01 SEPTEMBER 2020
| DD FORM 1423-1, FEB 2001 | PREVIOUS EDITION MAY BE USED | Page 1 of 13 Pages |
| CONTRACT DATA REQUIREMENTS LIST (CDRL) | |
(1 Data Item) Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
| A. CONTRACT LINE ITEM NO. |
| B. EXHIBIT |
| C. CATEGORY: |
| 1010, 1011, 1012, 1013, 1014, 1015, 1016, 1019, 1020 |
| F |
| TDP ____ |
| TM _____ |
| OTHER TRAINING DATA |
| D. SYSTEM/ITEM |
| E. CONTRACT/PR NO. |
| F. CONTRACTOR |
S2025 FY22 RRL CONTENT CONVERSION
| 1. DATA ITEM NO. |
| 2. TITLE OF DATA ITEM |
| 3. SUBTITLE |
17. PRICE GROUP
F001
| INSTRUCTIONAL MEDIA DESIGN PACKAGE (IMDP) |
| DESIGN STRATEGY |
| 4. AUTHORITY (Data Acquisition Document No.) |
| 5. CONTRACT REFERENCE |
| 6. REQUIRING OFFICE |
18. ESTIMATED
TOTAL PRICE
| DI-SESS-81520B |
| SOW PARA 3.5.1, 3.5.2.5, 3.5.3.2 |
| NAWCTSD RRL TSPM |
| 7. DD 250 REQ |
| 9. DIST STATEMENT |
| 10. FREQUENCY |
| 12. DATE OF FIRST SUBMISSION |
| 14. DISTRIBUTION |
| LT |
| REQUIRED |
| ASREQ |
| SEE BLOCK 16 |
| a. ADDRESSEE |
| b. COPIES |
| 8. APP CODE |
| D |
| 11. AS OF DATE |
| 13. DATE IF SUBSEQUENT SUBM. |
A
| 16. REMARKS |
| NAWCTSD TPOC |
| 1 |
BLK 4: DELETE ALL PARAGRAPHS EXCEPT 2.2 – 2.3, 2.3.2 – 2.3.6.b, 2.3.7 - 2.3.12, 2.4 – 2.4.6, 2.4.8 - 2.5.g .
1. BLKS 10/12/13: SUBMISSIONS SHALL BE DELIVERED FOR EACH COURSE FOR EACH RATING IN ACCORDANCE WITH (IAW) THE GOVERNMENT-ACCEPTED INTEGRATED MASTER SCHEDULE (IMS). SUBSEQUENT SUBMISSIONS SHALL BE IAW THE GOVERNMENT-ACCEPTED IMS AND SHALL INCORPORATE ALL GOVERNMENT PROVIDED COMMENTS ON THE PREVIOUS SUBMISSION.
2. BLK 14: SUBMISSIONS SHALL BE ELECTRONIC IN MICROSOFT OFFICE (WORD) 2010 OR LATER FORMAT. SUBMISSIONS SHALL BE POSTED TO THE CONTRACTOR DELIVERABLE ONLINE MANAGEMENT SYSTEM, INCLUDINGNAWCTSD FORM 4330 WITH THE APPROPRIATE INFORMATION FILLED IN.. AN E-MAIL INDICATING THE SUBMISSION IS READY FOR GOVERNMENT REVIEW SHALL BE SENT TO DESIGNATED ADDRESSES, ALSO INDICATING THE DATE GOVERNMENT REVIEW COMMENCES.. THE CONTRACTOR SHALL PROVIDE THE GOVERNMENT WITH AT LEAST ONE DAY NOTICE PRIOR TO THE BEGINNING OF THE GOVERNMENT REVIEW PERIOD. EMAIL ADDRESSES ARE IN SECTION F OF THE CONTRACT SCHEDULE.
3. THE GOVERNMENT WILL HAVE 20 WORKING DAYS FOR REVIEW AND ACCEPTANCE/CONDITIONAL ACCEPTANCE/REJECTION OF EACH SUBMISSION
4. CONTRACTOR INCORPORATION OF GOVERNMENT COMMENTS SHALL BE DUE WITHIN IN FIVE WORKING DAYS OF RECEIPT OF COMMENTS IF ACCEPTED WITH COMMENTS, AND WITHIN 10 WORKING DAYS OF RECEIPT OF COMMENTS IF REJECTED.
5. ACCEPTANCE OF CHANGES IN CONTRACT REQUIREMENTS/STANDARDS/SPECIFICATIONS DOES NOT CONSTITUTE GOVERNMENT AGREEMENT TO THOSE CHANGES. ONLY BY DIRECTION OF THE CONTRACTING OFFICER CAN SUCH CHANGES BE MADE.
DISTRIBUTION D. DISTRIBUTION AUTHORIZED TO DOD AND U.S. DOD CONTRACTORS ONLY; ADMINISTRATIVE OR OPERATIONAL USE, 24 JUL 2018. OTHER REQUESTS FOR THIS DOCUMENT MUST BE REFERRED TO NAVAL AIR WARFARE CENTER TRAINING SYSTEMS DIVISION, 12211 SCIENCE DRIVE, ORLANDO, FL 32826-3275 READY RELEVANT LEARNING TRAINING SYSTEMS PROGRAM MANAGER.
DESTRUCTION NOTICE - FOR CLASSIFIED DOCUMENTS, FOLLOW THE PROCEDURES IN DOD 5220.22-M, INDUSTRIAL SECURITY MANUAL, SECTION 11-19 OR DOD 5200.1-R, INFORMATION SECURITY PROGRAM REGULATION, CHAPTER IX. FOR UNCLASSIFIED, LIMITED DOCUMENTS, DESTROY BY ANY METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS OR RECONSTRUCTION OF THE DOCUMENT.
NAWCTSD PCO
NAWCTSD PJM
NAWCTSD RRL LSE
| G. PREPARED BY |
| H. DATE |
| I. APPROVED BY |
| J. DATE |
VINCE FLANGO, RRL FY22 CONTENT CONVERSION TPOC
LCDR MAURA BETTS, RRL FY22PROGRAM MANAGER
| DD FORM 1423-1, FEB 2001 | PREVIOUS EDITION MAY BE USED | Page 2 of 13 Pages |
| CONTRACT DATA REQUIREMENTS LIST (CDRL) | |
(1 Data Item) Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
| A. CONTRACT LINE ITEM NO. |
| B. EXHIBIT |
| C. CATEGORY: |
| 1010, 1011, 1012, 1014, 1015, 1016, 1019, 1020 |
| F |
| TDP ____ |
| TM _____ |
| OTHER TRAINING DATA |
| D. SYSTEM/ITEM |
| E. CONTRACT/PR NO. |
| F. CONTRACTOR |
S2025 FY22 RRL CONTENT CONVERSION
| 1. DATA ITEM NO. |
| 2. TITLE OF DATA ITEM |
| 3. SUBTITLE |
17. PRICE GROUP
| F002 |
| INSTRUCTIONAL MEDIA DESIGN PACKAGE |
| UPDATED STYLE GUIDE AND MODEL PRODUCTS (PROTOTYPES) |
| 4. AUTHORITY (Data Acquisition Document No.) |
| 5. CONTRACT REFERENCE |
| 6. REQUIRING OFFICE |
18. ESTIMATED
TOTAL PRICE
| DI-SESS-81520B |
| SOW PARA 3.5.2.1, 3.5.3.1 |
| NAWCTSD RRL TSPM |
| 7. DD 250 REQ |
| 9. DIST STATEMENT |
| 10. FREQUENCY |
| 12. DATE OF FIRST SUBMISSION |
| 14. DISTRIBUTION |
| LT |
| REQUIRED |
| ASREQ |
| SEE BLOCK 16 |
| a. ADDRESSEE |
| b. COPIES |
| 8. APP CODE |
| D |
| 11. AS OF DATE |
| 13. DATE IF SUBSEQUENT SUBM. |
A
| 16. REMARKS |
| NAWCTSD TPOC |
| 1 |
1. BLK 4: DELETE ALL PARAGRAPHS EXCEPT 2.3.1, 2.3.6.a thru f, AND 2.4.7.
2. BLK 10/12/13: THE FIRST SUBMISSION SHALL BE DELIVERED IN ACCORDANCE WITH (IAW) THE GOVERNMENT-ACCEPTED INTEGRATED MASTER SCHEDULE (IMS). THE FRIST SUBMISSION OF A PROTOTYPE SHALL INCLUDE DELIVERY OF AN UPDATED DRAFT STYLE GUIDE. SUBSEQUENT SUBMISSION SHALL BE IAW THE GOVERNMENT-ACCEPTED IMS AND SHALL INCORPORATE ALL GOVERNMENT PROVIDED COMMENTS ON THE PREVIOUS SUBMISSION. SUBSEQUENT SUBMISSIONS SHALL ENSURE THAT THE MODEL PRODUCTS AND THE STYLE GUIDE ARE ALIGNED.
3. BLK 13: FINAL SUBMISSIONS SHALL BE DELIVERED NLT TWO (2) MONTHS PRIOR TO END OF CONTRACT.
4. BLK 14: SUBMISSIONS OF THE STYLE GUIDE SHALL BE ELECTRONIC IN MICROSOFT OFFICE (WORD) 2010 OR LATER FORMAT. SUBMISSIONS OF THE STYLE GUIDE AND PROTOTYPES SHALL BE POSTED TO THE CONTRACTOR DELIVERABLE ONLINE MANAGEMENT SYSTEM, INCLUDING NAWCTSD FORM 4330 WITH THE APPROPRIATE INFORMATION FILLED IN . AN E-MAIL INDICATING THE SUBMISSION IS READY FOR GOVERNMENT REVIEW SHALL BE SENT TO DESIGNATED ADDRESSES, ALSO INDICATING THE DATE GOVERNMENT REVIEW COMMENCES. . THE CONTRACTOR SHALL PROVIDE THE GOVERNMENT WITH AT LEAST ONE DAY NOTICE PRIOR TO THE BEGINNING OF THE GOVERNMENT REVIEW PERIOD. EMAIL ADDRESSES ARE IN SECTION F OF THE CONTRACT SCHEDULE.
5. THE GOVERNMENT WILL HAVE 20 WORKING DAYS FOR REVIEW AND ACCEPTANCE/CONDITIONAL ACCEPTANCE/REJECTION OF EACH SUBMISSION
6. FOR EACH SUBMISSION, CONTRACTOR INCORPORATION OF GOVERNMENT COMMENTS SHALL BE DUE WITHIN 10 WORKING DAYS OF RECEIPT OF COMMENTS IF ACCEPTED CONDITIONALLY/REJECTED.
7. THE CONTRACTOR SHALL DEVELOP AND TEST ONE SEPARATE MODEL PRODUCT FOR EACH CONTENT DELIVERY MODE (INSTRUCTOR-FACILITATED INTERACTIVE TRAINING IMI LEVEL 2, SELF-DIRECTED INTERACTIVE TRAINING IMI LEVEL 3, PERFORMANCE SUPPORT, AND STRUCTURED-ON-THE-JOB-TRAINING) DEMONSTRATING THE DESIGN CONVENTIONS, STANDARDS, SCREEN INTERFACES, AND FUNCTIONALITY OF THE TRAINING PRODUCTS. EACH MODEL PRODUCT SHALL BE DEVELOPED BASED ON ONE ENABLING LEARNING OBJECTIVE, COVERING CONTENT AGREED UPON BY BOTH THE CONTRACTOR AND THE GOVERNMENT AND ADDRESSING THE MEDIA CHARACTERISTICS IDENTIFIED IN THE CORRESPONDING FRD WORKBOOK. THE PROTOTYPES SHALL DEMONSTRATE FULL FUNCTIONALITY OF ALL PROPOSED STRATEGIES AND SHALL PASS GOVERNEMNT CONTENT ACCEPTANCE TESTING (GCAT) REQUIREMENTS FOR HOSTING IN NEL ENVIRONMENTS.
8. THE STYLE GUIDE, IN ADDITION TO REQUIREMENTS OUTLINED IN DI-SESS-81520B, SHALL BE A LIVING DOCUMENT AND SHALL BE UPDATED AS CONVENTIONS AND STANDARDS EVOLVE, AND SHALL AT ALL TIMES ALIGN WITH THE MODEL PRODUCTS AS THEY EVOLVE.
9. THE CONTRACTOR SHALL INCLUDE WITHIN EACH SUBMISSION OF THE STYLE GUIDE ANY RECOMMENDED DEVIATIONS FROM THE GFI STYLE GUIDE. THE GOVERNMENT WILL REVIEW THE RECOMMENDED DEVIATIONS AS PART OF ITS REVIEW OF THE DELIVERABLE SUBMISSION.
10. ACCEPTANCE OF CHANGES IN CONTRACT REQUIREMENTS/STANDARDS/SPECIFICATIONS DOES NOT CONSTITUTE GOVERNMENT AGREEMENT TO THOSE CHANGES. ONLY BY DIRECTION OF THE CONTRACTING OFFICER CAN SUCH CHANGES BE MADE.
11. THE FOLLOWING DISTRIBUTION STATEMENT SHALL BE INCLUDED ON THE DELIVERABLE:
DISTRIBUTION D. DISTRIBUTION AUTHORIZED TO DOD AND U.S. DOD CONTRACTORS ONLY; ADMINISTRATIVE OR OPERATIONAL USE, 24 JUL 2018. OTHER REQUESTS FOR THIS DOCUMENT MUST BE REFERRED TO NAVAL AIR WARFARE CENTER TRAINING SYSTEMS DIVISION, 12211 SCIENCE DRIVE, ORLANDO, FL 32826-3275 READY RELEVANT LEARNING TRAINING SYSTEMS PROGRAM MANAGER.
DESTRUCTION NOTICE - FOR CLASSIFIED DOCUMENTS, FOLLOW THE PROCEDURES IN DOD 5220.22-M, INDUSTRIAL SECURITY MANUAL, SECTION 11-19 OR DOD 5200.1-R, INFORMATION SECURITY PROGRAM REGULATION, CHAPTER IX. FOR UNCLASSIFIED, LIMITED DOCUMENTS, DESTROY BY ANY METHOD THAT WILL PREVENT DISCLOSURE OF CONTENTS OR RECONSTRUCTION OF THE DOCUMENT.
NAWCTSD PCO
NAWCTSD PJM
| G. PREPARED BY |
| H. DATE |
| I. APPROVED BY |
| J. DATE |
VINCE FLANGO, RRL FY22 CONTENT CONVERSION TPOC
LCDR MAURA BETTS, RRL FY22PROGRAM MANAGER
| DD FORM 1423-1, FEB 2001 | PREVIOUS EDITION MAY BE USED | Page 3 of 13 Pages |
| CONTRACT DATA REQUIREMENTS LIST (CDRL) | |
(1 Data Item) Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
| A. CONTRACT LINE ITEM NO. |
| B. EXHIBIT |
| C. CATEGORY: |
| 1010, 1011, 1012, 1014, 1015, 1016, 1019, 1020 |
| F |
| TDP ____ |
| TM _____ |
| OTHER TRAINING DATA |
| D. SYSTEM/ITEM |
| E. CONTRACT/PR NO. |
| F. CONTRACTOR |
S2025 FY22 RRL CONTENT CONVERSION
1. DATA ITEM NO.
F003
2. TITLE OF DATA ITEM
INSTRUCTIONAL MEDIA PACKAGE
3. SUBTITLE
SCRIPT/STORYBOARDS
17. PRICE GROUP
| 4. AUTHORITY (Data Acquisition Document No.) |
| 5. CONTRACT REFERENCE |
| 6. REQUIRING OFFICE |
18. ESTIMATED
TOTAL PRICE
| DI-PSSS-81526C |
| SOW PARA 3.5.2.2, 3.5.2.5, 3.5.3.3 |
| NAWCTSD RRL TSPM |
| 7. DD 250 REQ |
| 9. DIST STATEMENT |
| 10. FREQUENCY |
| 12. DATE OF FIRST SUBMISSION |
| 14. DISTRIBUTION |
| REQUIRED |
| ASREQ |
| SEE BLOCK 16 |
| a. ADDRESSEE |
| b. COPIES |
| 8. APP CODE |
| SEE BLOCK 16 |
| 11. AS OF DATE |
| 13. DATE IF SUBSEQUENT SUBM. |
| 16. REMARKS |
| NAWCTSD TPOC |
| 1 |
1. BLK 4: DELETE ALL PARAGRAPHS EXCEPT 2.3.2, 2.3.3, 2.4, AND 2.5. CONTRACTOR FORMAT IS ACCEPTABLE.
2. BLKS 10/12/13: SUBMISSIONS SHALL BE DELIVERED IN INCREMENTS IN ACCORDANCE WITH (IAW) THE GOVERNMENT-ACCEPTED INTEGRATED MASTER SCHEDULE (IMS).
3. BLK 14: SUBMISSIONS SHALL BE VIA THE CONTRACTOR ONLINE MANAGEMENT SYSTEM, INCLUDING NAWCTSD FORM 4330 WITH THE APPROPRIATE INFORMATION FILLED IN. NO PAPER COPIES WILL BE ACCEPTED. AN E-MAIL INDICATING THE SUBMISSION IS READY FOR GOVERNMENT REVIEW SHALL BE SENT TO DESIGNATED ADDRESSES, ALSO INDICATING THE DATE GOVERNMENT REVIEW COMMENCES, . THE CONTRACTOR SHALL PROVIDE THE GOVERNMENT WITH AT LEAST ONE DAY NOTICE PRIOR TO THE BEGINNING OF THE GOVERNMENT REVIEW PERIOD. EMAIL ADDRESSES ARE IN SECTION F OF THE CONTRACT SCHEDULE.
4. THE GOVERNMENT WILL HAVE 20 WORKING DAYS FOR REVIEW AND CONDITIONAL ACCEPTANCE/REJECTION OF EACH SUBMISSION
5. CONTRACTOR INCORPORATION OF GOVERNMENT COMMENTS SHALL BE DUE AT CDRL F004 ON-SCREEN LESSON SUBMISSION IF ACCEPTED WITH COMMENTS, AND WITHIN 10 WORKING DAYS OF RECEIPT OF COMMENTS IF REJECTED.
6. STORYBOARDS SHALL, IN ADDITION TO REQUIREMENTS OUTLINED IN DI-SESS-81526C, CONTAIN A VISUAL REPRESENTATION OF ALL OBJECTS ON EACH SCREEN AND REFERENCES USED TO CREATE THE CURRICULUM (INCLUDING TITLE, PAGE, AND PARAGRAPH FOR CONTENT/TEXT ON EACH SCREEN).
7. STORYBOARDS SUBMISSIONS SHALL, IN ADDITION TO REQUIREMENTS OUTLINED IN DI-SESS-81526C, INCLUDE APPLICABLE TEST PACKAGE ASSESSMENT ITEMS CREATED AND INCLUDE REQUIREMENTS IDENTIFIED IN CDRL F005 TEST PACKAGE.
8. ACCEPTANCE OF CHANGES IN CONTRACT REQUIREMENTS/STANDARDS/SPECIFICATIONS DOES NOT CONSTITUTE GOVERNMENT AGREEMENT TO THOSE CHANGES. ONLY BY DIRECTION OF THE CONTRACTING OFFICER CAN SUCH CHANGES BE MADE.
9. THE DISTRIBUTION STATEMENT SHALL BE IAW THE HIGHEST CLASSIFICATION MARKING OF THE SOURCE MATERIAL FOR THE DELIVERABLE:
NAWCTSD PCO
NAWCTSD PJM
| G. PREPARED BY |
| H. DATE |
| I. APPROVED BY |
| J. DATE |
VINCE FLANGO, RRL FY22 CONTENT CONVERSION TPOC
LCDR MAURA BETTS, RRL FY22PROGRAM MANAGER
| DD FORM 1423-1, FEB 2001 | PREVIOUS EDITION MAY BE USED | Page 4 of 13 Pages |
| CONTRACT DATA REQUIREMENTS LIST (CDRL) | |
(1 Data Item) Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
| A. CONTRACT LINE ITEM NO. |
| B. EXHIBIT |
| C. CATEGORY: |
| 1010, 1011, 1012, 1014, 1015, 1016, 1019, 1020 |
| F |
| TDP ____ |
| TM _____ |
| OTHER TRAINING DATA |
| D. SYSTEM/ITEM |
| E. CONTRACT/PR NO. |
| F. CONTRACTOR |
S2025 FY22 RRL CONTENT CONVERSION
| 1. DATA ITEM NO. |
| 2. TITLE OF DATA ITEM |
| 3. SUBTITLE |
17. PRICE GROUP
| F004 |
| INSTRUCTIONAL MEDIA PACKAGE |
| ON-SCREEN LESSONS |
| 4. AUTHORITY (Data Acquisition Document No.) |
| 5. CONTRACT REFERENCE |
| 6. REQUIRING OFFICE |
18. ESTIMATED
TOTAL PRICE
| DI-PSSS-81526C |
| SOW PARA 3.5.2.3, 3.5.2.5, 3.5.3.4 |
| NAWCTSD RRL TSPM |
| 7. DD 250 REQ |
| 9. DIST STATEMENT |
| 10. FREQUENCY |
| 12. DATE OF FIRST SUBMISSION |
| 14. DISTRIBUTION |
| LT |
| REQUIRED |
| ASREQ |
| SEE BLOCK 16 |
| a. ADDRESSEE |
| b. COPIES |
| 8. APP CODE |
| SEE BLOCK 16 |
| 11. AS OF DATE |
| 13. DATE IF SUBSEQUENT SUBM. |
A
| 16. REMARKS |
| NAWCTSD TPOC |
| 1 |
1. BLK 4: DELETE ALL PARAGRAPHS EXCEPT 2.6.2 – 2.6.4, 2.6.6.a-o, 2.7.
2. BLKS 10/12/13: SUBMISSIONS SHALL BE IN ACCORDANCE WITH (IAW) THE GOVERNMENT-ACCEPTED INTEGRATED MASTER SCHEDULE (IMS).
3. BLK 14: SUBMISSIONS SHALL BE VIA THE CONTRACTOR ONLINE MANAGEMENT SYSTEM, INCLUDING NAWCTSD FORM 4330 WITH THE APPROPRIATE INFORMATION FILLED IN. AN E-MAIL INDICATING THE SUBMISSION IS READY FOR GOVERNMENT REVIEW SHALL BE SENT TO DESIGNATED ADDRESSES, ALSO INDICATING THE DATE GOVERNMENT REVIEW COMMENCES. THE CONTRACTOR SHALL PROVIDE THE GOVERNMENT WITH AT LEAST ONE DAY NOTICE PRIOR TO THE BEGINNING OF THE GOVERNMENT REVIEW PERIOD. EMAIL ADDRESSES ARE IN SECTION F OF THE CONTRACT SCHEDULE.
4. THE GOVERNMENT WILL HAVE 20 WORKING DAYS FOR REVIEW AND APPROVAL/CONDITIONAL ACCEPTANCE/REJECTION OF EACH INCREMENTALLY DELIVERED SUBMISSION.
5. CONTRACTOR INCORPORATION OF GOVERNMENT COMMENTS SHALL BE DUE WITHIN 10 WORKING DAYS OF RECEIPT OF COMMENTS.
6. FINAL APPROVAL WILL BE GRANTED ONLY IF THE SUBMISSION IS COMPLETE, INCORPORATES GOVERNMENT PROVIDED COMMENTS MADE DURING CDRL F003 SCRIPT/STORYBOARD REVIEW PERIOD AND DRAFT OSL REVIEW PERIOD, AND PERFORMS AS EXPECTED (FUNCTIONALITY, ETC.).
7. ON-SCREEN SUBMISSIONS SHALL, IN ADDITION TO REQUIREMENTS OUTLINED IN DI-SESS-81526C, INCLUDE APPLICABLE TEST PACKAGE ASSESSMENT ITEMS CREATED AND INCLUDE REQUIREMENTS IDENTIFIED IN CDRL F005 TEST PACKAGE.
8. ACCEPTANCE OF CHANGES IN CONTRACT REQUIREMENTS/STANDARDS/SPECIFICATIONS DOES NOT CONSTITUTE GOVERNMENT AGREEMENT TO THOSE CHANGES. ONLY BY DIRECTION OF THE CONTRACTING OFFICER CAN SUCH CHANGES BE MADE.
9. THE DISTRIBUTION STATEMENT SHALL BE IAW THE HIGHEST CLASSIFICATION MARKING OF THE SOURCE MATERIAL FOR THE DELIVERABLE:
NAWCTSD PCO
NAWCTSD PJM
| G. PREPARED BY |
| H. DATE |
| I. APPROVED BY |
| J. DATE |
VINCE FLANGO, RRL FY22 CONTENT CONVERSION TPOC
LCDR MAURA BETTS, RRL FY22PROGRAM MANAGER
| DD FORM 1423-1, FEB 2001 | PREVIOUS EDITION MAY BE USED | Page 5 of 13 Pages |
| CONTRACT DATA REQUIREMENTS LIST (CDRL) | |
(1 Data Item) Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
| A. CONTRACT LINE ITEM NO. |
| B. EXHIBIT |
| C. CATEGORY: |
| 1010, 1011, 1012, 1013, 1014, 1015, 1016, 1019, 1020 |
| F |
| TDP ____ |
| TM _____ |
| OTHER TRAINING DATA |
| D. SYSTEM/ITEM |
| E. CONTRACT/PR NO. |
| F. CONTRACTOR |
S2025 FY22 RRL CONTENT CONVERSION
| 1. DATA ITEM NO. |
| 2. TITLE OF DATA ITEM |
| 3. SUBTITLE |
17. PRICE GROUP
| F005 |
| TEST PACKAGE |
| TEST PACKAGE (ASSESSMENTS) |
| 4. AUTHORITY (Data Acquisition Document No.) |
| 5. CONTRACT REFERENCE |
| 6. REQUIRING OFFICE |
18. ESTIMATED
TOTAL PRICE
| DI-PSSS-81525C |
| 3.5.2.5, 3.5.4.5.1, 3.5.4.5.2, 3.5.4.5.5.4, 3.5.4.5.5.6 |
| NAWCTSD RRL TSPM |
| 7. DD 250 REQ |
| 9. DIST STATEMENT |
| 10. FREQUENCY |
| 12. DATE OF FIRST SUBMISSION |
| 14. DISTRIBUTION |
| REQUIRED |
| ASREQ |
| SEE BLOCK 16 |
| a. ADDRESSEE |
| b. COPIES |
| 8. APP CODE |
| SEE BLOCK 16 |
| 11. AS OF DATE |
| 13. DATE IF SUBSEQUENT SUBM. |
| 16. REMARKS |
| NAWCTSD TPOC |
| 1 |
1. BLK 4: DELETE ALL PARAGRAPHS EXCEPT 2.4, 2.4.1.a – c, 2.4.1.f, 2.4.1.j, 2.4.2b, 2.4.2d, 2.4.3, 2.4.4, AND 2.5.
2. BLK 10/12/13: SUBMISSIONS SHALL BE INCLUDED IN THE CDRL F001 INSTRUCTIONAL MEDIA DESIGN PACKAGE (IMDP) (EXAMPLE TEST ITEMS ONLY), CDRL F003 SCRIPT/STORYBOARD, CDRL F004 ON-SCREEN LESSONS AND THE CDRL F007 TRAINING CONDUCT SUPPORT DOCUMENT (CURRICULUM PACKAGE) INCREMENTS IN ACCORDANCE WITH (IAW) THE GOVERNMENT-ACCEPTED INTEGRATED MASTER SCHEDULE (IMS). TO AID REVIEW OF COMPLEX MEDIA PRODUCTS, SUBMISSIONS SHALL BE SCHEDULED IN THE IMS TO ALSO ACCOMPANY SOFTWARE PRODUCT DESIGN (SPD) (A002), SOFTWARE PRODUCT PACKAGE (SPP) (A005), AND LOGIC TABLES (A008).
3. BLK 14: SUBMISSIONS INCLUDED IN THE CDRL F001 INSTRUCTIONAL MEDIA DESIGN PACKAGE SHALL BE IN MICROSOFT OFFICE (WORD) 2010 OR LATER FORMAT. SUBMISSIONS SHALL BE POSTED TO THE CONTRACTOR DELIVERABLE ONLINE MANAGEMENT SYSTEM, INCLUDING NAWCTSD FORM 4330 WITH THE APPROPRIATE INFORMATION FILLED IN. . AN E-MAIL INDICATING THE SUBMISSION IS READY FOR GOVERNMENT REVIEW SHALL BE SENT TO DESIGNATED ADDRESSES, ALSO INDICATING THE DATE GOVERNMENT REVIEW COMMENCES.. THE CONTRACTOR SHALL PROVIDE THE GOVERNMENT WITH AT LEAST ONE DAY NOTICE PRIOR TO THE BEGINNING OF THE GOVERNMENT REVIEW PERIOD. EMAIL ADDRESSES ARE IN SECTION F OF THE CONTRACT SCHEDULE.
4. SUBMISSIONS INCLUDED IN THE CDRL F003 SCRIPT/STORYBOARD, CDRL F004 ON-SCREEN LESSONS AND THE CDRL F007 CURRICULUM PACKAGE SHALL BE VIA THE CONTRACTOR ONLINE MANAGEMENT SYSTEM, INCLUDING NAWCTSD FORM 4330 WITH THE APPROPRIATE INFORMATION FILLED IN. NO PAPER COPIES WILL BE ACCEPTED. AN E-MAIL INDICATING THE SUBMISSION IS READY FOR GOVERNMENT REVIEW SHALL BE SENT TO DESIGNATED ADDRESSES, ALSO INDICATING THE DATE GOVERNMENT REVIEW COMMENCES.. THE CONTRACTOR SHALL PROVIDE THE GOVERNMENT WITH AT LEAST ONE DAY NOTICE PRIOR TO THE BEGINNING OF THE GOVERNMENT REVIEW PERIOD. EMAIL ADDRESSES ARE IN SECTION F OF THE CONTRACT SCHEDULE.
5. THE GOVERNMENT WILL HAVE 20 WORKING DAYS FOR REVIEW AND ACCEPTANCE/CONDITIONAL ACCEPTANCE/REJECTION OF EACH INCREMENTALLY DELIVERED SUBMISSION. FOR TEST PACKAGE SUBMISSION DELIVERED WITH CDRL F001 INSTRUCTIONAL MEDIA DESIGN PACKAGE (IMDP) DOCUMENT, CONTRACTOR INCORPORATION OF GOVERNMENT COMMENTS SHALL BE WITH CDRL F003 STORYBOARD SUBMISSIONS IF ACCEPTED WITH COMMENTS, AND IN 10 WORKING DAYS OF RECEIPT OF COMMENTS IF REJECTED. FOR TEST PACKAGE SUBMISSION DELIVERED WITH F003 STORYBOARD, CONTRACTOR INCORPORATION OF GOVERNMENT COMMENTS SHALL BE WITH CDRL F004 ON-SCREEN LESSON SUBMISSION IF ACCEPTED WITH COMMENTS, AND IN 10 WORKING DAYS OF RECEIPT OF COMMENTS IF REJECTED. FOR TEST PACKAGE SUBMISSION DELIVERED WITH F004 ON-SCREEN LESSON, CONTRACTOR INCORPORATION OF GOVERNMENT COMMENTS SHALL BE DUE IN 10 WORKING DAYS OF RECEIPT OF COMMENTS IF REJECTED. FOR SUBMISSION DELIVERED WITH F007 CURRICULUM PACKAGE SUBMISSIONS, CONTRACTOR INCORPORATION OF GOVERNMENT COMMENTS SHALL BE DUE IN 10 WORKING DAYS OF RECEIPT OF COMMENTS IF ACCEPTED WITH COMMENTS OR REJECTED.
6. TEST PACKAGE SUBMISSIONS SHALL, IN ADDITION TO REQUIREMENTS OUTLINED IN DI-SESS-81525C, INCLUDE ASSESSMENT QUESTIONS WITH ANTICIPATED DISTRACTERS, THE CORRECT ANSWER, AND BOTH REMEDIATION, FEEDBACK VERBIAGE, DETAILED DESCRIPTION OF TEST BANKS, AN ASSESSMENT ITEM CROSS-REFERENCE CHART, AND ANSWER KEYS FOR EACH TEST TYPE.
7. ACCEPTANCE OF CHANGES IN CONTRACT REQUIREMENTS/STANDARDS/SPECIFICATIONS DOES NOT CONSTITUTE GOVERNMENT AGREEMENT TO THOSE CHANGES. ONLY BY DIRECTION OF THE CONTRACTING OFFICER CAN SUCH CHANGES BE MADE.
8. THE DISTRIBUTION STATEMENT SHALL BE IAW THE HIGHEST CLASSIFICATION MARKING OF THE SOURCE MATERIAL FOR THE DELIVERABLE.
NAWCTSD PCO
NAWCTSD PJM
| G. PREPARED BY |
| H. DATE |
| I. APPROVED BY |
| J. DATE |
VINCE FLANGO, RRL FY22 CONTENT CONVERSION TPOC
LCDR MAURA BETTS, RRL FY22PROGRAM MANAGER
| DD FORM 1423-1, FEB 2001 | PREVIOUS EDITION MAY BE USED | Page 6 of 13 Pages |
| CONTRACT DATA REQUIREMENTS LIST (CDRL) | |
(1 Data Item) Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
| A. CONTRACT LINE ITEM NO. |
| B. EXHIBIT |
| C. CATEGORY: |
| 1010, 1011, 1012, 1013, 1014, 1015, 1016, 1019, 1020 |
| F |
| TDP ____ |
| TM _____ |
| OTHER TRAINING DATA |
| D. SYSTEM/ITEM |
| E. CONTRACT/PR NO. |
| F. CONTRACTOR |
S2025 FY22 RRL CONTENT CONVERSION
| 1. DATA ITEM NO. |
| 2. TITLE OF DATA ITEM |
| 3. SUBTITLE |
17. PRICE GROUP
| F006 |
| TEST PACKAGE |
| COURSE TESTING PLAN (ADMINISTRATION) |
| 4. AUTHORITY (Data Acquisition Document No.) |
| 5. CONTRACT REFERENCE |
| 6. REQUIRING OFFICE |
18. ESTIMATED
TOTAL PRICE
| DI-PSSS-81525C |
| SOW PARA 3.5.2.6 |
NAWCTSD RRL TSPM
| 7. DD 250 REQ |
| 9. DIST STATEMENT |
| 10. FREQUENCY |
| 12. DATE OF FIRST SUBMISSION |
| 14. DISTRIBUTION |
| REQUIRED |
| SEE BLK 16 |
| SEE BLOCK 16 |
| a. ADDRESSEE |
| b. COPIES |
| 8. APP CODE |
| SEE BLOCK 16 |
| 11. AS OF DATE |
| 13. DATE IF SUBSEQUENT SUBM. |
| 16. REMARKS |
| NAWCTSD TPOC |
| 1 |
1. BLK 4: DELETE ALL PARAGRAPHS EXCEPT 2.4.1, 2.4.2, AND 2.4.3.
2. BLK 10/12/13: SUBMISSIONS SHALL BE PER EACH COURSE, DELIVERED IN INCREMENTS IN ACCORDANCE WITH (IAW) THE GOVERNMENT-ACCEPTED INTEGRATED MASTER SCHEDULE (IMS). FIRST SUBMISSION SHALL COINCIDE WITH SUBMISSION OF TEST PACKAGE (ASSESSMENTS) CDRL F005 ONCE ALL INCREMENTS OF A COURSE HAVE BEEN INITIALLY DELIVERED. SECOND SUBMISSION SHALL BE PRIOR TO TRAIN THE TRAINER EVENT. FINAL SUBMISSION SHALL BE POST COURSE PILOT EVENT.
3. BLK 14: SUBMISSIONS SHALL BE VIA THE CONTRACTOR ONLINE MANAGEMENT SYSTEM, INCLUDING NAWCTSD FORM 4330 WITH THE APPROPRIATE INFORMATION FILLED IN. AN E-MAIL INDICATING THE SUBMISSION IS READY FOR GOVERNMENT REVIEW SHALL BE SENT TO DESIGNATED ADDRESSES, ALSO INDICATING THE DATE GOVERNMENT REVIEW COMMENCES, THE CONTRACTOR SHALL PROVIDE THE GOVERNMENT WITH AT LEAST ONE DAY NOTICE PRIOR TO THE BEGINNING OF THE GOVERNMENT REVIEW PERIOD. EMAIL ADDRESSES ARE IN SECTION F OF THE CONTRACT SCHEDULE.
4. THE GOVERNMENT WILL HAVE 20 WORKING DAYS FOR REVIEW AND ACCEPTANCE/CONDITIONAL ACCEPTANCE/REJECTION OF EACH INCREMENTALLY DELIVERED SUBMISSION. CONTRACTOR INCORPORATION OF GOVERNMENT COMMENTS SHALL BE IN 10 WORKING DAYS OF RECEIPT OF COMMENTS.
5. ACCEPTANCE OF CHANGES IN CONTRACT REQUIREMENTS/STANDARDS/SPECIFICATIONS DOES NOT CONSTITUTE GOVERNMENT AGREEMENT TO THOSE CHANGES. ONLY BY DIRECTION OF THE CONTRACTING OFFICER CAN SUCH CHANGES BE MADE.
6. THE DISTRIBUTION STATEMENT SHALL BE IAW THE HIGHEST CLASSIFICATION MARKING OF THE SOURCE MATERIAL FOR THE DELIVERABLE:
NAWCTSD PCO
NAWCTSD PJM
| G. PREPARED BY |
| H. DATE |
| I. APPROVED BY |
| J. DATE |
VINCE FLANGO, RRL FY22 CONTENT CONVERSION TPOC
LCDR MAURA BETTS, RRL FY22PROGRAM MANAGER
| DD FORM 1423-1, FEB 2001 | PREVIOUS EDITION MAY BE USED | Page 7 of 13 Pages |
| CONTRACT DATA REQUIREMENTS LIST (CDRL) | |
(1 Data Item) Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
| A. CONTRACT LINE ITEM NO. |
| B. EXHIBIT |
| C. CATEGORY: |
| 1010, 1011, 1012, 1013, 1014, 1015, 1016, 1017, 1018, 1019, 1020 |
| F |
| TDP ____ |
| TM _____ |
| OTHER TRAINING DATA |
| D. SYSTEM/ITEM |
| E. CONTRACT/PR NO. |
| F. CONTRACTOR |
S2025 FY22 RRL CONTENT CONVERSION
| 1. DATA ITEM NO. |
| 2. TITLE OF DATA ITEM |
| 3. SUBTITLE |
17. PRICE GROUP
| F007 |
| TRAINING CONDUCT SUPPORT DOCUMENT |
| CURRICULUM PACKAGE (LP, TG, HANDOUTS, MATERIALS, PERFORMANCE SUPPORT AND SOJT PRODUCTS) |
| 4. AUTHORITY (Data Acquisition Document No.) |
| 5. CONTRACT REFERENCE |
| 6. REQUIRING OFFICE |
18. ESTIMATED
TOTAL PRICE
| DI-PSSS-81523D |
| 3.5.2.7, 3.5.3.5, 3.5.4.5.1, 3.5.4.5.4, 3.5.7.2, 3.5.8.2 |
| NAWCTSD RRL TSPM |
| 7. DD 250 REQ |
| 9. DIST STATEMENT |
| 10. FREQUENCY |
| 12. DATE OF FIRST SUBMISSION |
| 14. DISTRIBUTION |
| LT |
| REQUIRED |
| ASREQ |
| SEE BLOCK 16 |
| a. ADDRESSEE |
| b. COPIES |
| 8. APP CODE |
| SEE BLOCK 16 |
| 11. AS OF DATE |
| 13. DATE IF SUBSEQUENT SUBM. |
A
| 16. REMARKS |
| NAWCTSD TPOC |
| 1 |
1. BLK 4: DELETE ALL PARAGRAPHS EXCEPT 3.2 – 3.2.2.4, 3.2.2.7 – 3.2.2.8, 3.2.2.13 – 3.2.2.17, 3.2.2.19 – 3.2.2.25, 3.2.2.27 – 3.2.2.30, 3.2.2.32 – 3.2.2.33, 3.2.2.36 – 3.2.2.37, 3.2.3 – 3.2.4, 3.3 – 3.3.7, AND 3.4 – 3.5.2.5.
2. BLK 10/12/13: SUBMISSIONS SHALL BE IN ACCORDANCE WITH (IAW) THE GOVERNMENT-ACCEPTED INTEGRATED MASTER SCHEDULE (IMS), AND DELIVERED AT THE SAME TIME AS CORRESPONDING TRAINING MATERIALS IAW CDRLS F003 (SSBS) AND F004 (OSLS). SUBSEQUENT SUBMISSIONS SHALL BE DELIVERED PRIOR TO T3, AND PRIOR TO COURSE PILOT. FINAL SUBMISSION SHALL BE PROVIDED NLT TWO MONTHS PRIOR TO CONTRACT END. TO AID REVIEW OF COMPLEX MEDIA PRODUCTS, SUBMISSIONS SHALL BE SCHEDULED IN THE IMS TO ALSO ACCOMPANY SOFTWARE PRODUCT DESIGN (SPD) (A002), SOFTWARE PRODUCT PACKAGE (SPP) (A005), AND LOGIC TABLES (A008).
3. BLK 14: SUBMISSIONS SHALL BE IN MICROSOFT OFFICE 2010 OR LATER FORMAT, OR PDF 2010 OR LATER FORMAT. SUBMISSIONS SHALL BE POSTED TO THE CONTRACTOR ONLINE MANAGEMENT SYSTEM, INCLUDING NAWCTSD FORM 4330 WITH THE APPROPRIATE INFORMATION FILLED IN. AN E-MAIL INDICATING THE SUBMISSION IS READY FOR GOVERNMENT REVIEW SHALL BE SENT TO DESIGNATED ADDRESSES, ALSO INDICATING THE DATE GOVERNMENT REVIEW COMMENCES. THE CONTRACTOR SHALL PROVIDE THE GOVERNMENT WITH AT LEAST ONE DAY NOTICE PRIOR TO THE BEGINNING OF THE GOVERNMENT REVIEW PERIOD. EMAIL ADDRESSES ARE IN SECTION F OF THE CONTRACT SCHEDULE.
4. FOR EACH INCREMENTAL SUBMISSION OF COURSEWARE LESSONS, THE GOVERNMENT WILL HAVE 20 WORKING DAYS FOR REVIEW AND ACCEPTANCE/CONDITIONAL ACCEPTANCE/REJECTION OF EACH SUBMISSION.
5. FOR EACH SUBMISSION OF COURSEWARE LESSONS, CONTRACTOR INCORPORATION OF GOVERNMENT COMMENTS SHALL BE INCORPORATED WITHIN 10 WORKING DAYS OF RECEIPT OF COMMENTS IF ACCEPTED WITH COMMENTS OR REJECTED.
6. ACCEPTANCE OF CHANGES IN CONTRACT REQUIREMENTS/STANDARDS/SPECIFICATIONS DOES NOT CONSTITUTE GOVERNMENT AGREEMENT TO THOSE CHANGES. ONLY BY DIRECTION OF THE CONTRACTING OFFICER CAN SUCH CHANGES BE MADE.
THE DISTRIBUTION STATEMENT SHALL BE IAW THE HIGHEST CLASSIFICATION MARKING OF THE SOURCE MATERIAL FOR THE DELIVERABLE
NAWCTSD PCO
NAWCTSD PJM
| G. PREPARED BY |
| H. DATE |
| I. APPROVED BY |
| J. DATE |
VINCE FLANGO, RRL FY22 CONTENT CONVERSION TPOC
LCDR MAURA BETTS, RRL FY22PROGRAM MANAGER
| DD FORM 1423-1, FEB 2001 | PREVIOUS EDITION MAY BE USED | Page 8 of 13 Pages |
| CONTRACT DATA REQUIREMENTS LIST (CDRL) | |
(1 Data Item) Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
| A. CONTRACT LINE ITEM NO. |
| B. EXHIBIT |
| C. CATEGORY: |
| 1010, 1011, 1012, 1013, 1014, 1015, 1016, 1017, 1018, 1019, 1020 |
| F |
| TDP ____ |
| TM _____ |
| OTHER TRAINING DATA |
| D. SYSTEM/ITEM |
| E. CONTRACT/PR NO. |
| F. CONTRACTOR |
S2025 FY22 RRL CONTENT CONVERSION
| 1. DATA ITEM NO. |
| 2. TITLE OF DATA ITEM |
| 3. SUBTITLE |
17. PRICE GROUP
| F008 |
| TRAINING PROGRAM STRUCTURE DOCUMENT |
TRAINING COURSE CONTROL DOCUMENT (TCCD), TRAINING PROJECT PLAN (TPP), COUSRSE MASTER SCHEDULE (CMS), AND RESOURCE REQUIREMENTS LIST (RRL)
| 4. AUTHORITY (Data Acquisition Document No.) |
| 5. CONTRACT REFERENCE |
| 6. REQUIRING OFFICE |
18. ESTIMATED
TOTAL PRICE
| DI-SESS-81521B |
| 3.5.2.8, 3.5.4.5.1, 3.5.4.5.4, 3.5.7.2, 3.5.8.2 |
| NAWCTSD RRL TSPM |
| 7. DD 250 REQ |
| 9. DIST STATEMENT |
| 10. FREQUENCY |
| 12. DATE OF FIRST SUBMISSION |
| 14. DISTRIBUTION |
| LT |
| REQUIRED |
| ASREQ |
| SEE BLOCK 16 |
| a. ADDRESSEE |
| b. COPIES |
| 8. APP CODE |
| SEE BLOCK 16 |
| 11. AS OF DATE |
| 13. DATE IF SUBSEQUENT SUBM. |
A
| 16. REMARKS |
| NAWCTSD TPOC |
| 1 |
1. BLK 4: DELETE ALL PARAGRAPHS EXCEPT 2.3.1a-j, 2.3.1l-p, 2.3.1s, 2.3.1u-v, 2.3.1x-y, 2.3.2a-g, 2.3.2i-m, 2.3.3-2.3.4a(1), 2.3.4a(3), 2.3.4b(3)-(4), 2.3.4c(1), 2.3.4c(2)(c), 2.3.4c(3)-(4), 2.3.4c(5)(c), 2.3.4d(1)-(3), 2.3.4f(1)(a)-(c), 2.3.4f(2), 2.3.6, 2.3.7, 2.3.8a-k, 2.3.8n, 2.3.8p, 2.3.10, 2.3.13a-f, 2.3.13h-j, 2.3.13o-p, 2.3.13r-s
2. BLK 10/12/13: SUBMISSIONS SHALL BE IN ACCORDANCE WITH (IAW) THE GOVERNMENT-ACCEPTED INTEGRATED MASTER SCHEDULE (IMS). TO AID REVIEW OF COMPLEX MEDIA PRODUCTS, SUBMISSIONS SHALL BE SCHEDULED IN THE IMS TO ALSO ACCOMPANY SOFTWARE PRODUCT DESIGN (SPD) (A002), SOFTWARE PRODUCT PACKAGE (SPP) (A005), AND LOGIC TABLES (A008).
3. BLK 14: SUBMISSIONS SHALL BE IN MICROSOFT OFFICE (WORD) 2010 OR LATER FORMAT. SUBMISSIONS SHALL BE POSTED TO THE CONTRACTOR ONLINE MANAGEMENT SYSTEM, INCLUDING NAWCTSD FORM 4330 WITH THE APPROPRIATE INFORMATION FILLED IN. AN E-MAIL INDICATING THE SUBMISSION IS READY FOR GOVERNMENT REVIEW SHALL BE SENT TO DESIGNATED ADDRESSES, ALSO INDICATING THE DATE GOVERNMENT REVIEW COMMENCESTHE CONTRACTOR SHALL PROVIDE THE GOVERNMENT WITH AT LEAST ONE DAY NOTICE PRIOR TO THE BEGINNING OF THE GOVERNMENT REVIEW PERIOD. EMAIL ADDRESSES ARE IN SECTION F OF THE CONTRACT SCHEDULE.
4. THE GOVERNMENT SHALL HAVE 20 WORKING DAYS FOR REVIEW AND ACCEPTANCE/CONDITIONAL ACCEPTANCE/REJECTION.
5. CONTRACTOR INCORPORATION OF GOVERNMENT COMMENTS SHALL BE WITHIN 10 WORKING DAYS OF RECEIPT OF COMMENTS IF ACCEPTED CONDITIONALLY/REJECTED.
6. ACCEPTANCE OF CHANGES IN CONTRACT REQUIREMENTS/STANDARDS/SPECIFICATIONS DOES NOT CONSTITUTE GOVERNMENT AGREEMENT TO THOSE CHANGES. ONLY BY DIRECTION OF THE CONTRACTING OFFICER CAN SUCH CHANGES BE MADE.
7. THE DISTRIBUTION STATEMENT SHALL BE IAW THE HIGHEST CLASSIFICATION MARKING OF THE SOURCE MATERIAL FOR THE DELIVERABLE:
NAWCTSD PCO
NAWCTSD PJM
| G. PREPARED BY |
| H. DATE |
| I. APPROVED BY |
| J. DATE |
VINCE FLANGO, RRL FY22 CONTENT CONVERSION TPOC
LCDR MAURA BETTS, RRL FY22PROGRAM MANAGER
| DD FORM 1423-1, FEB 2001 | PREVIOUS EDITION MAY BE USED | Page 9 of 13 Pages |
| CONTRACT DATA REQUIREMENTS LIST (CDRL) | |
(1 Data Item) Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
| A. CONTRACT LINE ITEM NO. |
| B. EXHIBIT |
| C. CATEGORY: |
| 1010, 1011, 1012, 1013, 1014, 1015, 1016, 1017, 1018, 1019, 1020 |
| F |
| TDP ____ |
| TM _____ |
| OTHER TRAINING DATA |
| D. SYSTEM/ITEM |
| E. CONTRACT/PR NO. |
| F. CONTRACTOR |
S2025 FY22 RRL CONTENT CONVERSION
| 1. DATA ITEM NO. |
| 2. TITLE OF DATA ITEM |
| 3. SUBTITLE |
17. PRICE GROUP
| F009 |
| TRAINING SYSTEM SUPPORT DOCUMENT |
| TRAINING SYSTEMS SUPPORT PROCEDURES |
| 4. AUTHORITY (Data Acquisition Document No.) |
| 5. CONTRACT REFERENCE |
6. REQUIRING OFFICE
18. ESTIMATED
TOTAL PRICE
| DI-PSSS-81527D |
| SOW PARA 3.5.2.9, 3.5.3.5, 3.5.7.2, 3.5.8.2 |
| NAWCTSD RRL TSPM |
| 7. DD 250 REQ |
| 9. DIST STATEMENT |
| 10. FREQUENCY |
| 12. DATE OF FIRST SUBMISSION |
| 14. DISTRIBUTION |
| LT |
| REQUIRED |
| ASREQ |
| SEE BLK 16 |
| a. ADDRESSEE |
| b. COPIES |
| 8. APP CODE |
| SEE BLOCK 16 |
| 11. AS OF DATE |
| 13. DATE IF SUBSEQUENT SUBM. |
A
| 16. REMARKS |
| NAWCTSD TPOC |
| 1 |
BLK 4: DELETE ALL PARAGRAPHS EXCEPT 3.2, 3.2.1, 3.2.2.3-3.2.2.5.5, 3.2.3.2-3.2.3.4, 3.2.4, 3.3, 3.3.1, 3.3.1.1-3.3.2.4.10, 3.3.2.4.11-3.3.2.4.12, 3.3.2.6, 3.3.6.1-3.3.6.4, 3.3.6.6, 3.3.7, 3.3.8, 3.3.9.2-3.3.9.4, 2.3.9.7-2.3.9.8, 3.3.10.1, 3.3.102.1-3.3.10.2.8, 3.3.10.210-3.3.10.2.12, 3.3.10.3.
1. BLK 10/12/13: SUBMISSIONS SHALL BE IN ACCORDANCE WITH (IAW) THE GOVERNMENT-ACCEPTED INTEGRATED MASTER SCHEDULE (IMS). SUBMISSIONS SHALL INCLUDE A DRAFT VERSION, AND A FINAL VERSION.
2. BLK 14: SUBMISSIONS SHALL BE IN MICROSOFT OFFICE (WORD) 2010 OR LATER FORMAT. SUBMISSIONS SHALL BE POSTED TO THE CONTRACTOR ONLINE MANAGEMENT SYSTEM, INCLUDING NAWCTSD FORM 4330 WITH THE APPROPRIATE INFORMATION FILLED IN. AN E-MAIL INDICATING THE SUBMISSION IS READY FOR GOVERNMENT REVIEW SHALL BE SENT TO DESIGNATED ADDRESSES, ALSO INDICATING THE DATE GOVERNMENT REVIEW COMMENCES. THE CONTRACTOR SHALL PROVIDE THE GOVERNMENT WITH AT LEAST ONE DAY NOTICE PRIOR TO THE BEGINNING OF THE GOVERNMENT REVIEW PERIOD. EMAIL ADDRESSES ARE IN SECTION F OF THE CONTRACT SCHEDULE.
3. THE GOVERNMENT SHALL HAVE 20 WORKING DAYS FOR REVIEW AND ACCEPTANCE/CONDITIONAL ACCEPTANCE/REJECTION. FOR THE FINAL SUBMISSION, THE GOVERNMENT WILL HAVE 10 WORKING DAYS FOR REVIEW AND APPROVAL/ REJECTION.
4. CONTRACTOR INCORPORATION OF GOVERNMENT COMMENTS SHALL BE WITHIN 10 WORKING DAYS OF RECEIPT OF COMMENTS IF ACCEPTED WITH COMMENTS OR REJECTED.
5. ACCEPTANCE OF CHANGES IN CONTRACT REQUIREMENTS/STANDARDS/SPECIFICATIONS DOES NOT CONSTITUTE GOVERNMENT AGREEMENT TO THOSE CHANGES. ONLY BY DIRECTION OF THE CONTRACTING OFFICER CAN SUCH CHANGES BE MADE.
6. THE DISTRIBUTION STATEMENT SHALL BE IAW THE HIGHEST CLASSIFICATION MARKING OF THE SOURCE MATERIAL FOR THE DELIVERABLE:
NAWCTSD PCO
NAWCTSD PJM
| G. PREPARED BY |
| H. DATE |
| I. APPROVED BY |
| J. DATE |
VINCE FLANGO, RRL FY22 CONTENT CONVERSION TPOC
LCDR MAURA BETTS, RRL FY22PROGRAM MANAGER
| DD FORM 1423-1, FEB 2001 | PREVIOUS EDITION MAY BE USED | Page 10 of 13 Pages |
| CONTRACT DATA REQUIREMENTS LIST (CDRL) | |
(1 Data Item) Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
| A. CONTRACT LINE ITEM NO. |
| B. EXHIBIT |
| C. CATEGORY: |
| 1010, 1011, 1012, 1013, 1014, 1015, 1016, 1017, 1018, 1019, 1020 |
| F |
| TDP ____ |
| TM _____ |
| OTHER TRAINING DATA |
| D. SYSTEM/ITEM |
| E. CONTRACT/PR NO. |
| F. CONTRACTOR |
S2025 FY22 RRL CONTENT CONVERSION
| 1. DATA ITEM NO. |
| 2. TITLE OF DATA ITEM |
| 3. SUBTITLE |
17. PRICE GROUP
| F00A |
| INSTRUCTIONAL MEDIA PACKAGE |
| MEDIA SOURCE FILES |
| 4. AUTHORITY (Data Acquisition Document No.) |
| 5. CONTRACT REFERENCE |
| 6. REQUIRING OFFICE |
18. ESTIMATED
TOTAL PRICE
| DI-PSSS-81526C |
| 3.5.2.10.6, 3.5.2.11.4, 3.5.2.11.6, 3.5.2.11.7, 3.5.3.7, 3.5.4.5.5.4, 3.5.4.5.5.6, 3.5.7.2, 3.5.8.2 |
| NAWCTSD RRL TSPM |
| 7. DD 250 REQ |
| 9. DIST STATEMENT |
| 10. FREQUENCY |
| 12. DATE OF FIRST SUBMISSION |
| 14. DISTRIBUTION |
| LT |
| REQUIRED |
| ASREQ |
| SEE BLOCK 16 |
| a. ADDRESSEE |
| b. COPIES |
| 8. APP CODE |
| SEE BLOCK 16 |
| 11. AS OF DATE |
| 13. DATE IF SUBSEQUENT SUBM. |
A
| 16. REMARKS |
| NAWCTSD TPOC |
| 1 |
1. BLK 4: DELETE ALL PARAGRAPHS EXCEPT 2.6, 2.6.1c-2.6.1h, 2.6.2 -2.6.2b(5), 2.6.3 -2.6.3c(2)(c), 2.6.3c(2)(e) – 2.6.3c(2)(g), 2.6.3c(2)(k)-2.6.3c(2)(m), 2.6.3c(2)(s), 2.6.4-2.7.2f.
2. BLK 10/12/13: SUBMISSIONS SHALL BE IN ACCORDANCE WITH (IAW) THE GOVERNMENT-ACCEPTED INTEGRATED MASTER SCHEDULE (IMS).
3. BLK 14: SUBMISSIONS SHALL BE VIA EXTERNAL HARD DRIVE. NAWCTSD FORM 4330 WITH THE APPROPRIATE INFORMATION FILLED IN SHALL BE POSTED TO THE CONTRACTORONLINE MANAGEMENT SYSTEM AND AN E-MAIL INDICATING THE SUBMISSION IS READY FOR GOVERNMENT REVIEW SHALL BE SENT TO DESIGNATED ADDRESSES, ALSO INDICATING THE DATE GOVERNMENT REVIEW COMMENCES. . THE CONTRACTOR SHALL PROVIDE THE GOVERNMENT WITH AT LEAST ONE DAY NOTICE PRIOR TO THE BEGINNING OF THE GOVERNMENT REVIEW PERIOD. EMAIL ADDRESSES ARE IN SECTION F OF THE CONTRACT SCHEDULE.
4. THE GOVERNMENT WILL HAVE 5 WORKING DAYS FOR REVIEW AND ACCEPTANCE/REJECTION.
5. CONTRACTOR INCORPORATION OF GOVERNMENT COMMENTS SHALL BE WITHIN 5 WORKING DAYS OF RECEIPT OF COMMENTS IF REJECTED.
6. WHEN APPLICABLE, PAPER-BASED AND ELECTRONIC COPIES OF COPYRIGHT PERMISSIONS SHALL BE PROVIDED IN MICROSOFT OFFICE (WORD) 2010 OR LATER.
7. ACCEPTANCE OF CHANGES IN CONTRACT REQUIREMENTS/STANDARDS/SPECIFICATIONS DOES NOT CONSTITUTE GOVERNMENT AGREEMENT TO THOSE CHANGES. ONLY BY DIRECTION OF THE CONTRACTING OFFICER CAN SUCH CHANGES BE MADE.
8. THE DISTRIBUTION STATEMENT SHALL BE IAW THE HIGHEST CLASSIFICATION MARKING OF THE SOURCE MATERIAL FOR THE DELIVERABLE:
NAWCTSD PCO
NAWCTSD PJM
| G. PREPARED BY |
| H. DATE |
| I. APPROVED BY |
| J. DATE |
VINCE FLANGO, RRL FY22 CONTENT CONVERSION TPOC
LCDR MAURA BETTS, RRL FY22PROGRAM MANAGER
| DD FORM 1423-1, FEB 2001 | PREVIOUS EDITION MAY BE USED | Page 11 of 13 Pages |
| ONTRACT DATA REQUIREMENTS LIST (CDRL) | |
(1 Data Item) Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
| A. CONTRACT LINE ITEM NO. |
| B. EXHIBIT |
| C. CATEGORY: |
| 1010, 1011, 1012, 1013, 1014, 1015, 1016, 1017, 1018, 1019, 1020 |
| F |
| TDP ____ |
| TM _____ |
| OTHER TRAINING DATA |
| D. SYSTEM/ITEM |
| E. CONTRACT/PR NO. |
| F. CONTRACTOR |
S2025 FY22 RRL CONTENT CONVERSION
| 1. DATA ITEM NO. |
| 2. TITLE OF DATA ITEM |
| 3. SUBTITLE |
17. PRICE GROUP
| F00B |
| INSTRUCTIONAL MEDIA PACKAGE |
| FINAL CURRICULUM DELIVERY |
| 4. AUTHORITY (Data Acquisition Document No.) |
| 5. CONTRACT REFERENCE |
| 6. REQUIRING OFFICE |
18. ESTIMATED
TOTAL PRICE
| DI-PSSS-81526C |
| 3.5.2.10.7, 3.5.2.11.8, 3.5.3.8, 3.5.4.5.5.6.1, 3.5.7.1, 3.5.7.2, 3.5.8.2, 3.5.8.3 |
| NAWCTSD RRL TSPM |
| 7. DD 250 REQ |
| 9. DIST STATEMENT |
| 10. FREQUENCY |
| 12. DATE OF FIRST SUBMISSION |
| 14. DISTRIBUTION |
| SEE BLK 16 |
| a. ADDRESSEE |
| b. COPIES |
| 8. APP CODE |
| SEE BLOCK 16 |
| 11. AS OF DATE |
| 13. DATE IF SUBSEQUENT SUBM. |
A
| 16. REMARKS |
| NAWCTSD TPOC |
| 1 |
1. BLK 4: DELETE ALL PARAGRAPHS EXCEPT 2.1, 2.3.10, 2.6.2, 2.6.3-2.6.3B(2), AND 2.6.5B.
2. BLK 10/12/13: SUBMISSIONS SHALL BE IN ACCORDANCE WITH (IAW) THE GOVERNMENT-ACCEPTED INTEGRATED MASTER SCHEDULE (IMS)..
3. BLK 14: A TOTAL OF ONE (1) SET OF FINAL UNCLASSIFIED CURRICULUM SHALL BE DELIVERED VIA DOD SAFE (https://safe.apps.mil/) TO THE DESIGNATED E-MAIL ADDRESSES. A TOTAL OF TWO (2) SETS OF FINAL CLASSIFIED CURRICULUM CD-ROM/DVDs SHALL BE DELIVERED TO THE DESIGNATED ADDRESSES. NAWCTSD FORM 4330 WITH THE APPROPRIATE INFORMATION FILLED IN SHALL BE POSTED TO THE CONTRACTORONLINE MANAGEMENT SYSTEM AND AN E-MAIL INDICATING THE SUBMISSION IS READY FOR GOVERNMENT REVIEW SHALL BE SENT TO DESIGNATED ADDRESSES, ALSO INDICATING THE DATE GOVERNMENT REVIEW COMMENCES. THE CONTRACTOR SHALL PROVIDE THE GOVERNMENT WITH AT LEAST ONE DAY NOTICE PRIOR TO THE BEGINNING OF THE GOVERNMENT REVIEW PERIOD. EMAIL ADDRESSES ARE IN SECTION F OF THE CONTRACT SCHEDULE.
4. FOR THE SUBMISSION, THE GOVERNMENT WILL HAVE 10 WORKING DAYS FOR REVIEW AND APPROVAL/ACCEPTANCE/REJECTION.
5. CONTRACTOR INCORPORATION OF GOVERNMENT COMMENTS SHALL BE WITHIN 5 WORKING DAYS OF RECEIPT OF COMMENTS IF REJECTED.
6. IN ADDITION TO REQUIREMENTS OUTLINED IN DI-SESS-81526C, EACH SET OF THE UNCLASSIFIED FINAL CURRICULUM SENT VIA DOD SAFE AND THE CLASSIFIED FINAL CURRICULUM CDS/DVDS SHALL CONTAIN, AT A MINIMUM, ALL FILES ASSOCIATED WITH THE CREATION OF THE CURRICULUM, ALL DELIVERABLES PROVIDED TO THE GOVERNMENT DURING THE EFFORT, IN GOVERNMENT-ACCEPTED FINAL FORMAT, AND ALL FILES ASSOCIATED WITH THE DEPLOYMENT OF THE CURRICULUM. EACH SET OF THE FINAL UNCLASSIFIED CURRICULUM DELIVERED VIA DOD SAFE SHALL BE TITLED AND LABELED ACCORDINGLY. ALL FILES ASSOCIATED WITH THE DEPLOYMENT OF THE CLASSIFIED CURRICULUM WITHIN EACH SET OF THE FINAL CLASSIFIED CURRICULUM CD-ROM/DVD SHALL BE TITLED AND LABELED ACCORDINGLY.
7. ACCEPTANCE OF CHANGES IN CONTRACT REQUIREMENTS/STANDARDS/SPECIFICATIONS DOES NOT CONSTITUTE GOVERNMENT AGREEMENT TO THOSE CHANGES. ONLY BY DIRECTION OF THE CONTRACTING OFFICER CAN SUCH CHANGES BE MADE.
8. THE DISTRIBUTION STATEMENT SHALL BE IAW THE HIGHEST CLASSIFICATION MARKING OF THE SOURCE MATERIAL FOR THE DELIVERABLE.
NAWCTSD PCO
NAWCTSD PJM
| G. PREPARED BY |
| H. DATE |
| I. APPROVED BY |
| J. DATE |
VINCE FLANGO, RRL FY22 CONTENT CONVERSION TPOC
LCDR MAURA BETTS, RRL FY22PROGRAM MANAGER
| DD FORM 1423-1, FEB 2001 | PREVIOUS EDITION MAY BE USED | Page 12 of 13 Pages |
| CONTRACT DATA REQUIREMENTS LIST (CDRL) | |
(1 Data Item) Form Approved
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
| A. CONTRACT LINE ITEM NO. |
| B. EXHIBIT |
| C. CATEGORY: |
| 1017, 1020 |
| F |
| TDP ____ |
| TM _____ |
| OTHER TRAINING DATA |
| D. SYSTEM/ITEM |
| E. CONTRACT/PR NO. |
| F. CONTRACTOR |
S2025 FY22 RRL CONTENT CONVERSION
| 1. DATA ITEM NO. |
| 2. TITLE OF DATA ITEM |
| 3. SUBTITLE |
17. PRICE GROUP
| F00C |
| COURSE CONDUCT INFORMATION PACKAGE |
| TRAIN THE TRAINER (T3) |
| 4. AUTHORITY (Data Acquisition Document No.) |
| 5. CONTRACT REFERENCE |
| 6. REQUIRING OFFICE |
18. ESTIMATED
TOTAL PRICE
| DI-PSSS-81522D |
| SOW PARA 3.5.7, 3.5.7.2, 3.5.8.2 |
| NAWCTSD RRL TSPM |
| 7. DD 250 REQ |
| 9. DIST STATEMENT |
| 10. FREQUENCY |
| 12. DATE OF FIRST SUBMISSION |
| 14. DISTRIBUTION |
| LT |
| REQUIRED |
| 1TIME |
| SEE BLK 16 |
| a. ADDRESSEE |
| b. COPIES |
| 8. APP CODE |
| SEE BLOCK 16 |
| 11. AS OF DATE |
| 13. DATE IF SUBSEQUENT SUBM. |
A
| 16. REMARKS |
| NAWCTSD TPOC |
| 1 |
1. BLK 4: DELTE ALL PARAGRAPHS EXCEPT 3.2.1.3, 3.2.1.7, 3.2.1.8, 3.4.2.4-3.4.2.8, 3.4.2.15, AND 3.5.6.
2. BLK 13: SUBMISSION SHALL BE DELIVERED NLT TEN (10) WORKING DAYS AFTER THE CONCLUSION OF T3 EVENT.
3. BLK 14: SUBMISSION SHALL BE IN MICROSOFT OFFICE (WORD) 2010 OR LATER. SUBMISSION SHALL BE POSTED TO THE CONTRACTOR ONLINE MANAGEMENT SYSTEM. AN E-MAIL INDICATING THE SUBMISSION IS READY FOR GOVERNMENT REVIEW SHALL BE SENT TO DESIGNATED ADDRESSES, INDICATE THE DATE THE GOVERNMENT REVIEW COMMENCES, AND INCLUDE NAWCTSD FORM 4330 WITH THE APPROPRIATE INFORMATION FILLED IN. THE CONTRACTOR SHALL PROVIDE THE GOVERNMENT WITH AT LEAST ONE DAYS NOTICE PRIOR TO THE BEGINNING OF THE GOVERNMENT REVIEW PERIOD. EMAIL ADDRESSES ARE IN SECTION F OF THE CONTRACT SCHEDULE.FOR THE SUBMISSION,
4. THE GOVERNMENT WILL HAVE 10 WORKING DAYS FOR REVIEW AND APPROVAL/ACCEPTANCE/REJECTION.
5. CONTRACTOR INCORPORATION OF GOVERNMENT COMMENTS SHALL BE WITHIN 5 WORKING DAYS OF RECEIPT OF COMMENTS IF REJECTED.
6. ACCEPTANCE OF CHANGES IN CONTRACT REQUIREMENTS/STANDARDS/SPECIFICATIONS DOES NOT CONSTITUTE GOVERNMENT AGREEMENT TO THOSE CHANGES. ONLY BY DIRECTION OF THE CONTRACTING OFFICER CAN SUCH CHANGES BE MADE.
7. THE DISTRIBUTION STATEMENT SHALL BE IAW…