EXHIBIT_24_Sample Subcontract.pdf

PDF 209 KB Posted

Attached to
PIP-II F-37 BUILDING LWC PUMP ROOM PIPING SYSTEM INSTALLATION
Solicitation number
378854_MR
Issued by

About this file

This is a firm fixed-price subcontract for construction work associated with the PIP-II CPB HX and Pump project at Fermi National Accelerator Laboratory in Batavia, Illinois. The subcontract is issued by Fermi Forward Discovery Group, LLC (FFDG) under Prime Contract No. 89243024CSC000002 between the U.S. Department of Energy and FFDG for management and operation of the Fermi National Accelerator Laboratory. The subcontractor must furnish all labor, materials, transportation, overhead, insurance, bonding costs, safety oversight, quality control oversight, supervision, and equipment necessary to complete the work as described in the Project Manual, PIP-II CPB HX and Pump Project No. 4-3-3G and Drawing Set dated October 6, 2025. The work must be completed within 180 calendar days from receipt of the Notice-to-Proceed. The firm fixed price for base work is to be determined (TBD), with the FFP and total change orders representing the limit of FFDG's liability for all costs.

Monthly progress payments are made according to an FFDG-approved project schedule with required milestones and valuations, with 10 percent retained until final completion unless FFDG authorizes a lesser retention percentage. All invoices must be submitted to FFDG Accounts Payable at apinvoices@fnal.gov and are payable within 15 days of receipt; final invoices must be submitted within 60 days of work completion. FFDG may withhold payments for defective work, third-party claims, failure to pay subcontractors, damage to property, persistent non-performance, failure to provide reports, or filed claims or encumbrances. The FFDG Procurement Representative (Michele Reynolds, micheler@fnal.gov) is the sole authority to modify subcontract terms, while Steve Dixon serves as the FFDG Technical Representative for monitoring performance and clarifying technical requirements. The subcontractor must submit monthly progress reports and assist with administrative closeout upon completion. Incorporated documents include the Project Manual, FFDG General Terms and Conditions for Construction, insurance requirements, performance and payment bonds, Standard Form 1413, Subcontractor Annual Representations & Certifications, and Davis Bacon Wage Rates for Illinois.

View the file

Other files

Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Signature Page Subcontract No. TBD– PIP-II CPB HX and Pump

SUBCONTRACT NO. TBD

Fermi Forward Discovery Group LLC Kirk Road & Wilson Street P.O. Box 500 – Mail Station 210 Batavia, IL 60510-0500

Subcontractor:

TBD

FFDG Procurement Representative:

Name: Michele Reynolds Title: Procurement Manager Phone: (630) 840-2448 E-Mail: micheler@fnal.gov

Introduction

This is a firm fixed price subcontract (hereinafter “Subcontract”) for the construction work associated with the construction of PIP-II CPB HX and Pump, as further described herein.

This Subcontract is between Fermi Forward Discovery Group, LLC and the party identified above as the “Subcontractor.”

This Subcontract is issued under Prime Contract No. 89243024CSC000002 between the United States Government (hereinafter “Government”), represented by the Department of Energy (hereinafter called “DOE”) and Fermi Forward Discovery Group, LLC (hereinafter “FFDG”) for the management and operation of the Fermi National Accelerator Laboratory.

Agreement

The parties agree to perform their respective obligations in accordance with the terms, conditions, and provisions of the attached SCHEDULE OF ARTICLES and the documents referenced or incorporated therein, which together with this Signature Page shall collectively constitute the entire Agreement and shall supersede all prior negotiations, representations, or agreements, whether verbal or written.

TBD

FERMI FORWARD DISCOVERY GROUP, LLC

By:

By:

Name:

Name:

Title:

Title:

Date:

Date:

Schedule of Articles

SCHEDULE OF ARTICLES

ARTICLE 1 – SCOPE OF WORK

A. Description. The Subcontractor shall furnish all labor, materials, transportation, overhead, insurance, bonding costs, safety oversight, quality control oversight, supervision and equipment necessary to perform the work described in the Project Manual, PIP-II CPB HX and Pump Project No. 4-3-3G and Drawing Set, dated October 6, 2025, and other requirements as detailed in the specifications and drawings.

B. Location. The principal location for the work to be performed by the Subcontractor shall be the Fermi National Accelerator Laboratory, located in Batavia, Illinois.

C. Acceptance. Acceptance of the work under this Subcontract shall be based on the Subcontractor’s performance and completion of the work in consonance with high professional standards and compliance with the delivery and reporting requirements specified herein.

ARTICLE 2 – PERIOD OF PERFORMANCE

The work shall be completed within 180 calendar days upon receipt of the Notice-to-Proceed.

ARTICLE 3 – PRICE AND LIMITATIONS

The Firm Fixed-Price (FFP) and compensation for the performance of the base work shall be TBD.

The Firm-Fixed Price and the total amount of change order(s) shall be the limit of FFDG’s liability for all costs under this Subcontract, any other provision of this Subcontract notwithstanding.

ARTICLE 4 – INVOICES AND PAYMENT

A. Invoices

1. Monthly progress payments shall only be made in accordance with the submitted and FFDG approved project schedule, with the required milestones and valuations for each cited task. The FFDG Construction Coordinator and the Subcontractor shall review the progress of the Subcontract work monthly to determine the amount of compensation due the Subcontractor on that month’s invoice. The compensation due the Subcontractor on that month’s progress payment invoice shall then be determined in accordance with the Subcontractor’s cost loaded schedule.

2. In making such progress payments, there shall be retained 10 percent of the estimated amount until final completion and acceptance of the Subcontract work. However, if FFDG finds that satisfactory progress is being achieved, it may authorize the making of payments in which a lesser percentage is retained. When the work is substantially complete, FFDG shall retain an amount it considers adequate for the protection of the Government and may release to the Subcontractor all or any portion of any excess amount. Also, on completion and acceptance of each separate building, public work, or other division of the Subcontract, on which the price is stated separately in the Subcontract, payment may be made therefore without retention of a percentage.

3. The Subcontractor's monthly progress payment invoice(s) shall clearly state as a minimum all the following information:

Subcontractor Name - As stated in the subcontract:

Remittance Address:

Name of person requesting payment:

Telephone Number and/or email address of person requesting payment:

Subcontractor’s statement that the invoice is correct:

Project Name:

Project Number:

Subcontract Number:

Date of Project Update for this Invoice:

Update Number (as may be applicable):

Total Contract Value: $XXXX.XX Total Dollar Value Earned to Date: $XXXX.XX Less Previous Payments: $XXXX.XX Less Previous Retention: $XXXX.XX Gross Amount Earned This Update Period: $XXXX.XX

4. All invoices shall be emailed directly to the Fermi National Accelerator Laboratory (FNAL)

Accounts Payable Office at apinvoices@fnal.gov. The “subject” line of the email shall state the Subcontractor’s name and the Subcontract number.

If the Subcontractor is unable to submit an invoice by email, it may submit the invoice to the following address:

Fermi National Accelerator Laboratory Accounts Payable P.O. Box 500 Batavia, IL 60510 Apinvoices@fnal.gov

5. A “Final Invoice” shall be submitted within sixty (60) days of completion of the work or expiration or termination of this Subcontract.

6. All invoices shall state the Subcontract number; clearly identify the Subcontractor (including business heading or logo); include an invoice date, unique invoice number, and remittance address;

and sufficiently identify and support the payment requested. Invoice(s) in a spreadsheet format are not acceptable, but a spreadsheet can be used to support an invoice. The Subcontractor shall maintain records which support all invoiced amounts and provide them to FFDG Procurement Representative upon request.

B. Payment

All invoices except the final invoice shall be payable within fifteen (15) days of receipt; provided, however, that payments made thereafter shall not be subject to any penalty, interest, or late charges. Only those items/services identified in this Subcontract or a Subcontract Modification will be considered for payment.

Payments Withheld. FFDG may decline to make a progress payment, in whole or in part, to the extent reasonably necessary to protect FFDG, if in FFDG's opinion, the Subcontractor's application for payment is inaccurate in any material respect. If FFDG and the Subcontractor cannot agree on a revised amount, FFDG will promptly issue payment for such portion of the application for payment, if any, that it believes is correct or accurate. FFDG may also nullify the whole or any part of any progress payment previously issued, to such extent as may be necessary to protect FFDG from loss because of:

1. Defective Work not remedied;

mailto:Apinvoices@fnal.gov

2. Third-party claims filed or reasonable evidence indicating probable filing of such claims;

3. Failure of the Subcontractor to make payments properly to Subcontractors or for labor, materials, or equipment in accordance with prior approved Certificates of Payment;

4. Damage to the property of the U.S. Government, FFDG, another contractor, or anyone else;

5. Persistent failure to carry out the Work in accordance with the Contract Documents;

6. Failure of the Contractor to provide updated monthly reports or progress schedules; or

7. The filing of a notice of claim or encumbrance or attachment or a reasonable basis to believe that a claim or encumbrance may be filed, except if the purported claim or attachment is the result of FFDG's nonpayment of an amount contained in a previously submitted Application for Payment as to which no good-faith dispute exists between FFDG and Subcontractor.

When the above grounds in Subparagraph 1 through 7 stated above are removed, payment shall be made for amounts withheld because of them. Notwithstanding the above provisions of this Paragraph, FFDG may also withhold a reasonable portion of any payment for any of the above-stated reasons or any other reason relating to the Subcontractor’s non-performance. FFDG shall inform the Contractor in writing of such reason for withholding. Questions regarding invoices should be directed to the FFDG Procurement Representative.

ARTICLE 5 – SUBCONTRACT ADMINISTRATION

A. Notices, Requests, and Modifications. The Subcontractor shall submit all notices and requests for approval by email to FFDG Procurement Representative indicated at the following mail address:

Michele Reynolds Fermi Forward Discovery Group LLC P.O. Box 500 – Mail Station 210 Batavia, IL 60510-0500 micheler@fnal.gov

Only the FFDG Procurement Representative is authorized to modify the terms, conditions, and requirements of this Subcontract, including any changes to the description of the work, and to issue any notices and approvals required by this Subcontract.

B. Steve Dixon is the FFDG Technical Representative for this Subcontract. This individual is designated to monitor performance of the work and to interpret and clarify the technical requirements, but is not authorized to make changes to the work or to modify any of the terms and conditions of this Subcontract, including those related to the completion schedule or pricing.

C. Closeout. The Subcontractor shall, as a condition of full payment, assist FFDG after the completion of the work in accomplishing the administrative closeout of this Subcontract, including, as necessary or required, the furnishing of documentation and reports, the disposition of property, the disclosure of any inventions, the execution of any required assignment or release documents, the performance of any audits, and the settlement of any interim or disallowed costs.

ARTICLE 6 – REPORTS OR DELIVERABLES

Types of Reports

A. The Subcontractor shall prepare and submit the following reports to FFDG:

Monthly Progress Reports – An initial progress report, and revisions based on Subcontract changes affecting cost or schedule, shall establish and maintain a time-phased baseline against which performance mailto:micheler@fnal.gov can be measured. Monthly progress reports shall be submitted by the subcontractor on a monthly basis, as outlined in Exhibit C, Section 3.2, part D, and may be informal letter summaries in a format approved by the FFDG Technical Representative. These reports should contain a description of work performed during the month reported and work planned for the next month.

B. Submittal. Reports shall be separately submitted to the following recipients at the following email addresses:

Recipient Email

FFDG Technical Representative (Steve Dixon) steveo@fnal.gov FFDG Procurement Representative (Michele Reynolds) micheler@fnal.gov

ARTICLE 7 – RESERVED

ARTICLE 8 - INCORPORATED DOCUMENTS AND ORDER OF PRECEDENCE

The following documents are hereby incorporated as a part of this Subcontract and the Order of Precedence shall be as listed below.

Subcontract/Schedule of Articles

Exhibit A Project Manual, PIP-II CPB HX and Pump Project No. 4-3-3G and Drawing Set, dated October 6, 2025

Exhibit B Fermi Forward Discovery Group, LLC General Terms and Conditions for Construction, (08/2025)

Exhibit C Insurance Requirements for Construction Subcontracts (01/2025) Exhibit D Performance Bond, FL-40 (Rev. 1/7/2025) Exhibit E Payment Bond, FL-42 (Rev. 1/07/2025) Exhibit F Standard Form 1413 (Rev. 10/2023) Exhibit G Subcontractor Annual Representations & Certifications (SARC), Form SARC

(Rev. 5) Exhibit H Davis Bacon Wage Rates, General Decision, IL20250008, Building and

Residential, IL20250008, Modification No.13 dated 09/26/2025

ARTICLE 9 – GENERAL PROVISIONS

The FAR and DEAR clauses listed in the Clauses Incorporated by Reference [Clause 17 of FFDG General Terms and Conditions for Construction Subcontracts (08/2025)] shall be applicable to this Subcontract based on the value of the Subcontract, the status of the Subcontractor, and the nature and location of the work.

(END OF SCHEDULE OF ARTICLES)

Agreement