This is an Operation and Maintenance Plan for the Emergency Watershed Protection Program prepared for Volusia County, Florida's Road & Bridge Division, specifically addressing the B-19 Sweetwater Creek Streambank Stabilization project (MIL-VOL-002). The plan outlines comprehensive maintenance requirements for vegetation management, including weed and brush control through mowing or chemical application, insect and disease monitoring through the local Agricultural Extension Service, and revegetation procedures for areas lacking adequate cover. Revegetation specifications include topsoil application at 3.1 cubic yards per 1,000 square feet, fertilization and liming based on soil tests, bahiagrass seeding at 2-3 pounds per 1,000 square feet with mulch coverage, and post-germination ammonium nitrate applications for establishment. The plan also addresses structural maintenance of concrete pillow forms, requiring periodic inspections within 30 days of completion, after major storm events, and annually, with prompt repair of any damage and removal of excess vegetation using herbicides as needed.
The operation and maintenance schedule mandates immediate correction of all identified deficiencies, with inspection reports and maintenance records maintained on file. Equipment and supply requirements include a pickup truck for inspections, a tractor with disk harrow and mower, bahiagrass sod or seed as needed, fertilizer and lime determined by soil testing, mulch materials, and miscellaneous tools such as drop-type fertilizer spreaders and weed eaters. Fuel, oil, lubrication, and maintenance supplies for vehicles and equipment are required on an as-needed basis to ensure continued facility performance and erosion control at the streambank stabilization site.
View the file
Other files
Show 40 more
Latest 50 of 52 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OPERATION AND MAINTENANCE PLAN
Emergency Watershed Protection Program
MIL-VOL-002 / B-19 CANAL SITE
Road & Bridge Division Volusia County, Florida
OPERATION AND MAINTENANCE NEEDS
This site will require the Road & Bridge Division to perform periodic inspections and operation and maintenance activities to maintain satisfactory performance. The following recommendations will help the Road & Bridge Division in performing adequate operation and maintenance.
I. VEGETATION
A. Weed and Brush Control
Mow to control weeds, briars, and bushes. On areas inaccessible to power mowing equipment, weed and brush control should be accomplished by hand or chemicals.
B. Insect and Disease Control
No disease problems should occur on bahiagrass, centipede or common bermudagrass.
Identification of pests and needed control should be obtained from local Agricultural Extension Service Office.
C. Revegetation
As soon as possible, repair sites that become devoid of vegetation. This will usually occur when adequate vegetative cover was not initially established. If this is not the case, study the situation carefully to determine the causes. This will probably be due to soil erosion or vehicles which may need special on-site assistance from the Natural Resources Conservation Service representative. Use the following recommendations for normal vegetation of smaller areas.
Fill the low or washed out areas with topsoil. The topsoil should be free of weed seeds, litter, and rocks, and have a high organic matter content. One inch of topsoil will require
3.1 cubic yards per 1,000 square feet.
Fertilize with 13-13-13 or similar fertilizer at a rate based on soil tests. Lime with dolomite at a rate based on soil tests. Incorporate fertilizer and lime into the upper six (6) inches of soil. After final grading, distribute bahiagrass seed uniformly over the area at a rate of 2 - 3 lbs. per 1000 square foot with a drop-type fertilizer spreader or cyclone-type broadcast spreader. Cover the area in one direction and then at right angles in the other direction. Cover the seed lightly one-fourth (1/4) inch deep. Firm the seed into the soil with a roller. After seeding, apply a mulch of one (1) inch or more of close fitting material, or up to four (4) inches of loose fitting material, so that about 25 percent of the ground is visible. Disk or spade in lightly at or near vertical angle. Starting 4 - 6 weeks after the seed has germinated, apply ammonium nitrate at the rate of three (3) pounds per 1,000 square feet every month until grass is well established.
Sod can be used instead of seed and will obviously revegetate the area quicker than seeding. The site preparation, liming, and fertilization is the same for seeding. Lay pieces of sod over the entire area on the contour with snug, even joints. Stagger the joints from strip to strip. Roll or tamp sod immediately following placement. Do not overlap the sod. On steep slopes secure sod to surface with wooden pegs or wire staples. If a dry period occurs, irrigate with one (1) inch of water every third day unless rain occurs. Do not exceed an application rate of one (1) inch per hour. After the area is revegetated, use the maintenance measures discussed in Sections III and IV.
II. STRUCTURES
A. Concrete Pillow Forms
The concrete pillow forms do not require any operation. Perform periodic inspections of the pillow forms for signs of damage and washouts, especially after major storm events.
Promptly repair any damaged sections with concrete and reestablishing vegetation.
Remove excess vegetation that has become established within the limits of the concrete pillow forms. Apply herbicides as need to control vegetation.
III. SCHEDULE OF INSPECTIONS
The facility should be inspected (1) 30 days after completion; (2) after each major storm or occurrence of any unusual condition that might adversely affect the measure; and (3) annually. All deficiencies should be corrected immediately. Reports of the inspection(s) and subsequent follow up maintenance shall be kept on file.
IV. SUPPLIES AND EQUIPMENT NEEDS FOR O&M
The following supplies and equipment will be needed to operate and maintain the facility:
One pick-up truck used for inspection as needed.
Tractor with disk harrow and mower as needed.
Gasoline for truck and tractor; oil, lubrication, and maintenance supplies for truck and tractor as needed.
Bahiagrass sod or seed as needed.
Fertilizer and lime as required by soil test.
Mulch as needed.
Miscellaneous small tools such as drop type fertilizer spreader, weed eaters, etc.