About this file
The document is an Electrical Plan for the Milpitas Sports Center Scoreboard Replacement Project in California, involving the City of Milpitas' procurement of electrical installation services for new scoreboards. The project scope includes the removal of existing scoreboards and installation of 7 new scoreboards across 3 city locations, with the city providing the scoreboards and building permits. The contractor is required to handle demolition, electrical connections, and installation, including setting up new electrical disconnects, conduits, and ground rods. The contractor must perform at least 50% of the work directly and may subcontract up to 50% of the project work.
The electrical plan specifies technical requirements for scoreboard installation, including using NEMA 3R disconnects, sizing conductors per CEC Table 310.16, and considering load determination per ASCE 7-16 standards. The project involves installing scoreboards at different locations, including a senior scoreboard, a Dak Score/MX-1 interface box, and major and minor scoreboards on the west and east sides. The Sports Center field electrical panel is located between the football field and snack shack. The electrical installation must adhere to specific technical specifications for conduits, conductors, and electrical load management.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MILPITAS SPORTS CENTER
ELECTRICAL PLAN
Notes:
1. New scoreboards electrical loads are equal to or less than those of the existing boards being removed.
2. Over current protection, conduits and conductors from the panel to the new disconnects are existing to be re-used.
3. New disconnect shall be NEMA 3R (outdoor/rainproof) and shall be sized no smaller than the electrical load of the scoreboard.
4. Conductors shall be sized per CEC Table 310.16 and shall be listed for wet service.
5. Conduits shall be sized per CEC Chapter 9 Tables 4 & 5.
6. The load determination shall also consider Case B and Case C from ASCE 7-16 Figure 29.3-1. Case B required for all scoreboards, and Case C required for the 20’-0” W x 8’-6” H scoreboard (BA2014).
Senior Scoreboard Install new (BA2014) scoreboard, install new electrical disconnect, install new conduit and liquid tight from disconnect to score board. Install (1) new ground rod.
Dak Score/MX-1 interface box to be installed in existing equipment cage and connect to existing power.
Dak Score/MX-1 interface box to be installed in existing equipment cage and connect to existing power.
One Major (west side) and One Minor (east side) Scoreboards (total of two) Install new (BA624) scoreboards. Install new electrical disconnects, install new conduits and liquid tight from disconnects to score boards. Install (1) new ground rod.
Sports Center Field electrical panel located between football field and snack shack.