The document is an electrical plan exhibit for the Cardoza Park Scoreboard Replacement Project in Milpitas, California, involving the installation of a new BA2014 scoreboard at Cardoza Field. The City of Milpitas is seeking a qualified contractor to replace 7 scoreboards across 3 city locations, with the city providing the scoreboards and necessary building permits. The project requires complete removal of existing scoreboards, including footings, supporting structures, and electrical connections, and their replacement with new scoreboards. The contractor must perform at least 50% of the work directly, with the option to subcontract up to 50% of the work. A mandatory pre-bid conference is required for contractors to evaluate site access and conditions.
The electrical plan specifies technical requirements for the scoreboard installation, including using a NEMA 3R outdoor disconnect sized appropriately for the electrical load, installing new conduit, a ground rod, and a Christy box, and repairing exposed cable at the scoreboard base. Electrical specifications mandate conductor and conduit sizing per California Electrical Code (CEC) standards, with considerations for load determination including wind load cases from ASCE 7-16 guidelines. The new scoreboard's electrical loads are equal to or less than existing boards, and current over-current protection, conduits, and conductors from the panel will be re-used where possible.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CARDOZA PARK
ELECTRICAL PLAN
Notes:
1. New scoreboards electrical loads are equal to or less than those of the existing boards being removed.
2. Over current protection, conduits and conductors from the panel to the new disconnects are existing to be re-used.
3. New disconnect shall be NEMA 3R (outdoor/rainproof) and shall be sized no smaller than the electrical load of the scoreboard.
4. Conductors shall be sized per CEC Table 310.16 and shall be listed for wet service.
5. Conduits shall be sized per CEC Chapter 9 Tables 4 & 5.
6. The load determination shall also consider Case B and Case C from ASCE 7-16 Figure 29.3-1. Case C required for the 20’-0” W x 8’-6” H scoreboard (BA2014).
Cardoza Scoreboard Install new BA2014 scoreboard. Install new electrical disconnect, install new conduit and liquid tight from disconnect to score board, install (1) new ground rod, install one new Christy box. (Christy box installation will require approx. 5’ long trench from the Christy box to the score board support). Repair exposed cable at the base of the scoreboard.
Cardoza Field electrical panel located behind softball field Dak Score/MX-1 interface box to be installed in existing equipment cage and connect to existing power.