This document appears to be an Exhibit 5 Vacant Quarters Maintenance Monthly Report related to a federal contract opportunity for Total Preventive Maintenance, Repair, and Cleaning Services for Army Family Housing (AFH) at USAG Humphreys (South Korea).

The report requires the contractor to provide monthly and cumulative totals for various maintenance and repair items, including complete interior painting of dwelling units (DUs) of different sizes, cleaning of DUs, and ordered work such as partial room painting, floor repairs, and fire damage restoration. The report must be submitted to the Contracting Officer's Representative (COR) by the third workday after the completed month.

The related federal contract opportunity is Solicitation Number W91QVN24R0008, issued by the Department of the Army Materiel Command Army Contracting Command, for Total Preventive Maintenance, Repair, and Cleaning Services for Army Family Housing (AFH) at USAG Humphreys (South Korea).

View the file

Other files

File Type Posted
Amd 03 W91QVN-24-R-0008.pdf PDF
Amd 02 W91QVN-24-R-0008.pdf PDF
Minor Repair Information.xls XLS spreadsheet
Amd 01 W91QVN-24-R-0008.pdf PDF
Major Repair price information.xlsx XLSX spreadsheet
Exhibit 7 Change of Occupany Cleaning Check List.xlsx XLSX spreadsheet
Exhibit 16 Heavy Equipment Check Lists.docx DOCX document
Exhibit 18 Sample NCIR.docx DOCX document
Exhibit 29 AFH Area Site for bldgs 510 511 and 512.pptx PPTX presentation
Exhibit 25 Red Cloud Circle Map( O6 Housing).pptx PPTX presentation
Exhibit 27 Macarthur Circle Map(GFOQ) (1).pptx PPTX presentation
Exhibit 24 Parking Lot floor Plan 5101 5102 5103 5171 5172 5173 Area.pdf PDF
Exhibit 30 AFH Room Information.xlsx XLSX spreadsheet
Exhibit 13 Customer Complaint.docx DOCX document
Exhibit 15 COM Monthly Report.xlsx XLSX spreadsheet
Exhibit 19 AFH bldg 513 Garage plan.pdf PDF
Exhibit 1 PRS v1.docx DOCX document
Exhibit 2 Deliverables(Data Requirements) v2.docx DOCX document
Exhibit 17 Contract Discepancy Report CDR.docx DOCX document
Exhibit 14 GFOQ Monthly Report.docx DOCX document
Exhibit 11 Estimated Service Frequency.docx DOCX document
Exhibit 23 Building 5101 5102 5103 5171 5172 5173 Flr Plans.pdf PDF
Exhibit 6 Quality and Standards of Work.docx DOCX document
Exhibit 26 Duplex floor plan in Red Cloud Circle(O6 housing).pdf PDF
Exhibit 20 AFH bldg 510 Floor Plans 2 bedrooms.pptx PPTX presentation
Exhibit 10 Historical Vacate Quarters data_.docx DOCX document
Exhibit 3 Scheduled Services 1.docx DOCX document
Exhibit 12 Daily Contract Inspection Report.docx DOCX document
Exhibit 9 Change of Occupany Maintenance Checklist.docx DOCX document
W91QVN-24-R-0008 (2 May 24).pdf PDF
Exhibit 20 AFH bldg 510 Floor Plans.pptx PPTX presentation
Exhibit 8 Change of Occupany Painting Check List.docx DOCX document
Exhibit 4 Monthly Service Order Report.docx DOCX document
Exhibit 21 AFH Area Site for bldgs 511 and 512.pptx PPTX presentation
Exhibit 28 GFOQ Duplex Floor Plan Single floor Type and duplex.pdf PDF
Exhibit 22 Plans for Area Site 5101 5102 5103 5171 5172 5173.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXHIBIT 5

VACANT QUARTERS MAINTENANCE MONTHLY REPORT

ActualActual
WorkMonthlyCumulative
ItemDescriptionUnitsQuantityQuantity

COM Maintenance and repair QTRS

COPComplete interiorQTRS
painting

(a) DU less than 1,500 NSF 139.4 NSM

(b) DU 1,500 to 3,000 NSF 139.4 to 278.7 NSM

(c) DU greater than 3,000 NSF 278.7 NSM

COC Clean quarters QTRS

(a) DU with less than 1,500 NSF/139.4 NSM

(b) DU 1,500 and 3,000 NSF/139.4 to 278.7 NSM
(c) DU greater than 3,000 NSF/ 278.7 NSM

ORDERED WORK

PaintingPartial interiorROOMS
painting
Tile FloorRemove & Install vinylSY/SM
tile
WoodenRepair Replace Wooden floorsSY/SM
Floor

Ceramic Tile Remove and Install Ceramic Tile SY/SM

Fire DamageRepair smoke and fireQTRS
damaged quarters

* The contractor shall fill in monthly and cumulative totals.

Submit to the COR, HFB by the third workday after the completed month