Exhibit_B_Dixon_Landing_Park_Demolition_Plan.docx

DOCX document 1 MB Posted

Attached to
Scoreboard Replacement Project
Solicitation number
25-1038
Issued by
Santa Clara County, California

About this file

This is a demolition plan exhibit for the City of Milpitas' Scoreboard Replacement Project (Bid No. 25-1038), detailing the removal scope across three municipal park locations. The project encompasses the complete demolition and removal of seven existing scoreboards located at Dixon Landing Park (three scoreboards on Fields 1, 2, and 3), Milpitas Sports Center, and Cardoza Park. For each scoreboard, the demolition work includes removal of the scoreboard unit itself, electrical disconnect, supporting structure, and footings to full depth, with voids from footing removal to be filled with engineered slurry fill to the existing grade level. A mandatory pre-bid conference is scheduled for May 22, 2025, at 10:00 am, with electronic bids due by June 17, 2025, at 12:00 pm Pacific Time. The selected contractor must complete all work within 75 calendar days from the Notice to Proceed and will be responsible for installation of seven new Daktronics scoreboards (models BA-2014 and BA-624) that will be provided by the city.

Qualified contractors must hold active C-45 and C-10 licensing classifications and perform a minimum of 50% of the work directly, with the option to subcontract up to 50%. Performance and payment bonds equal to 100% of the contract value are required, along with proof of insurance and non-collusion declarations. The city will provide all necessary building permits prior to work commencement. A local purchasing preference is available for bidders within 10 miles of the project location, with potential bid advantage up to 10% of the lowest bid. All work is subject to California prevailing wage requirements. Contractors must maintain active registration with the California Secretary of State and comply with Milpitas business license requirements. The contract award represents a firm offer that cannot be withdrawn for 90 days following the bid opening date.

View the file

Other files

File Type Posted
Scoreboard_Replacement_Project.pdf PDF
Scoreboard_Replacement_Project.pdf PDF
Scope_of_Work_and_Specifications_Final_Draft_05.01.25.docx DOCX document
Scope_of_Work_and_Specifications_Final_Draft_05.01.25.docx DOCX document
Demolition_Plan_by_Location.pdf PDF
Demolition_Plan_by_Location.pdf PDF
Engineering_Drawings_and_Pre-Check_Documents_5.2.25.pdf PDF
Engineering_Drawings_and_Pre-Check_Documents_5.2.25.pdf PDF
Electrical_Plan_by_Location.pdf PDF
Electrical_Plan_by_Location.pdf PDF
Exemplar_Construction_Agreement.pdf PDF
Exemplar_Construction_Agreement.pdf PDF
Milpitas_PO_Terms_and_Conditions.pdf PDF
Milpitas_PO_Terms_and_Conditions.pdf PDF
Milpitas_Sports_Center_SO337360_calcs_SS_2024-04-24.pdf PDF
Milpitas_Sports_Center_SO337360_calcs_SS_2024-04-24.pdf PDF
Exhibit_B_Cardoza_Park_Demolition_Plan.docx DOCX document
Exhibit_B_Dixon_Landing_Park_Demolition_Plan.docx DOCX document
Exhibit_B_Milpitas_Sports_Center_Demolition_Plan.docx DOCX document
IFB_Submittal_Forms_to_Complete.pdf PDF
Exhibit_B_Dixon_Landing_Park_Electrical_Plan.docx DOCX document
Exhibit_B_Milpitas_Sports_Center_Electrical_Plan.docx DOCX document
Exhibit_B_Dixon_Landing_Park_Electrical_Plan.docx DOCX document
Exhibit_B_Milpitas_Sports_Center_Electrical_Plan.docx DOCX document
Exhibit_B_Title_Sheet-_Dixon_Landing_Park_Scoreboard_Replacement_Project.docx DOCX document
Scoreboard_Replacement_Project_Specifications_6-3-24.docx DOCX document
Exhibit_B_Cardoza_Park_Electrical_Plan.docx DOCX document
Exhibit_B_Title_Sheet-_Dixon_Landing_Park_Scoreboard_Replacement_Project.docx DOCX document
IFB_Submittal_Forms_to_Complete.pdf PDF
Exhibit_B_Cardoza_Park_Demolition_Plan.docx DOCX document
Exhibit_B_Cardoza_Park_Electrical_Plan.docx DOCX document
Exhibit_B_Title_Sheet_-_MSC_Scoreboard_Replacement_Project.docx DOCX document
Exhibit_B_Milpitas_Sports_Center_Demolition_Plan.docx DOCX document
Exhibit_B_Title_Sheet_-_MSC_Scoreboard_Replacement_Project.docx DOCX document
Scoreboard_Replacement_Project_Specifications_6-3-24.docx DOCX document
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DIXON LANDING PARK

DEMOLITION PLAN

Dixon Field 2 Scoreboard Remove scoreboard, remove electrical disconnect, remove existing scoreboard supporting structure and remove footings full and complete depth.

Dixon Field 3 Scoreboard Remove scoreboard, remove electrical disconnect, remove existing scoreboard supporting structure and remove footings full and complete depth.

Note: Void left from removal of existing footings to be filled with engineered slurry fill to level of existing grade.

Dixon Field 1 Scoreboard Remove scoreboard, remove electrical disconnect, remove existing scoreboard supporting structure and remove footings full and complete depth.

image1.png