Addendum 04 ITB 00002676 Address Exceptions and Deviations.pdf

PDF 199 KB Posted

Attached to
Elevator Modernization Construction, for 7 elevators at 5 different sites
Solicitation number
00002676
Issued by
Oregon

About this file

This addendum document issued by the City of Portland, Oregon's Procurement Services division modifies the specifications for ITB No. 00002676 for Elevator Modernization Services. The addendum was issued on January 16, 2026, with responses due by 4:00 pm on January 23, 2026. The document addresses six bidder-requested exceptions and deviations to the original contract specifications and indicates whether the City accepts or rejects each modification request. The addendum replaces Exhibit A with an updated version reflecting the City's decisions on these contract modifications and includes the pre-bid meeting attendance list as an attachment to the solicitation.

Of the six requested modifications, the City accepted three changes: updating Section 3.4.3 Late Delivery to include limitation of liability language for special, indirect, or consequential damages; removing Section 5.2 Grant Funding entirely; and modifying Section 6.1.1 Hold Harmless and Indemnification to specify that indemnification applies to wrongful actions, errors, or omissions. The City rejected three requests: declining to expand the Force Majeure definition in Section 1, refusing to add language exempting contractor confidential and proprietary information from inspection and audit under Sections 3.8-3.9, and declining the contractor's proposed modifications to Section 5.14 Ownership of Property. However, the City did modify Section 5.14 with its own revisions, adding provisions requiring the contractor to supply repairable and maintainable work products and to assist with system transitions and data migration if replacement occurs.

View the file

Other files

File Type Posted
Exhibit B - City 1900 Building Technical Specifications.pdf PDF
Exhibit D - North Precinct Building Technical Specifications.pdf PDF
Addendum 01 ITB 0000676 Pre-Bid Meeting Details.pdf PDF
Exhibit C1 - City East Precinct Building As Builts.pdf PDF
Exhibit C2 - East Precinct - Architectural and Plumbing As Builts.pdf PDF
Exhibit F1 - Alternate 1 - Technical Specification Page 4 Modification.pdf PDF
Notice of Intent to Award ITB 2676.pdf PDF
Invitation to Bid 00002676 Pre-Bid Meeting Attendance Sheet.pdf PDF
Exhibit E4 - Portland Control Center Sump Piping.pdf PDF
Exhibit F - Alternate 1 - St. Johns Building Technical Specification.pdf PDF
Exhibit E - Portland Communication Center Technical Specifications.pdf PDF
Exhibit C - City East Precinct Building Technical Specifications.pdf PDF
Exhibit D3 - North Precinct Sump Piping~1.pdf PDF
Exhibit E3 - Portland Control Center HVAC outdoor unit placement.pdf PDF
ITB 00002676 Elevator Modernization Proposal Receipt Record.pdf PDF
Addendum 05 ITB 00002676 Plumbing Scope Clarifications.pdf PDF
Exhibit E2 - PCC Architectural As Builts.pdf PDF
Addendum 02 ITB 00002676 Pre-Bid Meeting Details.pdf PDF
Exhibit B2 -1900 Building Plumbing As Builts.pdf PDF
Attachment 4 - Buyspeed Submittal Instructions~1.pdf PDF
Exhibit D1 - North Precinct Building As Builts.pdf PDF
ITB 00002676 Elevator Modernization Construction.pdf PDF
Exhibit B1 - 1900 Building Architectural As Builts.pdf PDF
Addendum 03 ITB 00002676 Update Close Date and Add Documents~1.pdf PDF
Exhibit E1 - Portland Communication Center As Builts.pdf PDF
Exhibit D2 - North Precinct Architectural As Builts.pdf PDF
Updated Exhibit A - ITB 00002676 Elevator Modernization Services Contract.pdf PDF
Attachment 5 - PPB Background Check Forms.pdf PDF
ITB 00002676 Elevator Modernization Bid Tabulation~1.pdf PDF
Attachment 2 - ITB 00002676 Bid Pricing Form.xlsx XLSX spreadsheet
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Page | 1

Procureme nt Se rvices City O p erations City of Portland , Oregon

@PortlandGov portlandgov

PortlandORGov

January 16, 2026

ADDENDUM NO. 04

ITB No. 00002676

FOR

Elevator Modernization Services

Responses Due: January 23, 2026 By: 4:00 pm

This Addendum provides changes to the specifications for the above-entitled project to be considered by each respondent. Any changes made by this Addendum to said specifications offset only the portion of the words or paragraphs specifically mentioned herein, and the balance of the specifications remain in full force. It is the responsibility of all respondents to conform to this addendum.

This Addendum shall:

1. Remove Exhibit A - ITB 00002676 Elevator Modernization Services Contract and replace it with the document titled Updated Exhibit A - ITB 00002676 Elevator Modernization Services Contract to reflect bidder requested exceptions and deviations.

2. Add the pre-bid meeting attendance list as an attachment to this solicitation.

3. Address the bidder requested contract exceptions and deviations in the table below.

Request No.

Requested Exceptions and Deviations

Contract Section 1 Definitions: Force Majeure

Requested Modification Update Section 1 Definition of Force Majeure to read the following:

“Force Majeure Event” (8/20) means, with respect to a Party, any event or circumstance, regardless of whether it was foreseeable, that was not caused by that Party and that prevents a Party from complying with any of its obligations under this Contract, neither party shall be liable for any loss, damage or delay nor be found to be in default or breach due to any cause beyond it’s reasonable control including, but not limited to, acts of God or nature;

fire; explosion; theft; floods; water; weather; traffic conditions; transportation, material or labor disruptions; epidemic, pandemic, quarantine or other local, state, or federal government action in response thereto; sabotage; cyber-security; national emergency; act of terrorism; earthquake; riot; civil commotion; war; vandalism; national or local labor strikes, Sylvester Donelson, Jr. Sara Morrissey Michael Jordan Chief Procurement Officer Deputy City Administrator Chief Administrative Officer https://twitter.com/PortlandGov https://www.instagram.com/PortlandGov/ https://www.facebook.com/PortlandORGov

Page | 2 lockouts, other labor disputes; misuse, abuse, neglect, mischief, or work by others (collectively “Causes Beyond Reasonable Control”).”

City of Portland Response The City rejects this modification to the Contract and will keep the current language.

Contract Section

3.4.3 Late Delivery

Requested Modification Update Section 3.4.3 Late Delivery to read: “Under no circumstances shall either party be liable for special, indirect, or consequential damages of any kind including, but not limited to, loss of goodwill, loss of business opportunity, additional financing costs or loss of use of any equipment or property. This limitation of liability also applies to indemnity of third-party claims.”

City of Portland Response The City accepts this change and will reflect the updated language in the Attachment Updated Exhibit A - ITB 00002676 Elevator Modernization Services Contract provided with this Addendum.

Contract Section 3.8-3.9 Records and Audits

Requested Exception Add the following language to Section 3.8-3.9: “Contractor does not agree to any inspection, audit, or copy of an of Contractor confidential, proprietary, or trade secret information, data, or documents including, without limitation, financials.”

City of Portland Response The City rejects this modification to the Contract and will keep the current language.

Contract Section

5.2 Grant Funding

Requested Modification Remove Section 5.2 Grant Funding from Exhibit A - ITB 00002676 Elevator Modernization Services Contract

City of Portland Response The City accepts this change and will reflect the removal of Section 5.2 Grant Funding in the Attachment Updated Exhibit A - ITB 00002676 Elevator Modernization Services Contract provided with this Addendum.

Contract Section

6.1 Hold Harmless and Indemnification Subsection 6.1.1

Requested Exception Update Subsection 6.1.1 to read: “Contractor shall indemnify, defend and hold harmless the City of Portland, its officers, agents, and employees from all claims, demands, suits, and actions for all losses, damages, liabilities, costs and expenses (including all attorney's fees and costs), caused by the negligent acts, willful misconduct, resulting from or arising out of the actions, errors, or omissions of Contractor or its officers, employees, Subcontractors, or agents under this Contract.”

City of Portland Response The City shall modify Subsection 6.1.1 to read, “"Contractor shall indemnify, defend and hold harmless the City of Portland, its officers, agents, and employees from claims, demands, suits, and actions for all losses, damages, liabilities, costs and expenses (including all

Page | 3 attorney's fees and costs), resulting from or arising out of the wrongful actions, errors, or omissions of Contractor or its officers, employees, Subcontractors, or agents under this Contract." This update will be reflected in the Attachment Updated Exhibit A - ITB 00002676 Elevator Modernization Services Contract provided with this Addendum.

Contract Section

5.14 Ownership of Property

Requested Modification Update Section 5.14 Ownership of Property to Read: Ownership of Property. All work product produced by the Contractor under this Contract is the exclusive property of the City.

“Work Product” includes, but is not limited to: research, reports, computer programs, manuals, drawings, recordings, photographs, artwork and any data or information in any form, but only to the extent that the foregoing are specifically developed by the Contractor solely for the City’s exclusive use only (and no other client of the Contractor) and the City was expressly contemplated to be the exclusive owner of such information under a separate written agreement. The Contractor and the City intend that such Work Product shall be deemed “work made for hire” of which the City shall be deemed the author. If for any reason a Work Product is deemed not to b a “work made for hire,” the Contractor hereby irrevocably assigns and transfers to the City all right, title and interest in such Work Product, whether arising from copyright, patent, trademark, trade secret, or any other state or federal intellectual property law or doctrines. Contractor shall obtain such interests and execute all documents necessary to fully vest such rights in the City. Contractor waives all rights relating to work product, including any rights arising under 17 USC 106A, or any other rights of authorship, identification approval, restriction or limitation of use or subsequent modifications. If the Contractor is an architect, the Work Product is the property of the Consultant-Architect, and by execution of this Contract, the Contractor-Architect grants the City an exclusive and irrevocable license to use that Work Product.

Notwithstanding the above, all preexisting trademarks, services marks, patents, copyrights, trade secrets, and other proprietary rights of Contractor are and will remain the exclusive property of Contractor. Contractor hereby grants to the City a non-exclusive, perpetual, irrevocable license, with the right to sublicense, to disclose, copy, distribute, display, perform, prepare derivative works of and otherwise exploit use any pre-existing Intellectual Property Rights.”

City of Portland Response The City shall modify Section 5.14 Ownership of Property to read, "5.14 Ownership of Property. (09/25) All work product produced by the Contractor under this Contract is the exclusive property of the City. “Work Product” includes, but is not limited to: research, reports, computer programs, manuals, drawings, recordings, photographs, artwork and any data or information in any form. The Contractor and the City intend that such Work Product shall be deemed “work made for hire” of which the City shall be deemed the author. If for any reason a Work Product is deemed not to be a “work made for hire,” the Contractor hereby irrevocably assigns and transfers to the City all right, title and interest in such Work Product, whether arising from copyright, patent, trademark, trade secret, or any other state or federal intellectual property law or doctrines. Contractor shall obtain such interests and execute all documents necessary to fully vest such rights in the City. Contractor waives all rights relating to work product, including any rights arising under 17 USC 106A, or any other rights of authorship, identification or approval, restriction or limitation on use or subsequent modifications. If the Contractor is an architect, the Work Product is the property of the Consultant-Architect, and by execution of this Contract, the Contractor-Architect grants the City an exclusive and irrevocable license to use that Work Product.

Notwithstanding the above, all pre-existing trademarks, services marks, patents, copyrights, trade secrets, and other proprietary rights of Contractor are and will remain the exclusive property of Contractor. Contractor hereby grants to the City a non-exclusive, perpetual, Page | 4 irrevocable license, with the right to sublicense, to disclose, copy, distribute, display, perform, prepare derivative works of and otherwise exploit any pre-existing Intellectual Property Rights incorporated into the Work Product(s).

Contractor shall not supply, modify, or install Work Product that would render the System unrepairable or unmaintainable by one or more competitor elevator companies. In the event the City replaces the Work Product or any component of the Work Product, including computer programs integral to the operation, repair, or maintenance of the System, Contractor shall make reasonable efforts to (1) assist the City in the transition or migration to the new System, including but not limited to knowledge transfer from experienced personnel,

(2) cooperate with the City on development of a transition plan, (3) provide City-requested Documentation and non-proprietary technical information, training and work materials, and reports, and (4) provide retrieval and migration of City data stored within the System or Work Product in a format acceptable to the City.” This update will be reflected in the Attachment Updated Exhibit A - ITB 00002676 Elevator Modernization Services Contract provided with this Addendum.

Please direct all questions and concerns to Kristina Kolata, Senior Procurement Specialist at 971-509-0713.

End of Addendum bt :kmk