573-2_Overhaul_Repair_of_Hydraulic_Cylinders.pdf

PDF 20 KB Posted

Attached to
NOAA Ship RONALD H. BROWN DOCKSIDE REPAIRS
Solicitation number
EA-133M-17-RP-0081
Issued by

About this file

573-2 Overhaul_Repair of Hydraulic Cylinders

View the file

Other files

File Type Posted
Pricing_Sheet__MSWord_RFP_EA-133M-17-RP-0081.R2.docx DOCX document
RB-085-001_Booklet_of_General_Plans.pdf PDF
Pricing_Sheet__MSWord_RFP_EA-133M-17-RP-0081.R1.docx DOCX document
WI_12330_Engine_Overhaul_Rev._2.pdf PDF
RFP_EA-133M-17-RP-0081,_REV-2.pdf PDF
J.1_SPECIFICATION_NOAA_SHIP_RONALD_H._BROWN_REV_2.pdf PDF
Amendment_0002_RFP_EA-133M-17-RP-0081.pdf PDF
RB-514-001.pdf PDF
WI_16240__Doors_Rev._2.pdf PDF
665-6932883.pdf PDF
WI_25140__AC_PLant_Renewals_Rev._2.pdf PDF
WI_13200__Switchboard_Cleaning_Rev._2.pdf PDF
WI_64390__CCTV_Monitoring_System_Installation_Rev._2.pdf PDF
529-6932931.pdf PDF
RFP_EA-133M-17-RP-0081,_REV-1.pdf PDF
14_in._exhaust_silencer.pdf PDF
514_6932961.pdf PDF
Switchboard_Breakers_Info.pdf PDF
J._4_Past_Performance_Information_Form_Rev.1.pdf PDF
000-1G_General_Requirements_for_Ship_Repair_Contract_Work_on_NOAA_Ships.pdf PDF
Amendment_0001_RFP_EA-133M-17-RP-0081.pdf PDF
10_in._exhaust_silencer.pdf PDF
J.5__Past_Performance_Questionnaire_Rev.1.pdf PDF
RB-085-001.pdf PDF
US_Standard_Bus_Connection_Bolt_Torque_Values.pdf PDF
Pricing_Sheet__MSWord_RFP_EA-133M-17-RP-0081.docx DOCX document
WI_22520_Woodward_Controls_Upgrade_spec.pdf PDF
439-001.pdf PDF
Motor_Inventory_Information.pdf PDF
RHB_Firehose_Inventory.pdf PDF
Tech_Manaul_167-00_Part_1.pdf PDF
551-04.pdf PDF
Tech_Manaul_167-00_Part_2.pdf PDF
RB_555-02_REV_C.pdf PDF
J.1_SPECIFICATION_NOAA_SHIP_RONALD_BROWN_REV_1.pdf PDF
Tech_Man_RB-437-00r.pdf PDF
634-1B_DECK_COVERINGS.pdf PDF
Righting_Device_Inspection_Form,_Blank.pdf PDF
300-1_Overhaul_of_Electrical_Rotating_Machinery.pdf PDF
528-6932928.pdf PDF
512-6932959.pdf PDF
NOAA_RHB_480VAC_SWBD_29JAN2011_RED.pdf PDF
J.3__Subcontracting_Plan.pdf PDF
631-2D_Coating_Systems_for_Steel_Surfaces.pdf PDF
555-6932945.pdf PDF
638-6932868.pdf PDF
623-6932856.pdf PDF
514-6932921.pdf PDF
256-6932914.pdf PDF
RH_Brown_Gauge-Thermometer_List.xls XLS spreadsheet
Show 40 more

Latest 50 of 81 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MOC-573-2

September 2000

National Oceanic and Atmospheric Administration Marine Operation Center

Standard Specification MOC-573-2

OVERHAUL/REPAIR OF HYDRAULIC CYLINDERS

1. SCOPE: This specification provides the minimum requirements for the overhaul and/or repair of hydraulic cylinders.

2. REFERENCES

None

3. REQUIREMENTS

3.1 Tag out system controllers and actuators to preclude

inadvertent operation and secure the movable member to prevent movement while cylinder is removed.

3.1.1 Disconnect and cap hydraulic lines from the cylinder.

Ensure containment is provided to prevent spillage of oil.

Hydraulic lines and inlet/outlet ports shall be capped or plugged with threaded fittings to prevent leakage or contamination of the system.

3.1.2 Remove the cylinder from the ship and transport to

repair facility.

3.2 Perform the following work on the removed cylinder:

3.2.1 Completely disassemble the cylinder and clean all

parts.

3.2.2 Prepare and preserve the external painted surfaces in

accordance with the identified painting specification or as original.

3.2.3 Reassemble the cylinder under clean conditions using

new "O" rings, seals, gaskets, packing, and piston rings.

Materials used shall meet or exceed original manufacturers specifications. During reassembly lubricate the above with a product equal to Hilton's Hyper-Lube, that is compatible with the system fluid.

3.2.4 Provide and install new nuts, washers, bolts, studs and inlet and outlet fittings.

3.3 Reinstall the cylinder in its original location.

MOC-573-2

September 2000

3.4 Top off hydraulic reservoir to full mark and purge all air from the system taking care to contain any fluid bled off.

3.5 Remove tag outs.

4. QUALITY ASSURANCE

4.1 After disassembly, inspect all components for trueness of bore and rod, wear, damage, corrosion or pitting. Provide a Condition Report detailing the inspection results, contractor's corrective action recommendations, and list of additional parts, material and labor not covered by this specification, required to restore the cylinder to the manufacturers specifications.

4.2 After reassembly, bench test the assembly at system working pressure to prove smoothness of operation and tightness of sealing surfaces.

4.3 Cycle the cylinder through a minimum of four evolutions to demonstrate operation and tightness of all disturbed fittings and connections. Upon satisfactory demonstration of operation and tightness apply "Denso tape" to all connections.

END OF SPECIFICATION