About this file
This is a Sales Tax Exemption Procedure document issued by Volusia County, Florida, for the Tomoka Farms Road Landfill Southeast Area Construction Cell I project. The procedure outlines the process for the prime contractor to obtain sales tax exemption on materials and services purchased for the project using the County's Consumer's Certificate of Exemption issued by the Florida Department of Revenue. The prime contractor must submit requisitions within 15 calendar days of the Notice to Proceed, with vendors required to register with the County and provide their Taxpayer Identification Number and certification documentation. The County's Purchasing and Contracts Division processes requisitions into purchase orders and deductive change orders to the prime contractor's contract price, reflecting the applicable sales tax savings. A non-mandatory pre-bid meeting is scheduled for March 12, 2026, at 11:00 AM with virtual Microsoft Teams attendance available, and the deadline for submitting questions is March 19, 2026, at 11:59 PM. Bids are due by 3:00 PM on April 2, 2026, through the County's eProcurement Portal. Substantial completion is required within 244 days of Notice to Proceed, with final completion required within 365 days total.
The document details a five-step process involving requisition origination, County receipt and review, processing through the accounting system, invoice verification by the prime contractor and County Construction Manager, and direct payment to the vendor by County Accounting. The prime contractor is responsible for submitting complete requisitions with all required information, receiving and inspecting materials, approving invoices after verifying conforming goods, and maintaining comprehensive records for County inspection. The County is obligated to issue purchase orders and change orders timely, provide designated contacts for status inquiries, and return incomplete or incorrect documents. An example computation shows total sales tax savings of $6,025 on a $100,000 roofing materials purchase, reducing the overall project cost through deductive change orders. The procedure complies with Florida Administrative Code Rule 12A-1.094 and applies to all tangible personal property, services, and materials purchased for the landfill construction project located at 1990 Tomoka Farms Road, Port Orange, Florida 32128.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sales Tax Exemption Procedure Page 1 of 4
SALES TAX EXEMPTION PROCEDURE
FOR CONSTRUCTION MANAGEMENT PROJECTS
Background
The State of Florida Department of Revenue has issued the County of Volusia (hereinafter “County”) a Consumer’s Certificate of Exemption. This Certificate exempts the County from the payment of Florida sales and use tax on real property rented, transient rental property rented, tangible personal property purchased or rented, or services purchased.
The following is a sample sales tax savings computation:
Description Value Roofing materials from vendor (paid by County): $100,000.00 6.5% Sales tax savings (on the first $5,000.00): $325.00 6.0% Sales tax savings (on remaining price): $5,700.00 Total: $106,025.00
Deductive change order to Prime Contractor's awarded contract price for the project : $106,025.00
Total sales tax savings: $6,025.00
Code Compliance
This Procedure complies with the Rule 12A-1.094 of Florida Administrative Code.
Definitions
1. CONSTRUCTION CHANGE ORDER (“CO”). A document issued to the Prime Contractor by County’s Purchasing and Contracts Division modifying the contract price or time.
2. FRIEGHT ON BOARD. F.O.B. Destination. Title shall pass to the County of Volusia on delivery of the conforming goods to the designated location. The risk of loss or damage in transit shall be upon the vendor/seller, delivery shall not be complete until the goods and/or services have been received, inspected, and accepted by the County of Volusia.
3. PROJECT. Tomoka Farms Road Landfill Southeast Area Landfill Construction Cell I located at 1990 Tomoka Farms Road, Port Orange, Florida 32128.
Sales Tax Exemption Procedure Page 2 of 4
4. PURCHASE ORDER (“PO”). A document issued to the Vendor by the County Purchasing and Contracts Division, after receipt of a properly completed and executed
REQUISITION.
5. REQUISITION. A document issued by the County and submitted by the Prime Contractor to the County Construction Manager for material qualified for sales tax exemption.
6. RQS. Electronic request through the County’s accounting system for goods and/or services with information necessary to create a PURCHASE ORDER.
FLOW OF DOCUMENTS
Step 1. REQUISITION ORIGINATION. Within 15 calendar days of the Notice to Proceed, the Prime Contractor shall submit to the Consultant (if applicable) and County Construction Manager the completed REQUISITION form(s) for approval. The REQUISITION shall be completed and signed by the designated authorized representative of the Prime Contractor. If the vendor(s) listed on the REQUISITION form(s) is/are not registered with the County, the Prime Contractor shall instruct them to register and request copies of the Vendor’s Taxpayer Identification Number (TIN) and Certification to attach to the REQUISITION form (s). Note: REQUISITION forms may be submitted prior to the Notice to Proceed, but will not be processed until after the Notice to Proceed is issued.
Step 2. RECEIPT OF REQUISITION BY COUNTY. The REQUISITION shall be date stamped, reviewed and delivered for processing into a PO along with a deductive CHANGE ORDER to Prime Contractor’s contract price for the material plus applicable sales tax.
Step 3. PROCESSING THE REQUISITION. The deductive CHANGE ORDER will be processed prior to the creation of the PO to the Vendor. Upon receipt of an executed deductive CHANGE ORDER, the County Construction Manager shall initiate an RQS in the County’s accounting system, which will be processed into a PO to the Vendor.
Purchasing and Contracts will E-mail the PO to the Vendor and the CO to the Prime Contractor. A copy of any special instructions and County Tax Exemption Certificate will be E-mailed with the PO.
Step 4. INVOICE PROCESSING. The Vendor shall issue an invoice to the County after the material is delivered to the site. The Prime Contractor shall receive the invoice, verify it against the delivered material via physical inspection, approve it by signature, and then forward it, within five (5) business days of the date receipt of the invoice, to the County Construction Manager. The County Construction Manager shall then verify, approve by signature, and submit it for payment by the County.
Step 5. DIRECT PAYMENT. County Accounting shall pay Vendor directly.
Sales Tax Exemption Procedure Page 3 of 4
County Responsibilities
1. County shall issue POs in a timely fashion.
2. County shall provide the proper REQUISITION and CO forms to the Prime
Contractor, if needed; however, the Prime Contractor’s forms are acceptable provided it contains all the information required in paragraph 2 of Prime Contractor’s Responsibilities.
3. County shall assign, process, and issue POs and COs as required.
4. County shall return to the Prime Contractor all documents that are incomplete or incorrect.
5. County shall provide a designated contact person with whom direct inquiries may be made regarding the status of REQUISITIONS, POs, and COs.
Prime Contractor Responsibilities
1. Prior to the Notice to Proceed, the pre-construction meeting will be conducted. At the meeting the Contractor shall provide a list of typed names, signatures and contact information of those representatives duly authorized to act on behalf of the Prime Contractor to process requisition and change order requests for purchases made for this project.
2. Contractor shall submit a complete and correct requisition for processing. The
REQUISITION shall include, but not be limited to:
a. Firm name, contact, address, telephone, fax and email
b. Shipping address
c. Item no., Quantity, Unit, and Unit Price of each item to be ordered
d. Description (Brand, model & specification number)
e. Extended and total price of order
f. Authorized signatures
g. Any special instructions
h. Completed TIN and Certification form, required
4. Contractor shall submit PO changes to the County construction manager for approval as required using approved format.
5. Contractor shall receive, inspect, test (if appropriate), store, and secure material ordered. Approve invoices after verifying receipt of conforming material.
6. Contractor shall advise County of any discrepancies in a timely manner prior to payment by County Finance. All prompt payment discounts will accrue solely to the County’s benefit. All payments by the County are subject to Florida’s Prompt Payment Act (ss. 218.70-218.80, Florida Statutes).
Sales Tax Exemption Procedure Page 4 of 4
7. Contractor shall add to the Builder’s Risk insurance, the “County of Volusia is a loss payee for the Project.” Such insurance shall cover the full value of items received and accepted.
8. Contractor shall maintain records of all items purchased under this Procedure.
These records shall be available for inspection upon County’s request.