This is a Technical Specification document for an elevator modernization project at COP St. John's Building in Portland, Oregon, issued under VDA No. ECS-70234 with an effective date of March 22, 2025. The project requires the elevator contractor to furnish and install a complete modernization package for Elevator #1, including a new car station, hall stations, controller/selector, electrical wiring, power unit, seismic requirements for the hydraulic system, door controller, car top inspection station, door hardware, firefighter's emergency operation system, and all ADA-compliant components. The contractor must retain the existing car speed, capacity, and entrance size while verifying exact measurements on-site and ensuring fit and finish of all surface-mounted fixtures. All work is specified as a turnkey project with the elevator contractor responsible for coordinating any required sub-tier work and completing the modernization on schedule without incurring additional costs to the owner.

The scope includes significant ancillary work such as providing a new main line disconnect with auxiliary contacts for battery lowering, machine room ventilation to maintain temperatures not exceeding 95 degrees Fahrenheit 95 percent of the time, illumination in the machine room meeting 200 lux code minimums and pit illumination meeting 10 foot-candles, 120-volt 15-amp disconnects for car lighting and intercom systems, flashing hat signals for phase 1 fire service, fire recall initiation device interfaces, and patching of hoistway and machine room openings with fire-resistant material. All costs associated with licenses, permits, inspections, testing, personnel, and equipment necessary to complete the modernization are to be included in the base bid, with any overtime work required to meet the project schedule also at no additional cost to the owner.

View the file

Other files

File Type Posted
Exhibit B - City 1900 Building Technical Specifications.pdf PDF
Exhibit D - North Precinct Building Technical Specifications.pdf PDF
Addendum 01 ITB 0000676 Pre-Bid Meeting Details.pdf PDF
Exhibit C1 - City East Precinct Building As Builts.pdf PDF
Exhibit C2 - East Precinct - Architectural and Plumbing As Builts.pdf PDF
Notice of Intent to Award ITB 2676.pdf PDF
Invitation to Bid 00002676 Pre-Bid Meeting Attendance Sheet.pdf PDF
Exhibit E4 - Portland Control Center Sump Piping.pdf PDF
Exhibit F - Alternate 1 - St. Johns Building Technical Specification.pdf PDF
Exhibit E - Portland Communication Center Technical Specifications.pdf PDF
Exhibit C - City East Precinct Building Technical Specifications.pdf PDF
Exhibit D3 - North Precinct Sump Piping~1.pdf PDF
Exhibit E3 - Portland Control Center HVAC outdoor unit placement.pdf PDF
Addendum 04 ITB 00002676 Address Exceptions and Deviations.pdf PDF
ITB 00002676 Elevator Modernization Proposal Receipt Record.pdf PDF
Addendum 05 ITB 00002676 Plumbing Scope Clarifications.pdf PDF
Exhibit E2 - PCC Architectural As Builts.pdf PDF
Addendum 02 ITB 00002676 Pre-Bid Meeting Details.pdf PDF
Exhibit B2 -1900 Building Plumbing As Builts.pdf PDF
Attachment 4 - Buyspeed Submittal Instructions~1.pdf PDF
Exhibit D1 - North Precinct Building As Builts.pdf PDF
ITB 00002676 Elevator Modernization Construction.pdf PDF
Exhibit B1 - 1900 Building Architectural As Builts.pdf PDF
Addendum 03 ITB 00002676 Update Close Date and Add Documents~1.pdf PDF
Exhibit E1 - Portland Communication Center As Builts.pdf PDF
Exhibit D2 - North Precinct Architectural As Builts.pdf PDF
Updated Exhibit A - ITB 00002676 Elevator Modernization Services Contract.pdf PDF
Attachment 5 - PPB Background Check Forms.pdf PDF
ITB 00002676 Elevator Modernization Bid Tabulation~1.pdf PDF
Attachment 2 - ITB 00002676 Bid Pricing Form.xlsx XLSX spreadsheet
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

COP St. John’s Bldg 14 24 00 - 6 Elevator #1 Portland, OR VDA No. ECS-70234 3/22/2025

B. Obtain all licenses and permits, and pay all fees and all other costs, including making arrangements for all inspections and tests required by regulating agencies (AHJ), in accordance with this Elevator Specifications.

C. File necessary plans, prepare documents, and obtain necessary approval of governmental departments having jurisdiction and required certificates of inspection for work in accordance with the Elevator Specification.

D. Elevator Contractor is not relieved from furnishing and installing work shown or specified which may be beyond requirements of ordinances, laws, regulations and codes.

E. Supply personnel and equipment for all tests and final inspections. All costs of such testing and inspections shall be included in the Base Bid.

1.05 MODERNIZATION REQUIREMENTS

A. Work Included by Elevator Contractor:

1. Furnish and install car station, hall stations, controller/selector, electrical wiring in

Machine Room/car/hoistway, power unit, seismic requirements for hydraulic system, door controller, car top inspection station, door hardware, Firefighter's Emergency Operation, all requirements of The Americans with Disability Act (ADA) and all other elevator components as listed in this Elevator Specification.

2. Retain existing car speed, capacity, and elevator entrance size.

3. Verify exact distances between points shown on their Shop Drawings by actual measurements at the site. This includes fit and finish of surface mount Hall fixtures and lanterns covering existing cutouts.

4. Owner shall incur no extra cost for the Elevator Modernization as stated in the elevator specifications. Provide any and all overtime work in order to complete the total Elevator Modernization on schedule.

5. All existing elevator equipment that is being retained/reused shall be placed in first-class operating condition by the Elevator Contractor at no extra cost to the Owner.

B. All work below to be included in Elevator Contractor scope as a Turnkey Project. Elevator contractor will be responsible for coordinating any sub tier work required to complete the job.

Work shall include:

1. Provide new main line disconnect with auxiliary contacts for battery lowering.

2. Provide Machine Room ventilation to maintain the temperature at not more than ninety-five degrees Fahrenheit (95° F) for ninety-five percent (95%) of the time unless a lower temperature is specified by the elevator equipment manufacturer.

3. Provide illumination in the elevator Machine Room sufficient to meet code minimum of 200 lx (19 fc). Identify the location of the supply side of the overcurrent protective device as per NFPA-70, Article 620.

4. Provide illumination in the elevator Pit sufficient to meet code (currently a minimum of 10 fc). per NFPA-70, Article 620.

5. Provide 120Vac 15A Car light disconnect with overcurrent protection in Machine Room

6. Provide 120Vac 15A disconnect for Intercom system or other devices.

7. Provide flashing hat signal for phase 1 fire service.

8. Provide and interface fire recall initiation devices needed in lobbies, Machine Room and

Hoistway.

9. Patch any openings in Hoistway and Machine Room with fire resistant material.