Exhibit_S_-_CQA_Plan.pdf
PDF 2 MB Posted
- Solicitation number
- 26-B-51IF
- Issued by
- Volusia County, Florida
About this file
Construction Quality Assurance Plan Summary
This is a Construction Quality Assurance (CQA) Plan document prepared by SCS Engineers for Volusia County, Florida, in support of the Southeast Expansion Area Cell 1 Construction project at the Tomoka Farms Road Landfill. The plan establishes comprehensive quality assurance and quality control procedures for the construction of approximately 30 acres of landfill, a lined leachate surface impoundment, truck unloading area, and associated pump stations and forcemain. The project requires conformance to Florida Administrative Code Chapter 62-701.400 and includes detailed specifications for earth material testing, geomembrane installation, geotextile placement, and geocomposite deployment. The CQA Plan defines roles and responsibilities for all parties including the Permitting Agency (Florida Department of Environmental Protection), Owner (Volusia County), Design Engineer, CQA Consultant, Construction Quality Assurance Representative (CQAR), Contractor, manufacturers, installers, and testing laboratories. Key deliverables include daily field reports, observation and testing reports, photodocumentation, progress reports, record drawings, and a final Certification of Construction Completion report.
The CQA Plan establishes detailed testing protocols and acceptance criteria for all materials and construction activities. Pre-construction qualification and conformance testing is required for excavated subgrade soil, general fill, structural fill, protective cover soil, and topsoil, with testing conducted by independent CQC and CQA soil laboratories. Geomembrane manufacturing quality control requires testing of resin properties, polymer density, melt index, and oxidation induction time, with conformance testing performed on samples at specified frequencies before shipment to the project site. Field quality control for the textured 60-mil and 80-mil HDPE geomembranes includes non-destructive testing (vacuum box and air pressure testing) of all seams as work progresses and destructive seam strength testing at a rate of one test per 500 linear feet of welded seam, with minimum peel strength requirements of 98 lb/in width for 60-mil wedge welds and 121 lb/in width for 80-mil wedge welds. The plan specifies that no deficient materials or workmanship shall be accepted, with all non-conforming work subject to correction at the Contractor's expense or removal from the work area at the discretion of the CQA Consultant.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Southeast Expansion Area Construction Quality Assurance Plan Volusia County, Florida
Volusia County 1990 Tomoka Farms Road Port Orange, Florida, 32128
Florida Board of Professional Engineers Certificate No. 00004892
10150 Highland Manor Drive, Suite 320 Tampa, FL 33610
(813) 621-0080
Project No. 09219088.13 | 3/23/2026
Southeast Expansion Area Construction Quality Assurance Plan Volusia County, Florida
Submitted to:
Florida Department of Environmental Protection 2600 Blair Stone Road, MS 4565 Tallahassee, Florida 33239
Prepared for:
Volusia County 1990 Tomoka Farms Road Port Orange, Florida, 32128
Project No. 09219088.13 | 3/23/2026
Table of Contents
Section Page
Volusia County Construction Quality Assurance Plan Southeast Expansion Area 3/23/2026 i
INTRODUCTION
Purpose Discrepancies Between Documents
DEFINITIONS
Construction Quality Assurance Construction Quality Control Manufacturer Quality Control Manufacturer Quality Assurance Geosynthetic Materials Geomembrane Materials
PERSONNEL, ORGANIZATION, AND RESPONSIBILITIES
PERMITTING AGENCY
OWNER
DESIGN ENGINEER
CQA CONSULTANT
CQAR
CONTRACTOR
CONTRACTOR’S REPRESENTATIVE
GEOSYNTHETICS MANUFACTURER
GEOSYNTHETICS INSTALLER
CQA GEOSYNTHETICS LABORATORY
CQA SOILS LABORATORY
CQC SOIL LABORATORY
SURVEYOR
Non-conformance Record Drawings
COMMUNICATION AND PROJECT MEETINGS
Pre-Construction Meeting Progress Meetings Construction Resolution Meetings Geomembrane Pre-Installation Meeting
EARTH MATERIAL QUALITY ASSURANCE
General pre-construction Materials qualification Testing pre-construction Materials CONFORMANCE Testing
Excavated Subgrade Soil Testing General Fill Soil Testing Structural Fill Soil Testing Protective Cover Soil Testing Topsoil Testing
Construction Quality Evaluation ii
Deficiencies Notification, Repair, and Retesting
Subbase Preparation and Acceptance Subbase Repair
Protective Cover Soil Layer Anchor Trenches
Geomembrane Material TEXTURED 60 mil and 80 mil Geomembrane Manufacturing and Delivery
Geomembrane Manufacturing Manufacturer Quality Control Documentation Manufacturer Quality Control Certificates Manufacturer Quality Control Testing
Delivery, Handling, and Storage Delivery and Handling Storage
Geomembrane Conformance Testing 60 mil and 80 mil Conformance Sample Collection Conformance Testing
Geomembrane Field Quality Control 60 mil and 80 mil Panel Identification Panel Placement and Deployment
Personnel Requirement Seam Layout Seaming Methods Seam Preparation Seaming Procedures Extrusion Welding Hot Wedge Welding Trial Welds
Field Seam Testing Non-destructive Testing Destructive Testing
CQA GEOSYNTHETICS LABORATORY
Procedures for Destructive Test Failures
Defects, Repairs, and Wrinkles Geocomposite Material Manufacturing and Delivery
Geocomposite Manufacturing and Delivery Manufacturing
Manufacturer Quality Control Documentation Manufacturer Quality Control Certificates iii
Manufacturer Quality Control Testing Delivery, Handling, and Storage
Delivery and Handling Storage
Geocomposite Conformance Testing Conformance Sample Collection Conformance Testing
Geocomposite Field Quality Control Deployment Roll Joining Methods Roll Joining Requirements Defects and Repairs Placement of Soil Materials
Geotextile Material Geotextile Manufacturing and Delivery
Manufacturing Manufacturer Quality Control Documentation Manufacturer Quality Control Certificates Manufacturer Quality Control Testing
Delivery, Handling, and Storage Delivery and Handling Storage
Geotextile Field Quality Control Installation Seaming Procedures Defects and Repairs Placement of Soil Materials
Documentation Reports
Daily Logs and Summary Reports Observation and Testing Reports Photodocumentation And Reporting Data Sheets Design and/or TECHNICAL SPECIFICATIONS Changes Progress Reports Record Drawings Certification Report
Tables
TABLE 02220-1 EXCAVATED SUBGRADE SOIL QUALIFICATION TESTING
TABLE 02220-2 GENERAL FILL SOIL QUALIFICATION TESTING
TABLE 02220-3 STRUCTURAL FILL SOIL QUALIFICATION TESTING
iv
TABLE 02220-4 PROTECTIVE COVER LAYER GRADATION REQUIREMENTS
TABLE 02220-5 PROTECTIVE COVER MATERIAL QUALIFICATION TESTING
TABLE 02766-1 RESIN MQC REQUIREMENTS
TABLE 02776-2 HDPE LINER MANUFACTURING QUALITY CONTROL TESTING
TABLE 02766-3 REQUIRED GEOMEMBRANE CONFORMANCE TESTING
TABLE 02766-4 MINIMUM PEEL AND SHEAR SEAM STRENGTH VALUES
TABLE 02931-1 RESIN MQC TESTING
TABLE 02931-2 GEONET MQC TESTING
TABLE 02931-3 GEOTEXTILE MQC TESTING
TABLE 02931-4 GEOCOMPOSITE MQC TESTING
TABLE 02931-1 GEONET PROPERTIES
TABLE 02931-2 GEOTEXTILE PROPERTIES
TABLE 02931-3 GEOCOMPOSITE PROPERTIES
TABLE 02940-1 GEOTEXTILE PROPERTIES
ATTACHMENTS
ATTACHMENT A DAILY FIELD REPORT
ATTACHMENT B CERTIFICATE OF SUBBASE ACCEPTANCE
ATTACHMENT C GEOMEMBRANE PLACEMENT LOG
ATTACHMENT D GEOMEMBRANE SEAMING LOG
ATTACHMENT E GEOMEMBRANE REPAIR LOG
ATTACHMENT F TRIAL WELD LOG
ATTACHMENT G NON-DESTRUCTIVE TEST LOG
ATTACHMENT H DESTRUCTIVE TEST LOG
ATTACHMENT I PANEL PLACEMENT LOG
INTRODUCTION
PURPOSE
This Construction Quality Assurance Plan (CQA Plan) addresses the Construction Quality Assurance (CQA) and Construction Quality Control (CQC) testing, procedures, and requirements for the construction activities of the Southeast Expansion Area and leachate surface impoundment located at the Tomoka Farms Road Landfill.
The WORK for this CONTRACT consists of constructing an approximately 30-acre landfill, lined leachate pond, truck unloading area, and associated pumpstations and forcemain at the Tomoka Farms Road Landfill located in Volusia County, Florida referred to as the Southeast Expansion Area Cell 1 Construction (PROJECT). The WORK to be performed by the CONTRACTOR consists of, but is not limited to, furnishing all labor, materials, equipment, tools, transportation, incidentals and operations, and performing all WORK necessary to complete the PROJECT in accordance with the CONTRACT DRAWINGS and TECHNICAL SPECIFICATIONS.
This CQA Plan supplements the CONSTRUCTION DRAWINGS and TECHNICAL SPECIFICATIONS and has been prepared to meet the requirements outlined in the Florida Administrative Code (FAC), Chapter 62-701.400.
Detailed Manufacturer Quality Control (MQC), Manufacturer Quality Assurance (MQA), and CQC requirements, which are the responsibility of organizations that manufacture materials and CONTRACTORS that install these materials is provided in the TECHNICAL SPECIFICATIONS. Upon completion of the PROJECT a Certification of Construction Completion report will be prepared by the CQA CONSULTANT documenting construction was performed in accordance with the design intent, CONSTRUCTION DRAWINGS and TECHNICAL SPECIFICATIONS.
DISCREPANCIES BETWEEN DOCUMENTS
This CQA Plan is intended to be a supporting document to improve the overall implementation of the WORK. The CQA Plan may be more or less specific than the TECHNICAL SPECIFICATIONS and conflicts may potentially exist between the documents. The CONTRACTOR is instructed to bring discrepancies immediately to the attention of the DESIGN ENGINEER and/or CQA CONSULTANT for resolution. The DESIGN ENGINEER has the sole authority to determine the resolution of discrepancies existing within the CONSTRUCTION DRAWINGS and TECHNICAL SPECIFICATIONS.
Unless otherwise determined by the DESIGN ENGINEER, the more stringent requirement shall be the controlling resolution.
DEFINITIONS
Whenever the terms listed below are used, the intent and meaning will be interpreted as indicated.
CONSTRUCTION QUALITY ASSURANCE
CQA is a planned system of activities and actions, employed by the OWNER, that provides the OWNER and PERMITTING AGENCY assurance the PROJECT was constructed as specified in the Construction Permit, CONSTRUCTION DRAWINGS, and TECHNICAL SPECIFICATIONS. CQA refers to measures taken by the DESIGN ENGINEER, CQA CONSULTANT, and OWNER to determine compliance with the requirements for materials and workmanship as stated in the CONSTRUCTION DRAWINGS and TECHNICAL SPECIFICATIONS for the PROJECT. CQA includes construction observation and monitoring, materials testing, verifications, audits, and evaluations of materials and workmanship necessary to determine and document the quality of the WORK. CQA refers to measures taken by the CQA organization to assess if the INSTALLERS and CONTRACTORS are in compliance with the CONSTRUCTION DRAWINGS and TECHNICAL SPECIFICATIONS for the PROJECT.
CONSTRUCTION QUALITY CONTROL
CQC refers to those actions taken by MANUFACTURERS, FABRICATORS, INSTALLERS, and CONTRACTOR to ensure materials and workmanship meet the requirements of the CONSTRUCTION DRAWINGS, TECHNICAL SPECIFICATIONS, and CQA Plan. CQC is a planned system of observations used to directly monitor and control the quality of a construction PROJECT. CQC is performed by the CONTRACTOR or specialty SUBCONTRACTORS, and is necessary to achieve quality in the constructed or installed system. CQC refers to measures taken by the CONTRACTOR or specialty SUBCONTRACTORS to determine compliance with the requirements for materials and workmanship as stated in the CONSTRUCTION DRAWINGS and TECHNICAL SPECIFICATIONS for the PROJECT. In the case of soils, CQC is provided by the CONTRACTOR. In the case of geosynthetics, CQC is provided by the MANUFACTURERS and INSTALLERS of the various geosynthetics
MANUFACTURER QUALITY CONTROL
MQC is a planned system of inspections used to directly monitor and control the manufacture of a material that is factory-originated. MQC is normally performed by the MANUFACTURER of materials and is necessary to ensure minimum (or maximum) specified values in the manufactured product.
MQC refers to measures taken by the MANUFACTURER to determine compliance with the requirements for materials and workmanship as stated in the CONSTRUCTION DRAWINGS and TECHNICAL SPECIFICATIONS for the PROJECT.
MANUFACTURER QUALITY ASSURANCE
MQA is a planned system of activities that provides assurance that materials were manufactured as specified in the CONSTRUCTION DRAWINGS and TECHNICAL SPECIFICATIONS for the PROJECT. MQA includes manufacturing facility inspections, verifications, audits, and evaluation of raw materials and products to assess the quality of the manufactured materials. MQA refers to measures taken by the MQA organization to determine if the MANUFACTURER of the product is in compliance with the CONSTRUCTION DRAWINGS and TECHNICAL SPECIFICATIONS for the PROJECT.
GEOSYNTHETIC MATERIALS
For the purposes of this CQA Plan, the term “geosynthetic” is applied to materials manufactured from synthetic polymers (such as geomembranes, geotextiles, and geocomposites).
GEOMEMBRANE MATERIALS
For the purposes of this CQA Plan, the term “geomembrane” is applied to flexible membrane liners.
More specifically, “geomembrane” refers to synthetic liners, with a textured surface for increased friction (top and bottom). A textured high-density geomembrane shall be used on this PROJECT.
PERSONNEL, ORGANIZATION, AND RESPONSIBILITIES
The principal parties involved in the CQA and CQC for the PROJECT include the PERMITTING AGENCY, OWNER, DESIGN ENGINEER, CQA CONSULTANT, CONSTRUCTION QUALITY ASSURANCE
REPRESENTATIVE (CQAR), CONTRACTOR, CONTRACTOR’S REPRESENTATIVE, GEOSYNTHETICS
MANUFACTURER, GEOSYNTHETICS INSTALLER, CQA GEOSYNTHETICS LABORATORY, CQC SOIL
LABORATORY, CQA SOILS LABORATORY, and SURVEYOR. The general responsibilities of each of these parties are described in the following subsections. The responsibility and/or authority of a given party may be modified or expanded by the OWNER, DESIGN ENGINEER, and/or CQA CONSULTANT as dictated by specific needs as WORK progresses. Refer to Figure 3-1 Organizational Chart below that shows the relationships of the parties involved in the Tomoka Farms Road Landfill Southeast Expansion Area.
PERMITTING AGENCY
The PERMITTING AGENCY is authorized to issue the Construction Permit based on review and acceptance of the permit application by the DESIGN ENGINEER. The PERMITTING AGENCY must have issued a Construction Permit for the PROJECT prior to commencement of WORK. As construction progresses, the PERMITTING AGENCY has the responsibility and authority to review and accept design revisions or requests for variances submitted by the DESIGN ENGINEER on behalf of the OWNER.
OWNER
The OWNER is responsible for the facility, including coordinating the design and construction of the Tomoka Farms Road Landfill Southeast Expansion Area. This responsibility includes compliance with the Construction Permit and the submission of CQA documentation demonstrating the PROJECT was constructed in accordance with the CONSTRUCTION DRAWINGS, TECHNICAL SPECIFICATIONS, and Construction Permit for the PROJECT. The OWNER has the authority to contract and manage parties charged with design, CQA and construction. The OWNER also has the authority to accept or reject CONSTRUCTION DRAWINGS, TECHNICAL SPECIFICATIONS, CQA Plan, reports, recommendations of the CQA CONSULTANT, and the materials and workmanship of the CONTRACTORS.
DESIGN ENGINEER
The DESIGN ENGINEER is the individual or firm responsible for the design and preparation of the CONSTRUCTION DRAWINGS, TECHNICAL SPECIFICATIONS, and CQA Plan. The DESIGN ENGINEER must approve all design and TECHNICAL SPECIFICATIONS changes, CQA procedural changes, and design clarifications necessitated during construction. The DESIGN ENGINEER shall be a professional skilled in the appropriate discipline, certified or licensed as required by regulation, and shall be familiar with applicable regulatory requirements.
CQA CONSULTANT
CQA shall be the responsibility of the OWNER and CQA CONSULTANT who will act as the OWNER’S representative. The CQA CONSULTANT is a party independent of the CONTRACTORS, MANUFACTURERS, and INSTALLERS, and if applicable, the DESIGN ENGINEER. The CQA CONSULTANT is responsible during construction for field testing and observing and documenting activities related to construction, the Construction Permit, and the CQA Plan. The CQA CONSULTANT will be represented on-site by a CQAR, as appropriate, to observe construction. In general, the responsibilities and authorities of the CQA CONSULTANT include, but are not limited to, the following:
Understanding the CONSTRUCTION DRAWINGS, TECHNICAL SPECIFICATIONS, and Construction Permit in relation to all aspects of the CQA Plan.
Securing documents from the DESIGN ENGINEER and OWNER which approve deviations from the CONSTRUCTION DRAWINGS, TECHNICAL SPECIFICATIONS, Construction Permit and/or CQA Plan.
Implementation of this CQA Plan and coordination with the CQA GEOSYNTHETICS LABORATORY and CQA SOILS LABORATORY for material sample collection, testing, and confirming the results of the test data.
Maintaining open lines of communication with other parties involved in construction.
Verifying material quality through submittals provided by the CONTRACTOR.
Reviewing CQC and MQC test reports and material certifications provided by the
CONTRACTOR.
Compiling record construction data.
Preparation of a Certification of Construction Completion report.
CQAR
The CQAR is a qualified individual assigned by the CQA CONSULTANT to be responsible for observing and documenting activities related to the CQA of the production and installation of the WORK on behalf of the CQA CONSULTANT and OWNER. In general, the responsibilities and authorities of the CQAR include, but are not limited to, the following:
Completing a daily report documenting WORK. A typical daily report with the required information is provided in ATTACHMENT A DAILY FIELD REPORT.
Performing independent on-site observation of the WORK in progress to assess compliance with the CONSTRUCTION DRAWINGS, TECHNICAL SPECIFICATIONS, Construction Permit, and CQA Plan.
Documenting and reporting deviations from the CONSTRUCTION DRAWINGS, TECHNICAL SPECIFICATIONS, Construction Permit, and CQA Plan to the OWNER, DESIGN ENGINEER, and
CONTRACTOR.
Documenting, rejecting, and determining the extent of defective or non-conforming WORK.
Immediately notifying the OWNER, DESIGN ENGINEER and/or CQA CONSULTANT, and CONTRACTOR of defective or non-conforming WORK.
Verifying and documenting corrective measures were implemented as required by the OWNER, DESIGN ENGINEER, and/or CQA CONSULTANT.
Verifying the INSTALLER’S test equipment meets testing and calibration requirements and those tests conducted are according to procedures defined in the TECHNICAL SPECIFICATIONS and CQA Plan.
Documenting and recording CQA activities and collecting data required for the CQA CONSULTANT to prepare the Certification of Construction Completion report that will be submitted to the appropriate PERMITTING AGENCY.
Compiling photographic documentation of the WORK.
CONTRACTOR
The CONTRACTOR is anyone with whom the OWNER enters into a contractual AGREEMENT to perform construction activities for the PROJECT. The CONTRACTOR shall meet the qualifications as indicated in the CONTRACT DOCUMENTS. The CONTRACTOR shall always provide a representative during any construction activity onsite. In general, the responsibilities of the CONTRACTOR include, but are not limited to, the following:
The CONTRACTOR is responsible for the WORK in conformance with the CONTRACT DOCUMENTS and for completion of the PROJECT and site-specific responsibilities as required by the CONSTRUCTION DRAWINGS, TECHNICAL SPECIFICATIONS, Construction Permit, and CQA Plan.
Submittal coordination by the MANUFACTURERS and INSTALLERS as required by the TECHNICAL SPECIFICATIONS and the overall CQC for the PROJECT.
Scheduling and coordination of the required WORK with the MANUFACTURERS and the INSTALLERS to complete the PROJECT.
Furnishing as-built drawings and a copy of complete documentation for the WORK.
Daily updating of the CONSTRUCTION DRAWINGS onsite and for all deviations from those drawings. All deviations must be initialed as approved by the CQAR onsite.
Completing a video inspection of all on-site roadways documenting the conditions prior to the WORK being started. Verify record data is obtained and provided to the OWNER and CQA
CONSULTANT.
o Record survey information and associated point data shall be obtained on the same datum and coordinate basis as the CONSTRUCTION DRAWINGS and shall be provided by the CONTRACTOR.
CONTRACTOR’S REPRESENTATIVE
The CONTRACTOR’S REPRESENTATIVE is a qualified individual assigned by the CONTRACTOR to represent them onsite at all times during performance of the WORK. The CONTRACTOR’S REPRESENTATIVE shall meet the qualifications as indicated in the CONTRACT DOCUMENTS. The CONTRACTOR’S REPRESENTATIVE shall have the authority to direct and instruct their crew and SUBCONTRACTORS. In general, the responsibilities of the CONTRACTOR’S REPRESENTATIVE include, but are not limited to, the following:
Coordinating and supervising their crew and SUBCONTRACTORS work onsite.
Ensuring construction activities are conducted in accordance with the CONSTRUCTION DRAWINGS, TECHNICAL SPECIFICATIONS, Construction Permit, and CQA Plan.
Communicating with the CQAR any discrepancies between the CONSTRUCTION DRAWINGS, TECHNICAL SPECIFICATIONS, and field conditions.
Attending all meetings held on the PROJECT as a representative of the CONTRACTOR.
Keeping a daily log of all construction activities onsite.
Proposing alternative construction methods, where necessary, to the CQAR for approval and signature, as required in the TECHNICAL SPECIFICATIONS and CQA Plan.
GEOSYNTHETICS MANUFACTURER
The GEOSYNTHETICS MANUFACTURER is responsible for production of geosynthetics including geomembranes, geocomposites, geotextiles, and geosynthetic clay liners (GCL) which meet the requirements as specified in the CONSTRUCTION DRAWINGS, TECHNICAL SPECIFICATIONS, and CQA Plan for the PROJECT. The GEOSYNTHETICS MANUFACTURER shall meet the qualifications as indicated in the CONTRACT DOCUMENTS. In general, the responsibilities of the GEOSYNTHETICS MANUFACTURER include, but are not limited to, the following:
Providing documentation regarding the characteristics of the raw material, final product, testing performed to verify the characteristics, and the MQC measures performed during manufacturing.
Loading and transporting geosynthetics from the manufacturing plant to the PROJECT site and is responsible for any damage to the geosynthetics which may occur during these operations.
GEOSYNTHETICS INSTALLER
The GEOSYNTHETICS INSTALLER is responsible for unloading, field handling, seaming, storing, and temporarily loading against wind and other aspects of the geosynthetics installation in accordance with the CONSTRUCTION DRAWINGS, TECHNICAL SPECIFICATIONS, Construction Permit, and CQA Plan. The GEOSYNTHETICS INSTALLER shall meet the qualifications as indicated in the CONTRACT DOCUMENTS. In general, the responsibilities of the GEOSYNTHETICS INSTALLER include, but are not limited to, the following:
The preparation of the panel layout drawings, including dimensions and details, and for providing the installation schedule and list of proposed field personnel and their qualifications.
During installation, the GEOSYNTHETICS INSTALLER is responsible for providing CQC documentation and “Certificate of Subbase Acceptance” before placement of the geosynthetic clay liner (GCL).
Upon completion of the geosynthetics installation, the GEOSYNTHETICS INSTALLER shall provide the installation documentation, installation warranties, and MANUFACTURER warranties to the CQA CONSULTANT.
CQA GEOSYNTHETICS LABORATORY
The CQA GEOSYNTHETICS LABORATORY is a third party, independent from the OWNER, MANUFACTURERS, and GEOSYNTHETICS INSTALLER. The CQA GEOSYNTHETICS LABORATORY service cannot be provided by any party involved with the manufacture or installation of any of the geosynthetic components. The CQA CONSULTANT is required to coordinate the CQA GEOSYNTHETICS LABORATORY work schedule and type and quantity of tests. In general, the responsibilities of the CQA GEOSYNTHETICS LABORATORY include, but are not limited to, the following:
Performing the laboratory tests on geosynthetic materials as required by the CONSTRUCTION DRAWINGS, TECHNICAL SPECIFICATIONS, Construction Permit, and CQA Plan.
Providing documentation of testing equipment used, analytical test results, and test methods followed. All results will be reported to the CQA CONSULTANT.
CQA SOILS LABORATORY
The CQA SOILS LABORATORY is responsible for performing the conformance laboratory testing on soils and aggregate as required by the CONSTRUCTION DRAWINGS, TECHNICAL SPECIFICATIONS, Construction Permit, and CQA Plan during placement. The CQA CONSULTANT is required to coordinate the CQA SOILS LABORATORY work schedule and type and quantity of tests. In general, the responsibilities of the CQA SOILS LABORATORY include, but are not limited to, the following:
Performing the conformance laboratory tests on soil materials as required by the CONSTRUCTION DRAWINGS, TECHNICAL SPECIFICATIONS, Construction Permit, and CQA Plan.
Providing documentation of testing equipment used, analytical test results, and test methods followed. All results will be reported to the CQA CONSULTANT.
CQC SOIL LABORATORY
The CQC SOIL LABORATORY is responsible for performing the pre-qualification laboratory testing on soils and aggregates as required by the CONSTRUCTION DRAWINGS, TECHNICAL SPECIFICATIONS, Construction Permit, and CQA Plan from proposed borrow sources prior to implementation into the PROJECT. The CONTRACTOR is required to coordinate the CQC SOIL LABORATORY work schedule and type and quantity of tests. In general, the responsibilities of the CQC SOIL LABORATORY include, but are not limited to, the following:
Performing laboratory tests on soil materials as required by the CONSTRUCTION DRAWINGS, TECHNICAL SPECIFICATIONS, Construction Permit, and CQA Plan.
Providing documentation of testing equipment used, analytical test results, and test methods followed. All test results, and an indication of whether they pass or fail, will be reported to the
CQA CONSULTANT.
SURVEYOR
The SURVEYOR is the responsibility of the CONTRACTOR and is responsible for all stakeout and survey control as outlined in the CONSTRUCTION DRAWINGS and TECHNICAL SPECIFICATIONS. The SURVEYOR shall be licensed in the State of Florida. Also, refer to Section 01050 Site Conditions Survey of the TECHNICAL SPECIFICATIONS.
NON-CONFORMANCE
A deficiency in characteristics, documentation, or procedure that renders the quality of an item or activity unacceptable or indeterminate by the CQA CONSULTANT. Examples of non-conformance include but are not limited to physical defects, test failures, and inadequate documentation.
RECORD DRAWINGS
Drawings recording the constructed dimensions, details, coordinates, etc. of the elements for a PROJECT. Also referred to as “as-builts.”
Figure 3-1 Organizational Chart
COMMUNICATION AND PROJECT MEETINGS
Continuous communication between parties involved in the construction and CQA of this PROJECT, including, but not limited to, the PERMITTING AGENCY, OWNER, DESIGN ENGINEER, CQA
CONSULTANT, CONSTRUCTION QUALITY ASSURANCE REPRESENTATIVE (CQAR), CONTRACTOR,
CONTRACTOR’S REPRESENTATIVE, GEOSYNTHETICS MANUFACTURER, GEOSYNTHETICS INSTALLER, CQA GEOSYNTHETICS LABORATORY, CQC SOILS LABORATORY, CQA SOILS LABORATORY, and SURVEYOR, coupled with regularly scheduled meetings are necessary components of this CQA Plan.
Such communication and meetings are intended to resolve construction quality and design issues as early as possible, to keep all parties informed of schedules, and verify the WORK is proceeding in accordance with the schedule, CONTRACT DRAWINGS, TECHNICAL SPECIFICATIONS, and this CQA Plan. At a minimum there should be a Pre-Construction Meeting, regular Progress Meetings, Construction Resolution Meetings (as needed), and Geomembrane Pre-Installation Meeting as described below.
PRE-CONSTRUCTION MEETING
The Pre-Construction Meeting shall be held at least two weeks prior to start of construction and should be attended by the OWNER, DESIGN ENGINEER, CQA CONSULTANT, CQAR, and CONTRACTOR.
Other specialty subcontractors can attend the meeting, if required. Specific topics at the meeting should include, but are not limited to, the following.
Introduction of all personnel and review the responsibilities of each party.
Establish PROJECT communication and delineate lines of authority and communication.
Review the CONTRACTOR’S schedule for construction, including material shipment and working hours.
Critical WORK sequencing.
Liquidated damages, (if any).
Review methods for documenting and reporting, and for transmittal, distribution, review, and approval of CONTRACTOR’S submittals.
Processing Applications for Payment.
Field decisions and Change Orders.
Maintaining Record Documents.
Use of premises, stockpile areas, laydown areas, material storage areas, access roads, haul roads, security, housekeeping and related items, maintenance of traffic, and OWNER’S needs.
Major equipment deliveries and priorities.
Establish locations for soil and geosynthetic materials stockpile.
CONTRACTOR’S assignments for health and safety.
Minutes from the Pre-Construction Meeting shall be prepared by the CQA CONSULTANT and distributed to all parties in attendance, in addition to an established distribution list, for PROJECT communications.
PROGRESS MEETINGS
Progress Meetings shall be held at a mutually agreed upon day and time and attended by representatives of the OWNER, DESIGN ENGINEER and/or CQA CONSULTANT, CQAR, CONTRACTOR GEOSYNTHETICS INSTALLER, and other specialty subcontractors can attend the meeting, if required.
Topics for the Progress Meetings shall include, but are not limited to, the following.
The purpose of the Progress Meetings will be to review the progress of the WORK, maintain coordination of efforts, discuss changes in scheduling, and resolve problems which may develop. Corrections, additions, or deletions to the minutes shall be noted and addressed at the following meeting.
The WORK progress to date, scheduled activities for the next 2 weeks, issues requiring resolution, and any new business or revisions to the WORK.
Review of construction issues including questions on CONSTRUCTION DRAWINGS, TECHNICAL SPECIFICATIONS, material test results, test failures, retests, procedures, weather conditions, working hours, holidays, communications, schedules, pay applications, problems and resolutions, documentation, minutes from previous Progress Meetings, and other PROJECT related topics.
Review health and safety issues for the site.
Minutes from the Progress Meetings shall be prepared by the CQA CONSULTANT and distributed to all parties in attendance, in addition to an established distribution list, for PROJECT communications.
CONSTRUCTION RESOLUTION MEETINGS
In some cases, construction issues or problems may arise that demand specific attention outside of the regular Progress Meetings and may include parties not available at the regular Progress Meetings. Such Construction Resolution Meetings shall be held as necessary to resolve construction problems or issues in a timely manner so WORK can proceed. To the extent possible, these meetings shall be scheduled such that the key parties are available. Also, refer to Section 01200 Project Meetings of the TECHNICAL SPECIFICATIONS.
Minutes from the Construction Resolution Meetings shall be prepared by the CQA CONSULTANT and distributed to all parties in attendance, in addition to an established distribution list, for PROJECT communications.
GEOMEMBRANE PRE-INSTALLATION MEETING
A Geomembrane Pre-Installation Meeting shall be held at a mutually agreed upon day and time and attended by representatives of the OWNER, DESIGN ENGINEER, CQA CONSULTANT, CQAR, CONTRACTOR, GEOSYNTHETICS INSTALLER, and other parties that may be involved in geomembrane installation activities. Topics for the Geomembrane Pre-Installation Meeting shall include, but are not limited to, the following. Also, refer to Section 01200 Project Meetings of the TECHNICAL
SPECIFICATIONS.
A “Certificate of Subgrade Acceptance” shall be co-signed by the GEOSYNTHETICS INSTALLER and the CQAR prior to commencement of GCL installation in the area under consideration.
As-built documents reviewed and approved by the CQA CONSULTANT prior to installation.
All geosynthetic materials have been approved for use by the CQA CONSULTANT prior to installation.
Geomembrane seam properties.
Destructive testing requirements.
Non-destructive testing requirements.
o Vacuum testing.
o Air pressure testing.
Equipment acceptable for use on geosynthetics.
Trial seams.
Adequate ballast to prevent wind uplift.
Geonet overlap, shingling, and tying requirements.
Panel layout orientation.
Requirements prior to placing overlying materials.
Minutes from the Geomembrane Pre-Installation Meeting shall be prepared by the CQA CONSULTANT and distributed to all parties in attendance, in addition to an established distribution list, for PROJECT communications.
EARTH MATERIAL QUALITY ASSURANCE
GENERAL
This section of the CQA Plan describes procedures for laboratory testing of earth material (soil, aggregate, etc.) components of the PROJECT. The two categories of testing covered in this CQA Plan include the following:
1. Pre-construction material qualification testing conducted by the CONTRACTOR.
2. Pre-construction material conformance testing during construction conducted by the CQA
CONSULTANT.
PRE-CONSTRUCTION MATERIALS QUALIFICATION TESTING
Pre-construction materials qualification testing shall be performed on samples from potential soil borrow sources identified by the by CONTRACTOR by the CONTRACTOR’S independent CQC SOIL LABORATORY to ascertain acceptability as construction materials by the CQA CONSULTANT prior to incorporation into construction.
Criteria to be used for determination of acceptability of earth materials for use during construction are defined in the TECHNICAL SPECIFICATIONS. Special testing, if determined to be required by the CQA CONSULTANT and the criteria to be used to determine the acceptability of materials, shall be conducted at the direction of the OWNER, the CQA CONSULTANT, or their representative.
PRE-CONSTRUCTION MATERIALS CONFORMANCE TESTING
Pre-construction materials conformance testing shall be performed on samples from potential soil borrow sources identified by the CONTRACTOR by the CQA CONSULTANT'S independent CQA SOILS LABORATORY to ascertain acceptability as construction materials prior to incorporation into construction. Criteria to be used for determination of acceptability of earth materials for use during construction are defined in the TECHNICAL SPECIFICATIONS.
Conformance testing shall also be performed by the CQA CONSULTANT'S CQA SOILS LABORATORY during the course of the WORK to verify continued material compliance with the TECHNICAL
SPECIFICATIONS.
Excavated Subgrade Soil Testing
Insitu material that does not contain waste, as determined by the CQAR, and meets the TECHNICAL SPECIFICATIONS for its intended use, may be reused and incorporated into the PROJECT. No excavated material shall be wasted without permission, and where necessary to waste such material it shall be at the direction of the CQA CONSULTANT and OWNER. Prior to being reused or incorporated into the WORK, the CQA CONSULTANT shall review the Excavated Subgrade Soil test results from the CONTRACTORS independent CQC SOILS LABORATORY to ascertain acceptability as construction material in accordance with the TECHNICAL SPECIFICATIONS.
TABLE 02220-1 EXCAVATED SUBGRADE SOIL QUALIFICATION TESTING
TEST METHOD/PROPERTY
FREQUENCY
(MINIMUM)
ASTM D2216 Natural Moisture Content 1 test per source or change in material ASTM D698 Standard Proctor 1 test per source or change in material ASTM D2487 Soil Classification 1 test per source or change in material ASTM D6913 Sieve Analysis of Coase- Grained Soil 1 test per source or change in material ASTM D7928 Sieve Analysis of Fine- Grained Soil 1 test per source or change in material ASTM D4318 Atterberg Limits 1 test per source or change in material ASTM D6141 Chemical Compatibility 1 test per source or change in material
General Fill Soil Testing
Prior to incorporation of General Fill material into construction, the CQA CONSULTANT shall review test results from the pre-construction (qualification) materials testing on samples from potential soil borrow sources identified by the CONTRACTOR by the CONTRACTOR’S independent CQC SOIL LABORATORY as required by the TECHNICAL SPECIFICATIONS to ascertain acceptability as construction material.
The CQA CONSULTANT will collect one random sample of the proposed borrow material and test it as required by the TECHNICAL SPECIFICATIONS to confirm its acceptability as construction material prior to providing approval for placement by the CONTRACTOR.
After the material has been approved for use in the PROJECT, the CQA CONSULTANT will coordinate testing to be performed by the CQA SOILS LABORATORY during the course of the WORK to verify continued material compliance with the TECHNICAL SPECIFICATIONS. Any non-conformance test results obtained by the CQA SOILS LABORATORY will be reported to the OWNER, CQA CONSULTANT, and CONTRACTOR. Material not meeting PROJECT requirements will be removed at the CONTRACTORS expense if placed without prior approval by the OWNER or CQA CONSULTANT.
TABLE 02220-2 GENERAL FILL SOIL QUALIFICATION TESTING
TEST METHOD/PROPERTY
FREQUENCY
(MINIMUM)
ASTM D2216 Natural Moisture Content 1 test per source or change in material ASTM D698 Standard Proctor 1 test per source or change in material ASTM D6913 Sieve Analysis of Coase- Grained Soil 1 test per source or change in material ASTM D7928 Sieve Analysis of Fine- Grained Soil 1 test per source or change in material ASTM D2487 Soil Classification 1 test per source or change in material ASTM D4318 Atterberg Limits 1 test per source or change in material ASTM D6141 Chemical Compatibility 1 test per source or change in material
Structural Fill Soil Testing
Prior to incorporation of Structural Fill material into construction, the CQA CONSULTANT shall review test results from the pre-construction (qualification) materials testing on samples from potential soil borrow sources identified by the CONTRACTOR by the CONTRACTOR’S independent CQC SOIL LABORATORY as required by the TECHNICAL SPECIFICATIONS to ascertain acceptability as construction material.
The CQA CONSULTANT will collect one random sample of the proposed borrow material and test it as required by the TECHNICAL SPECIFICATIONS to confirm its acceptability as construction material prior to providing approval for placement by the CONTRACTOR.
After the material has been approved for use in the PROJECT, the CQA CONSULTANT will coordinate testing to be performed by the CQA SOILS LABORATORY during the course of the WORK to verify continued material compliance with the TECHNICAL SPECIFICATIONS. Any non-conformance test results obtained by the CQA SOILS LABORATORY will be reported to the OWNER, CQA CONSULTANT, and CONTRACTOR. Material not meeting PROJECT requirements will be removed at the CONTRACTORS expense if placed without prior approval by the OWNER or CQA CONSULTANT.
TABLE 02220-3 STRUCTURAL FILL SOIL QUALIFICATION TESTING
TEST METHOD/PROPERTY
FREQUENCY
(MINIMUM)
ASTM D2216 Natural Moisture Content 1 test per source or change in material ASTM D698 Standard Proctor 1 test per source or change in material ASTM D2487 Soil Classification 1 test per source or change in material ASTM D6913 Sieve Analysis of Coase- Grained Soil 1 test per source or change in material ASTM D7928 Sieve Analysis of Fine- Grained Soil 1 test per source or change in material ASTM D4318 Atterberg Limits 1 test per source or change in material
Protective Cover Soil Testing
Prior to incorporation of Protective Cover material into construction, the CQA CONSULTANT shall review test results from the pre-construction materials evaluation on samples from potential soil borrow sources by the CONTRACTOR’S independent CQC SOIL LABORATORY as required by the TECHNICAL SPECIFICATIONS to ascertain its acceptability as construction material. The CQA CONSULTANT will collect one random sample of the proposed borrow material and test it as required by the TECHNICAL SPECIFICATIONS to confirm its acceptability as construction material prior to providing approval for placement by the CONTRACTOR.
After the materials have been approved for use in the PROJECT, the CQA CONSULTANT will coordinate testing to be performed by the CQA SOILS LABORATORY during the course of the WORK to verify continued material compliance with the TECHNICAL SPECIFICATIONS. Any non-conformance test results obtained by the CQA SOILS LABORATORY will be reported to the OWNER, CQA CONSULTANT, and CONTRACTOR. Material not meeting PROJECT requirements will be removed at the CONTRACTORS expense if placed without prior approval by the OWNER or CQA CONSULTANT.
TABLE 02220-4 PROTECTIVE COVER LAYER GRADATION REQUIREMENTS
SIEVE SIZE
PERCENT PASSING
(MAXIMUM)
No. 4 100 No. 10 100 No. 40 80 No. 60 45 No. 100 0 - 15 No. 200 0 - 4
TABLE 02220-5 PROTECTIVE COVER MATERIAL QUALIFICATION TESTING
TEST METHOD/PROPERTY
FREQUENCY
(MINIMUM)
VALUE
(MINIMUM)
ASTM D6913 Sieve Analysis of Coarse-Grained Soil
1 test per source or change in material See note 2
ASTM D2434 Hydraulic Conductivity 1
1 test per source or change in material 1x10-3 cm/sec
Notes:
1. Refer to TABLE 02220-4 PROTECTIVE COVER LAYER GRADATION REQUIREMENTS of the
TECHNICAL SPECIFICATIONS.
2. Sample compacted in lab to 90% Standard Proctor.
Topsoil Testing
Prior to incorporation of Topsoil material into construction, the CQA CONSULTANT shall review test results from the pre-construction materials evaluation on samples from potential soil borrow sources by the CONTRACTOR’S independent CQC SOIL LABORATORY as required by the TECHNICAL SPECIFICATIONS to ascertain its acceptability as construction material. The CQA CONSULTANT will collect one random sample of the proposed borrow material and test it as required by the TECHNICAL SPECIFICATIONS to confirm its acceptability as construction material prior to providing approval for placement by the CONTRACTOR.
After the materials have been approved for use in the PROJECT, the CQA CONSULTANT will coordinate testing to be performed by the CQA SOILS LABORATORY during the course of the WORK to verify continued material compliance with the TECHNICAL SPECIFICATIONS. Any non-conformance test results obtained by the CQA SOILS LABORATORY will be reported to the OWNER, CQA CONSULTANT, and CONTRACTOR. Material not meeting PROJECT requirements will be removed at the CONTRACTORS expense if placed without prior approval by the OWNER or CQA CONSULTANT.
CONSTRUCTION QUALITY EVALUATION
Construction quality evaluation shall be performed on all soil components of the WORK. These evaluations will be performed at the frequencies indicated in the TECHNICAL SPECIFICATIONS.
Criteria used for determination of acceptability of the WORK will be as identified in the TECHNICAL SPECIFICATIONS. Construction evaluation testing includes the visual observations of the WORK; in-place density/moisture content testing; surveys of as-built conditions and elevations; thickness monitoring; and special testing. Observation of the WORK shall include, but is not limited to, the following:
Size of foreign materials and stones and other physical properties of the soil during processing, placement, and compaction.
Thickness of lifts as loosely placed and as compacted.
Action of the compaction equipment on the construction surface.
Deficiencies
If defects are discovered in the earthwork, the extent and nature shall be evaluated by the CQA CONSULTANT. If a defect is indicated by a failing test, the CQA CONSULTANT shall determine the limits of the affected area by additional tests, observations, a review of records, and other means as deemed appropriate. If the defect is related to adverse site conditions, the CQA CONSULTANT shall define the limits and nature of the defect.
Notification, Repair, and Retesting
The CQA CONSULTANT shall notify the OWNER, DESIGN ENGINEER, and CONTRACTOR after determining the nature and extent of the defect. Deficiencies shall be corrected by the CONTRACTOR to the satisfaction of the OWNER, DESIGN ENGINEER, and CQA CONSULTANT. The CQA CONSULTANT shall also verify all installation requirements as outlined in the TECHNICAL SPECIFICATIONS and this CQA Plan (i.e., material quality, thickness, and compaction) have been met and all submittals are provided. Appropriate retests shall be scheduled by the CQA CONSULTANT when the WORK deficiency is corrected.
SUBBASE
Preparation and Acceptance
The CONTRACTOR shall be responsible for preparing the Subbase upon which the GCL will be placed according to the TECHNICAL SPECIFICATIONS. Prior to acceptance, the CQA CONSULTANT shall verify the following:
A qualified land surveyor has verified all lines and grades and the CQA CONSULTANT has provided approval of the survey documents.
The supporting soil provides a firm, unyielding foundation.
The surface to be lined is relatively smooth and free of stones (greater than 1/2-inch in any dimension), protrusions, irregularities, roots, loose soil, abrupt changes in grade, or other conditions that may puncture or abrade the geomembrane.
There is no standing water or areas excessively softened by high moisture content.
All tests have been completed and meet the TECHNICAL SPECIFICATIONS and no other tests are necessary.
The INSTALLER shall certify, in writing, that the surface on which the GCL will be installed is acceptable. A “Certificate of Subbase Acceptance” shall be co-signed by the INSTALLER and the CQAR prior to commencement of installation in the area under consideration and a copy of this certificate provided to the CQA CONSULTANT. After the supporting soil has been accepted by the INSTALLER and CQAR, it shall be the INSTALLER’S responsibility to indicate to the CQA CONSULTANT any change in the supporting soil condition that may require correction. If the CQA CONSULTANT concurs with the INSTALLER, the CONTRACTOR shall ensure the supporting soil is repaired and the supporting documentation has been provided to the CQA CONSULTANT and approved.
Subbase Repair
At any time during the GCL installation, the CQA CONSULTANT shall indicate to the INSTALLER and CONTRACTOR locations which may not provide adequate support to the GCL so the areas in question can be tested and, if necessary, repaired. To that end the Subbase shall be observed by the INSTALLER and the CQAR and the decision to repair areas, if any, shall be made by the OWNER and the CQA CONSULTANT.
PROTECTIVE COVER SOIL LAYER
Placement of the Protective Cover soil material layer will only occur after the underlying geosynthetic materials installation are complete and approved by the CQA CONSULTANT in accordance with the
TECHNICAL SPECIFICATIONS.
Place Protective Cover soil material to the lines and grades shown on the CONSTRUCTION DRAWINGS. The CONTRACTOR shall place the Protective Cover soil material as shown on the CONSTRUCTION DRAWINGS to the thickness identified (measured perpendicular to the slopes).
Place Protective Cover soil material in a manner to not cause wrinkles and undue stresses to the underlying geosynthetic materials.
The CONTRACTOR shall provide and maintain a means of continuously observing the installed depth of the Protective Cover soil material on the required grid intervals in accordance with the TECHNICAL SPECIFICATIONS. If temporary markers are used, the marker shall be free standing and shall not be sharp or pointed so it cannot damage the geosynthetic materials if hit by equipment. Markers shall be removed after use and shall not be abandoned in-place after Protective Cover installation.
By survey methods, the CONTRACTOR shall verify that all grades, slopes, and elevations conform to specified requirements. Record elevations in accordance with the TECHNICAL
SPECIFICATIONS.
ANCHOR TRENCHES
The CQA CONSULTANT shall verify the anchor trenches have been constructed according to the CONSTRUCTION DRAWINGS and TECHNICAL SPECIFICATIONS. Rounded or smoothed corners shall be provided where the geomembrane enters anchor trenches to avoid sharp bends in the geosynthetic materials. No loose or excessively wet soil shall be allowed to underlie the geosynthetic materials in the anchor trenches. The anchor trenches shall be adequately drained to prevent ponding or otherwise softening of the adjacent soils while the trench is open. The anchor trenches shall be carefully backfilled and compacted by the CONTRACTOR or the INSTALLER as outlined in the TECHNICAL SPECIFICATIONS. Care shall be taken when backfilling the trenches to prevent bridging of the geosynthetic materials or damage.
GEOMEMBRANE MATERIAL TEXTURED 60 MIL AND 80 MIL
GEOMEMBRANE MANUFACTURING AND DELIVERY
Geomembrane Manufacturing
This CQA Plan has been created to verify the specified geomembrane is manufactured and tested according to Section 02776 HDPE Polyethylene Geomembrane Liner of the TECHNICAL
SPECIFICATIONS.
Manufacturer Quality Control Documentation The GEOMEMBRANE MANUFACTURER for the textured 60 mil and 80 mil geomembranes shall provide documentation and certification the materials meets the requirements outlined in Section 02776 HDPE Polyethylene Geomembrane Liner of the TECHNICAL SPECIFICATIONS and MQC measures have been implemented during the manufacturing process. The following information will be provided by the GEOMEMBRANE MANUFACTURER to the CQA CONSULTANT prior to shipment of the geomembranes to the PROJECT site:
The origin (resin supplier’s name, resin production plant), identification (brand name, number) and production date of the resin.
MQC certificates issued by the resin supplier noting results of density and melt index.
MQC certificates for all MQC testing of the geomembranes required by Section 02776 HDPE Polyethylene Geomembrane Liner of the TECHNICAL SPECIFICATIONS.
The CQA CONSULTANT shall verify the property values certified by the GEOMEMBRANE MANUFACTURER meet the test methods listed in Section 02776 HDPE Polyethylene Geomembrane Liner of the TECHNICAL SPECIFICATIONS and the GEOMEMBRANE MANUFACTURER guaranteed minimum values.
An inventory list of quantities with descriptions of materials which comprise the geomembranes shipments.
Manufacturer Quality Control Certificates The GEOMEMBRANE MANUFACTURER for the textured 60 mil and 80 mil geomembranes shall be required to perform, at a minimum, the tests listed in Section 02776 HDPE Polyethylene Geomembrane Liner of the TECHNICAL SPECIFICATIONS. Prior to shipment to the PROJECT site, the GEOMEMBRANE MANUFACTURER shall provide the CQA CONSULTANT the MQC certificates for the geomembranes, written on the MANUFACTURER’S company letterhead, for each roll of geomembrane, signed by a responsible party employed by the GEOMEMBRANE MANUFACTURER.
The MQC certificates shall include at a minimum the roll identification numbers and the MQC test results (listed individually). The CQA CONSULTANT shall review the MQC certificates and verify the required testing frequencies and results meet the requirements specified according to Section 02776 HDPE Polyethylene Geomembrane Liner of the TECHNICAL SPECIFICATIONS and the MANUFACTURER’S guaranteed minimum values for all materials and rolls. The CQA CONSULTANT shall report any noncompliance to the OWNER, INSTALLER, and GEOMEMBRANE MANUFACTURER.
Manufacturer Quality Control Testing Testing during manufacturing for the textured 60 mil and 80 mil geomembranes shall be accomplished by the GEOMEMBRANE MANUFACTURER laboratory. The MANUFACTURER shall test the resin batches per the frequency, at a minimum, that conforms to TABLE 02766-1 RESIN MQC REQUIREMENTS as required by Section 02776 HDPE Polyethylene Geomembrane Liner of the
TECHNICAL SPECIFICATIONS.
TABLE 02766-1 RESIN MQC REQUIREMENTS
TEST METHOD/PROPERTY 60 mil VALUE 80 mil VALUE 60 and 80 mil FREQUENCY
(MINIMUM)
ASTM D1505 Polymer Density 0.932 to 0.950 (g/cm3)
0.932 to 0.950 (g/cm3) not less than 1 test per resin lot
ASTM D1238 Polymer Melt Index ≤ 1.0 g/10 min. ≤ 1.0 g/10 min. not less than 1 test per resin lot
ASTM D3895 Oxidation Induction Time > 100 min. > 100 min. not less than 1 test per resin lot
The MANUFACTURER shall test the textured 60 mil and 80 mil geomembranes per the frequency of material per lot, at a…