9.2 |
| N/A |
| Activity Hazard Analysis |
| Together with the Accident Prevention Plan and for changes. |
| KO and COR |
| 2 |
| As specified |
| 2.9.3 |
| N/A |
| Safety and Occupational Health (SOH) Risks and Compliance Plans |
| Together with the Accident Prevention Plan and for changes. |
| KO and COR |
| 2 |
| As specified |
| 2.9.5 |
| N/A |
| NAVFAC Contractor Incident Reporting System (CIRS) |
| Within five calendar days of accident. |
| KO and COR |
| 2 |
| As required |
| 2.9.5 |
| N/A |
| Weight Handling Equipment Accident Report |
| Within 15 working days of accident. |
| KO and COR |
| 2 |
| As required |
| 2.9.5 |
| N/A |
| Crane and Rigging Gear Near Miss Report |
| Within 15 working days of accident. |
| KO and COR |
| 2 |
| As required |
| 2.9.7 |
| N/A |
| Monthly On-Site Labor Report |
| First work day of each month. |
| KO and COR |
| 2 |
| Monthly |
| 2.9.8 |
| N/A |
| OSHA Citations and Violations Corrective Action Report |
| Within 48 hours after receiving a citation. |
| KO and COR |
| 2 |
| As required |
| 2.9.9 |
| N/A |
| Contractor safety records |
| Upon request. |
| KO and COR |
| 1 |
| As required |
| 2.9.10 |
| N/A |
| Safety Certifications |
| Within 15 calendar days prior to contract start and as old certifications expire. |
| KO and COR |
| 2 |
| As required |
| 2.10 |
| N/A |
| EMS Goals and Policy Measurement Information |
| Upon request. |
| KO and COR |
| 1 |
| As required |
| 2.10.2.1 |
| N/A |
| Sampling Plan |
| Within 5 calendar days of sampling |
| KO and COR |
| 1 |
| As required |
| 2.10.2.2 |
| N/A |
| Class I and II ODS Report |
| Within 24 hours following delivery of refrigerant to DLA |
| KO and COR |
| 2 |
| As required |
| 2.10.2.2 |
| N/A |
| OTIS database update |
| As Specified |
| KO and COR |
| 1 |
| As required |
| 2.10.2.2 |
| N/A |
| Refrigerant Recovery Equipment |
| As Specified |
| KO and COR |
| 1 |
| As Required |
| 2.10.2.3 |
| J-0200000-05 |
| Solid Waste Management Report |
| Monthly and Annually by October 10th |
| KO and COR |
| 1 |
| As Required |
| 2.10.2.4 |
| N/A |
| Waste Stream Determination |
| Within 30 calendar days prior to start of contract performance and within 14 days of identification of any new waste stream. |
| KO and COR |
| 1 |
| As Required |
| 2.10.2.6 |
| N/A |
| Fuel and hazardous substance spill notification |
| Within 15 minutes of discovery |
| Regional Dispatch Center |
| 1 |
| As required |
| 2.10.2.6 |
| N/A |
| Fuel and hazardous substance spill notification |
| As soon as possible but not more 24 hours of discovery |
| KO and COR |
| 1 |
| As required |
| 2.10.2.6 |
| N/A |
| Fuel and hazardous substance spill report |
| Within 48 hours of discovery |
| KO and COR |
| 1 |
| As required |
| 2.10.2.7 |
| N/A |
| Emergency Planning and Community Right-To-Know Act (EPCRA) Report |
| Within 15 calendar days prior to contract start and not less than 10 working days prior to planned use of hazardous material. |
| KO and COR |
| 2 |
| As specified |
| 2.10.2.7 |
| J-0200000-05 |
| Contractor Hazardous Material Inventory Log |
| Within 15 calendar days after the end of each calendar year and at termination of the contract. |
| KO and COR |
| 2 |
| Annually |
| 2.10.2.11 |
| N/A |
| Asbestos Containing Material (ACM) |
| Verbally notify the KO and COR within one hour and follow-up with written Notification within 24 hours |
| KO and COR |
| 2 |
| As specified |
| 2.10.2.12 |
| N/A |
| Hazardous Air Pollutants |
| First work day of each month |
| KO and COR |
| 2 |
| As specified |
| 2.10.3 |
| N/A |
| Sustainable Procurement and Practices Plan |
| Within 15 calendar days prior to contract start and within 15 calendar days after exercised option periods. |
| KO and COR |
| 2 |
| Annually |
| 2.10.3 |
| N/A |
| Sustainable Delivery of Services Report |
| Within five calendar days after each contract period. |
| KO and COR |
| 2 |
| Annually |
| 2.10.3.2 |
| N/A |
| Recovered Material Certification |
| As specified |
| KO and COR |
| 2 |
| When a product containing recovered materials is equal to or better than the original and could be used. |
| 2.11 |
| N/A |
| Mission Essential Contractor Services Plan |
| Within 15 calendar days prior to contract start and within seven calendar days of changes. |
| KO and COR |
| 2 |
| As Required |
| 2.11 |
| N/A |
| Disaster Preparedness/ Mission Critical/Mission Essential Personnel |
| Within 15 calendar days prior to contract start and within seven calendar days of changes. |
| KO and COR |
| 2 |
| As specified |
| 2.12 |
| N/A |
| Technical Library Table of Contents |
| Within 15 calendar days after contract start and within seven calendar days of changes |
| KO and COR |
| 2 |
| As specified |
| 2.14.1 |
| N/A |
| Notification to the Government for Work Above the Recurring Work Limitations and Rough Order of Magnitude |
| Within two hours of identification |
| KO and COR |
| 2 |
| As required |
| 2.14.1 |
| N/A |
| Detailed Scope of Work and Detailed Estimate |
| Within two work days |
| KO and COR |
| 1 |
| As required |
| 2.15.1.1 |
| N/A |
| Over and Above Work Proposals |
| Within two working days following receipt of request |
| KO |
| 1 |
| As required |
| 2.16 |
| N/A |
| Phase Out Plan |
| Within 90 day of last Option Period |
| KO and COR |
| 2 |
| As Required |
Vital HVAC Mission Critical Jacksonville, Florida Page 6 of 6