J.1 SPECIFICATION_NOAA SHIP RONALD H. BROWN_REV 2

View the file

Other files for this federal contract opportunity

Other files attached to NOAA Ship RONALD H. BROWN DOCKSIDE REPAIRS, newest first.
File Type Posted
RFP_EA-133M-17-RP-0081,_REV-2.pdf PDF
Pricing_Sheet__MSWord_RFP_EA-133M-17-RP-0081.R1.docx DOCX document
WI_16240__Doors_Rev._2.pdf PDF
665-6932883.pdf PDF
WI_25140__AC_PLant_Renewals_Rev._2.pdf PDF
WI_13200__Switchboard_Cleaning_Rev._2.pdf PDF
WI_12330_Engine_Overhaul_Rev._2.pdf PDF
RB-085-001_Booklet_of_General_Plans.pdf PDF
RFP_EA-133M-17-RP-0081,_REV-1.pdf PDF
RB-085-001.pdf PDF
439-001.pdf PDF
J.1_SPECIFICATION_NOAA_SHIP_RONALD_BROWN_REV_1.pdf PDF
Switchboard_Breakers_Info.pdf PDF
US_Standard_Bus_Connection_Bolt_Torque_Values.pdf PDF
WI_22520_Woodward_Controls_Upgrade_spec.pdf PDF
Motor_Inventory_Information.pdf PDF
RHB_Firehose_Inventory.pdf PDF
Tech_Manaul_167-00_Part_1.pdf PDF
Tech_Manaul_167-00_Part_2.pdf PDF
551-04.pdf PDF
RB_555-02_REV_C.pdf PDF
514_6932961.pdf PDF
14_in._exhaust_silencer.pdf PDF
Tech_Man_RB-437-00r.pdf PDF
J.3__Subcontracting_Plan.pdf PDF
201-6932912.pdf PDF
J.5__Past_Performance_Questionnaire.pdf PDF
RB-085-001.pdf PDF
514-6932961.pdf PDF
RB_555-02_REV_C_Model.pdf PDF
528-6932928.pdf PDF
512-6932959.pdf PDF
300-1_Overhaul_of_Electrical_Rotating_Machinery.pdf PDF
514-6932921.pdf PDF
623-6932856.pdf PDF
514-6932962,_Diagram.pdf PDF
512-6932955_HVAC_Mn_Dk_r.pdf PDF
171-6932832.pdf PDF
259-6932917.pdf PDF
573-2_Overhaul_Repair_of_Hydraulic_Cylinders.pdf PDF
J.2__USDL_Poster.pdf PDF
512-6932954_HVAC_02_Lvl_and_up.pdf PDF
J.4_Past_Performance_Information_Form.pdf PDF
J.1__SPECIFICATION_NOAA_SHIP_RONALD_BROWN_DOCKSIDE_REPAIR.pdf PDF
512-6932958_HVAC_ER.pdf PDF
634-1B_DECK_COVERINGS.pdf PDF
506-6932919_REV_C.pdf PDF
Brown_Life_Raft_Certificates_2016.pdf PDF
NOAA_CAT_3500__Standard_Spec.pdf PDF
300-6932739_Bonding_Grounding.pdf PDF
Show all 50

NOAA Ship RONALD H. BROWN DOCKSIDE REPAIRS has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NOAA SHIP RONALD H. BROWN

(R-104)

Work Item Index

Item # Title

BASIC WORK ITEMS (ORF)

10420 GENERAL REQUIREMENTS BASIC

19920 TEMPORARY SERVICES BASIC

11000 MISC STEEL REPAIRS BASIC

12330 ENGINE OVERHAUL BASIC

12560 MISC. VALVES AND PIPING BASIC

13200 SWITCHBOARD MAINTENANCE BASIC

14370 TANK LEVEL INDICATORS REPAIRS BASIC

15040 GAUGE CALIBRATION BASIC

15120 VENTILATION REPAIRS BASIC

15160 REEFER BOX REPAIRS BASIC

15550 FIRE FIGHTING SYSTEMS CERTIFICATION BASIC

15830 LIFE RAFT INSPECTIONS BASIC

16230 EXTERIOR LADDERS MAINTENANCE BASIC

16240 DOOR REPAIRS AND RENEWALS BASIC

16310 MAIN MAST PRESERVATION BASIC

16340 WEATHER DECKS PRESERVATION BASIC

16341 INTERIOR DECKS PRESERVATION BASIC

BASIC WORK ITEMS (PAC)

22520 WOODWARD CONTROLS UPGRADE BASIC

25140 AIR CONDITIONING PLANT RENEWALS BASIC

25920 SCBA/DIVE COMPRESSOR MODIFICATION BASIC

ADDITIONAL WORK (ORF)

3000 ADDITIONAL WORK

ADDITIONAL WORK (PAC)

4000 ADDITIONAL WORK

OPTIONAL ITEMS (ORF)

52330 EXHAUST STACK CLEANING OPTIONAL

55920 VENTILATION SYSTEMS CLEANING OPTIONAL

OPTIONAL ITEMS (PAC)

64390 CCTV MONTITORING SYSTEM INSTALLATION OPTIONAL

INDEX – FY17 DS

REV. 2

14 July 2017

MED/JAL ITEM NO. 10420 BASIC ITEM

INTENT, SCOPE, GENERAL REQUIREMENTS

10420-1

Scope and Intent of the Drydock or Dockside Ship Repair Contract

The National Oceanic and Atmospheric Administration (NOAA) operates a fleet of research vessels that supports research and mapping for the National Fisheries Service, National Ocean Service, Office of Atmospheric Research and the National Weather Service, as well as provides support to other Federal agencies. These research missions are time sensitive and therefore the data must be collected at specific times during the sailing season to be meaningful. At the end of each sailing season the vessels enter a repair period (drydock or dockside) to address repairs that have been previously identified, perform upgrades to mission systems or ship systems that either extend the life of the ship or provide new data collection capabilities or for safer operations of ships systems as well as address any emergent work that would adversely affect the ships ability to safely perform its mission on schedule, while meeting all regulatory body requirements (American Bureau of Shipping and United States Coast Guard) and all habitability requirements, including any that may be required as a result of contracts for personnel to augment ship staff.

The work items in the repair specification are identified well in advance of the performance period in order meet the contracting lead times. Additional work items (emergent work) may arise during the period between the work package submittal, contract award, or even prior to the start of or during the contract performance period. In accordance with Commerce Acquisition Regulation (CAR) clause 1352.271-72, the Contracting Officer may order additional changes during the contract period of performance to address any additional work items identified as necessary to ensure the intent of the drydock or dockside repair contract is met;

that is, that the vessel shall be able to safely perform its mission, that it will meet all habitability requirements and regulatory body requirements, and that such repairs will be timely performed to ensure to the maximum extent practicable that the ship's schedule is not adversely impacted.

1.0 ABSTRACT

This Item describes the intent, scope, and general requirements that apply to this Work Package.

2.1 REFERENCES

2.2 NOAA Standard Specification AMC-000-1F, "General Requirements for

Ship Repair Work on NOAA Ships"

2.3 NOAA Standard Specification AMC-631-2D, “Coating Systems for Steel Surfaces”

2.4 NOAA Standard Specification MOC-300-3, “General Requirements for

Electrical/ Electronic Items”

2.5 AGOR Drawing No. RB-085-001, Rev A, “Booklet of General Plans”

2.6 AGOR Drawing No. RB-631-6932857, Rev A, “Paint Schedule”

2.7 AGOR Drawing No. RB-501-6932918, Rev B, “Piping Standard Details”

2.8 IEEE STD 45-1983, Recommended practice for electronic installations

14 July 2017

MED/JAL ITEM NO. 10420 BASIC ITEM

10420-2

On shipboard.

2.9 American Bureau of Shipping, Rules for building and classing steel vessels.

2.10 Code of Federal Regulations, Title 46, Subchapter J, Electrical

Engineering

3.1 REQUIREMENTS

3.2 References listed in 2.0 form a part of these Detail

Specifications. All provisions and requirements contained therein are applicable to all work items, including all additional work items which are authorized by the Contracting Officer.

3.3 Provide and maintain a Quality Assurance (QA) TEST AND INSPECTION

PLAN applicable to all work items, including all additional work items which are authorized by the Contracting Officer and update it weekly for each weekly progress meeting. The form shall include the following minimum information for each work item and additional work item:

1) Specification item and paragraph number

2) Component/Equipment name

3) Test or Inspection description

4) Acceptance Criteria

5) QA Inspection Report

3.4 The design and execution of work items within the work package are the Contractor’s responsibility. Work items and Contract Guidance Drawings

14 July 2017

MED/JAL ITEM NO. 10420 BASIC ITEM

10420-3 provided as part of the work package do not fully describe all work required to meet regulatory requirements. However, all work performed by the Contractor and Subcontractor, regardless of tier, shall comply with regulatory requirements, and the cost shall be borne by the Contractor/Subcontractor.

Only the costs of ABS ship surveys/inspections will be borne by the Government. However, the scheduling of ABS surveys/inspections remains the Contractor’s responsibility.

3.5 Weigh each item removed from and installed on the ship. Provide a summary report to the COTR indicating the total weight in pounds of items removed, the total weight in pounds of new items installed, and the locations of weight removals and installations, with reference to deck level, frame number, height above deck level, and distance from centerline.

3.6 Unless otherwise stated in the individual work items, prepare and coat all new steel, all existing steel surfaces identified to be cleaned and painted, and any paint system disturbed while accomplishing work items, in accordance with reference 2.2. Finish coat colors shall match those of the surrounding, unmodified area. In addition, all power tools used to prepare internal spaces for painting, such as staterooms, the bow thruster space, engine room, stern thruster rooms and Generator Rooms, shall be fitted with dust collecting equipment to keep air bourne contaminants to a minimum. This does not relieve the Contractor from using protective coverings on equipment in those spaces.

3.7 At no time will the ship be required to moor at any dock which has a water depth of less than that required to provide a minimum clearance of two

(2) foot under the lowest underwater hull projection during the entire period for which the ship is at the Contractor’s facility.

3.8 Ship’s force will maintain a minimal presence during

accomplishment of work to these specifications. Their availability to operate ship’s equipment will be limited. Unless otherwise specified, provide a minimum of one working day prior notice for any equipment operations.

3.9 Several items require the modification or installation of various piping systems. All piping systems, unless otherwise specified within these specifications shall be installed in accordance with references 2.6.

3.10 Several items require the installation of new cabling and electrical equipment. All new cabling and electrical equipment shall be installed in accordance with reference 2.3.

3.10 Drawings shall be updated only when specified in the individual work item. All CAD drawings shall be updated in AutoCad 2000. All paper drawings shall be redlined. The Redline and CAD updates shall include a complete list of new parts used, to the level of detail shown on existing parts lists on the referenced drawings. The Government shall provide either a full size copy of the drawing to be redlined or a copy of the CAD drawing. The updated drawings shall be returned to the COTR no later than 14 days after completion of the contract.

3.11 All new equipment and furnishings purchased by the Contractor for installation on the vessel shall be provided with factory supplied technical manuals, or data sheets, complete with parts listings. Faxed copies of this information is not acceptable. This documentation shall be turned over to the

14 July 2017

MED/JAL ITEM NO. 10420 BASIC ITEM

10420-4

COTR after installation is completed.

3.12 The Contractor shall schedule and participate in a one- day sea trial near the end of the work performance period to witness testing of all repaired or newly installed equipment and machinery. The sea-trial is expected to take 10 hours, departing from and returning to the contractor’s facility.

The COTR will coordinate the sea-trial date with the Contractor and other vendors, with at least 72 hours notice.

3.13 The contractor shall assume that the ship’s force will be living on board during the first seven days and last seven days of the availability.

During this period, no systems that would impact hotel services on board should be disrupted.

4.1 NOTES

4.2 NOAA Ship RONALD H. BROWN, ABSID Number 9727531, has ABS Class

Notations A1, E, AMS, and ACCU. The ship is currently in Active Status. The following descriptive data of NOAA Ship RONALD H. BROWN is provided for information:

Overall length - 274'- 0" Beam, Molded - 52'- 6" Draft, Design - 17'- 0" Draft, Navigational - 19'- 0" Depth to Main Deck - 26'- 6" Displacement (FL) - 3527 LT Displacement (LS) - 2252 LT Propulsion Z-Drives - 2 Speed Sustained - 12 Knots

4.3 NOAA will deliver NOAA Ship RONALD H. BROWN from Pier Papa, Old

Navy Base, North Charleston SC to the contractor’s facility. Delivery of the ship back to the Government shall be at the contractor’s facility.

4.4 NOAA Ship RONALD H. BROWN is an AGOR class Oceanographic Research

Vessel commissioned in 1997. REVELLE is the lead ship in the “AGOR 24" class.

Most of the drawings were based on the lead ship. There may be differences between the drawings and the ship. Take into account these differences during the bidding.

4.5 Technical Manuals are not supplied with these specifications, but are available for review upon scheduling at the NOAA Port Office Charleston, 1050 Register St, North Charleston, SC PH: 843-566-9191.

03 APRIL 2017

MED/JAL ITEM NO. 19920 BASIC ITEM

TEMPORARY SERVICES

19920-1

1.0 ABSTRACT

This Item describes the requirements for temporary services for the vessel for the duration of the contract.

2.2 NOAA Standard Specification AMC-000-2C, "Temporary Services at the

Contractor’s Facility”.

3.0 ITEM LOCATION/DESCRIPTION: See para. 7.0

4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES: None.

5.1 NOTES

5.2 The contractor and all subcontractors regardless of tier are advised to review other work items under this contract, including but not limited to 10420 to determine their effect on the work required under this work item. Many of the definitions relating to performance of this work item are found in references included in work item 10420.

5.3 The vessel’s drain lines from the staterooms and galley (grey water system) do not have a separate holding tank. All drain lines go to the sewage holding tank.

6.0 QUALITY ASSURANCE REQUIREMENTS: None additional.

7. STATEMENT OF WORK REQUIRED

7.1 Provide all facilities and services required in Reference 2.1, with the following additional requirements, details, and exceptions.

7.1.1 Electric Power: Electric Power requirements are 480 VAC, 3 PH, 60 HZ, 800 amps total service through two (2) 400 amp electrical shore power cables. Shore power cables shall be provided by the Contractor and must fit the ship’s receptacles. Ship’s receptacles are Joy Manufacturing Company part number X8999-39. Estimated average hotel load will be 350 kw.

7.1.2 Air: Provide 125 psi dry, filtered, compressed air at 100 cfm, connected to the ship’s service air line on the Main Deck. Air shall be available 24 hours/day during the entire yard period.

7.1.3 Cooling Water: There is not a Main Deck connection in the auxiliary salt wter system for a shore connection. Water can be provided by connecting a fire hose from the pier to a ball valve located in the aux. salt water system piping on the upper level of the Generator Room, stbd. side aft near the #1 AC Plant. This configuration will provide cooling for the air conditioning plant. Provide water a rate of 100 gpm at 60 psig.

7.1.4 Sanitary Water: the ship uses potable water for sanitary flushing.

7.1.5 Phone Lines: Four phone lines are required on board the ship for general ship’s use. Two lines shall be provided in the COTR Dockside Office Space for the COTR (1 voice, 1 fax/internet), and two lines for the Ship’s

19920-2

(R-104)

03 APRIL 2017

MED/JAL ITEM NO. 19920 BASIC ITEM

Dockside Office. Total of 8 lines.

7.1.6 Potable Water: Install a temporary fitting on the main deck connection to provide potable water a rate of 50 gpm at 50 psig.

7.1.7 Shore Sewage Line: The vessel’s sewage system is fitted with 3 inch, camlock, quich disconnect fitting for use as a shore sewage connection.

The fitting is located on the Main Deck port and starboard.

7.1.8 Parking Spaces: Fifteen (15) vehicle parking spaces are required.

7.1.9 Security Service shall be provided on board the ship from 1600H- 0800H weekdays, and 24 hours a day on weekends and Government holidays.

Government holidays are listed at http://www.opm.gov/fedhol.

7.1.10 The requirement to clean the engine room bilges shall be accomplished with a pressure washer near the end of the contract. To be coordinated with the COR.

7.1.12 Provide dockside office spaces as follows:

a) Offices and conference room shall be co-located, land based, air-conditioned, heated, and located near the ship and other shipyard shops and offices.

b) Provide a separate private conference room (250 sq ft) immediately adjacent to the COR office and equipped with minimum one eight person conference table with 10 chairs.

c) Provide one lockable office for the COR.

d) Provide a lockable office space for the ship’s crew equipped for eight people. The minimum acceptable size of the office area is 1800 sq ft. t Within the 1800 sq ft office, provide a separate private lockable space for use as a dedicated server room. The ship’s ET’s will move the ship’s servers from on board to this space for the duration of the contract. This server room at a minimum shall provide two each separate 20 amp 110v electrical circuits, and a full size server rack. This space is to be air conditioned to maintain 72 degrees F.

e) Provide high speed internet for all office spaces, 150 mbps download speed minimum.

7.1.13 Provide the services of a crane and crane operator to support the ship during the performance period. For estimating purposes, assume 24 hours total of crane service will be required, to be designated in 1 hour blocks. Only the COTR is authorized to request crane hours. The COTR will provide the Contractor with 24 hours notice for crane service. These hours are for ship force use only, and are separate from any Contractor related work.

7.1.14 Provide two each golf carts for the duration of the contract, one for the COR and one for ship’s crew.

19920-3

(R-104)

03 APRIL 2017

MED/JAL ITEM NO. 19920 BASIC ITEM

7.2 Remove and properly dispose of Waste Oil and Oily Waste from the Wast

Oil Tank (4-84-0) and Oily Waste Tank (4-87-0). Upon removal of waste, open tanks and pressure wash clean all tank internals.

Remove and properly dispose of all cleaning liquids and debris.

Port Engineer to inspect each tank upon completion of cleaning.

Close up tanks using new gaskets.

Capacity (gal.) Waste to be Disposed (gal)

Waste Oil Tank (4-84-0): 3,831 3,500 Oily Waste Tank (4-87-0): 4,976 4,570

8.0 GENERAL REQUIREMENTS: None Additional.

14 July 2017

MED/JAL ITEM NO. 11000 BASIC ITEM

MISC Steel Repairs

11000-1

1.1 ABSTRACT

1.2 This item describes misc. steel repairs throughout the vessel.

2.1 REFERENCES/ENCLOSURES:

2.2 Drawing RB-512 6932959,HVAC Arrg’t & Details 1st Plat Aft

2.3 Drawing RB-512-6932955, Hvac Arrg’t & Details Upper Main Deck

2.4 Drawing RB-512-6932954 Hvac Arrg’t & Details 02 Lvl and UP

2.5 NOAA Standard Item MOC 300-1, Overhaul of Electrical Rotating Equipment.

2.6 Drawing RB-101-6932819, Structural Module No. 19

2.7 Drawing RB-512-6932958, HVAC Arrangement and Details Generator Room

3.0 ITEM LOCATION/DESCRIPTION: Refer to 7.0.

4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICE: None.

advised to review other work items under this contract, including but not limited to 10420 to determine their effect on the work required under this work item. Many of the definitions relating

6.0 QUALITY ASSURANCE: NONE ADDITIONAL.

7.1 STATEMENT OF WORK REQUIRED:

7.2 Accomplish the following to repair and preserve the Winch Room ventilation plenums and ducting. Refer to References 2.1-2.4. The Winch Room Supply Fan S2-101-2 plenum extends from the 01 Level, through the main deck, into the Winch Room on the 1st platform deck. See Elevation 7A in Reference 2.1.

7.2.1 Temporarily remove Supply Fan S2-101-2 from ship to shop.

This fan is 460V, 3 Phase, 3 HP. Accomplish the requirements of Reference 2.4 for this fan and motor assembly. Repairs to include renewal of bearings, and machining of bearing end bells.

7.2.2 Blast and apply coating system the interior of the plenum from the top of the 01 Level down to the winch room. Also blast the interior of the vent trunk in the overhead of the

14 July 2017

MED/JAL ITEM NO. 11000 BASIC ITEM

11000-2 winch room. There is a manhole access to this plenum on the man deck inboard side. There is a manhole access to the winch room overhead vent truck on the bottom of the vent trunk. Blast to SSPC-SP-6, Commercial Blast.

7.2.2.1 Prior to blasting operations temporarily install

drop cloths, masking, division shields, seals, blanks and filtering materials to prevent abrasives and foreign substances from entering lights, machinery, piping, hatches, fork truck guards, deck drains, ventilation systems, tank vents, valve stems, motor shafts, seals and temporary openings during blasting and painting operations. All equipment in the Winch Room is to be shrink wrapped and sealed to prevent contamination.

7.2.2.2 The COR is to inspect all blasted areas with the

Paint Rep. prior to application of the first coat.

7.2.2.3 Apply one coat of International 300V at 4 mils DFT.

7.2.3 It is anticipated that blasting operations will expose some areas of the plenum and trunk that will require steel renewals. During the inspection in 7.1.2.2, areas that require steel renewal are to be taped off prior to application of the primer coat. Submit an as found condition report with any areas of steel that require renewal.

7.2.4 For estimating purposes, assume that the baffle located on the 01 Level in the plenum will require cropping and renewal. Refer to reference 2.1 and 2.5. Reference 2.5 Section 95-A and 90-A apply (Hull 252).

7.2.5 For estimating purposes, assume that six (6) each L7x4x3/8 stiffeners on the aft bulkhead of the plenum (FR 101) on the 01 Level will require renewal.

7.2.6 Upon completion of all steel work, and prior to further coating applications, the COR and Paint Rep are to inspect the plenum and trunk areas. Upon completion of this inspection, apply the following coating system to all surfaces:

7.2.6.1 Two (2) each coats of International 300V, with

stripe coats in between each coat, alternating between bronze and silver.

7.2.7 Renew ducting in the Winch Room. To include ducting between

Fan S2-101-2 and the plenum as well as ducting on the discharge of the fan to the main trunk. New ducting is to be stainless steel 16 gauge.

14 July 2017

MED/JAL ITEM NO. 11000 BASIC ITEM

11000-3

7.2.8 Renew the three (3) each vent grills on the winch room trunk with new 316 stainless steel frames and mesh, approximate size is 18”x16”. Install with new stainless steel hardware.

7.3 Accomplish the following to renew deteriorated steel in Generator Room Supply ventilation port plenum. Refer to Reference 2.6.

7.3.1 Prior to start of work, accomplish operational testing of the damper assemblies and submit an as found condition report.

7.3.2 Temporarily disconnect electrically and remove the existing stainless steel fire damper assemblies. Note that these assemblies can be temporarily rigged from the overhead for completion of the work in this item. This assembly consists of two assemblies tack welded together, grind welds to facilitate removal.

7.3.3 Renew the damper deck transition structure. See Reference

2.6 Section 21A. New transition piece is to be fabricated

from 3/8” plate.

7.3.4 Coat all new and disturbed steel with two each coats epoxy primer and one top coat to match existing.

7.3.5 Reinstall the damper assemblies with new stainless steel hardware. Connect electrically and accomplish operational testing in presence of COR.

7.4 Accomplish the following to inspect and preserve the Haz Mat Locker

(1-66-3) deck.

7.4.1 Temporarily remove the two (2) each hazmat lockers and one each bench unit from the Haz Mat Locker.

7.4.2 Crop and renew the foundations for the two each lockers and the bench unit.

7.4.3 Prepare the deck and six inches up all vertical surfaces to SSP-SP-11. Apply the following coating system, two each coats International 300V, 4 mils DFT each, one each top coat to match existing.

7.4.4 Reinstall all lockers and bench with new stainless steel hardware.

14 July 2017

MED/JAL ITEM NO. 11000 BASIC ITEM

11000-4

7.5 Accomplish the following to remove the VSAT dome from the top of the aft winch control room (02-94-1).

7.5.1 Disconnect and remove the aft VSAT dome from its foundation.

7.5.2 Pull back the VSAT dome signal and electrical cables from the top of the Winch Control Room to the overhead of the Winch Control Room. Coil each cable neatly and secure to the overhead. Renew the multicable transit blocks in way of the removed cable to restore water tight boundary. For estimating purposes, assume there are 10 each cables.

7.5.3 Remove the VSAT dome supporting structure. Grind deck smooth (top of Winch Control Room) in way of removals.

7.5.4 Accomplish the following to preserve the Winch Control Room top:

7.5.4.1 Prepare all surfaces to SSPC-SP-11. To include the

deck and the interior and exterior surfaces of the slanted plate attached to the top of the Winch Control Room. Also to include six inches up all masts or other appendages welded to the deck.

7.5.4.2 Apply the following coating system to all surfaces:

7.5.4.2.1 Two (2) each coats of Interational 300V or

equal, 4 mils DFT each.

7.5.4.2.2 Two top coats of International 990, or

equal, 4 mils DFT, color to match existing.

7.6 Accomplish the following repairs for the galley food service line hot table. The table is a THURMADUKE STEAM (ELECTRIC)TABLE Model:

E5DLSS. The unit is located in the ship’s galley.

7.6.1 Disassemble the steam table in order remove the steam table top which is a solid piece encompassing the five (5) each water wells.

7.6.2 Using the existing as a template, fabricate a new 316 SSTL table top identical to the existing.

7.6.3 Reassemble the steam table with the new top piece, utilizing new stainless steel fasteners.

7.7 Accomplish all fit ups and weld inspections to the satisfaction of the ABS Surveyor for work in this item. Provide ABS material certs for all steel utilized.

END OF ITEM

14 July 2017

MED/JAL ITEM NO. 12330 BASIC ITEM

DIESEL ENGINE OVERHAUL

12330-1 l.0 ABSTRACT

1.1 This item describes the 10,000 hour (Topend) overhaul of the #4 diesel engine.

2.2 NOAA Specification “Overhaul of Caterpillar 3500 Series Diesel Engines”

3.1 ITEM LOCATION/DESCRIPTION:

3.2 Location: Generator Room

3.3 Description:

3.2.1 No. 4 Diesel Generator:

CAT 3508, S/N 23Z05685

KATO Generator, 750 KW

4.1 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES:

4.2 Government Furnished Material: Engine Lube Oil and Jacket Water

4.3 Government Furnished Services: The Government will be providing the services for ABS surveys and inspections.

5.1 NOTES:

5.2 The contractor and all subcontractors, regardless of tier must consult the General Requirements contained in Work Item 10420 to determine applicability to this work item. Many of the definitions relating to performance of this work item are found in the General Requirements. In the performance of this work item, the contractor and all subcontractors regardless of tier must comply with the requirements.

5.3 The Contractor shall comply with all requirements of the vessel’s equipment tag out program prior starting work.

5.4 Prior to the start of work, the Contractor shall contact the Chief Engineer to coordinate the implementation of the Tag Out Program for the entire performance period of this item. The Prime Contractor shall be responsible for compliance by both prime and subcontractor personnel.

6.0 QUALITY ASSURANCE REQUIREMENTS: None Additional

14 July 2017

MED/JAL ITEM NO. 12330 BASIC ITEM

DIESEL ENGINE OVERHAUL

12330-2

7.1 STATEMENT OF WORK REQUIRED

7.2 Not Used.

7.3 Accomplish a 10,000 hour “Top End” overhaul of the #4 Ship Service

Diesel Generator in accordance with Reference 2.1 with the following exceptions and changes.

7.3.1 The Government will drain the engine of lube oil and

jacket water prior to commencement of the overhaul. Lube oil will be drained to the waste oil tank.

7.3.2 The Government will provide and install new lube oil, jacket water, and jacket water treatment.

7.4 Remove the governor from the engine and send to an authorized Woodward Governor repair facility for overhaul. The governor is a Woodward EGB-10P, S/N 22543860/61.

7.4.1 Overhaul is to include complete disassembly, inspection, and bench testing, painting and calibration after repairs. The following parts are to be renewed:

7.4.1.1 All o-rings, seals, gaskets

7.4.1.2 All bearings, bushings.

7.4.1.3 Drive Shaft

7.4.1.4 Oil cup

7.4.1.5 Integral cooler (overhaul kit)

7.4.1.6 PV Plunger and bushing

7.4.1.7 Dial (EGB13 overhaul kit)

7.4.1.8 Provide condition report with estimate for

additional parts required upon disassembly.

7.4.1.9 Reassemble and bench test in accordance with

manufacturer’s requirements.

7.4.1.10 Reinstall on engine. Make all adjustments for

normal engine operation.

7.4.1.11 Provide the services of an authorized Woodward

Technician during dock trials to set and calibrate the overhauled governor and the 2301A Governor controller located in the switchboard.

7.5 Temporarily remove the existing thermostatic control valves, AMOT

Model B, for this engine. Renew all thermostats, seals, O Rings and gaskets for the unit. Reinstall with new piping gaskets.

7.5 Note that Reference 2.1 Paragraph 3.4.4 contains a requirement for an underway sea trial. For estimating purposes assume this will be 10 hour sea trial departing and returning to the contractor’s facility.

END OF SPECIFICATION

14 July 2017

MED/JAL ITEM NO. 12560 BASIC ITEM

MISC VALVES AND PIPING

12560-1

1.2 This item describes the modification of various piping systems.

2.1 REFERENCES/ENCLOSURES:

2.2 Drawing RB-541 6932935 FUEL OIL TRANS & SERV SYS ARR & DETLS

2.3 Drawing 256-6932914, Sea Water Service System Diagram

2.4 Drawing RB-555-6932945, AFFF System Arrangement and Details

2.5 Drawing RB-528 6932928, Plumbing, Sewage and Weather Deck Drains

2.6 Drawing RB-506 6932919, FILLS,VENTS,& SOUNDS DIAG & DETAIL

2.7 Drawing RB-529 6932931 C BILGE & BALLAST SYS ARR & DET

3.0 ITEM LOCATION/DESCRIPTION: Refer to 7.0.

4.1 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICE:

4.2 Sixteen (16) Each three in rubber expansion joints – ($24,000) but not limited to 10420 to determine their effect on the work required under this work item. Many of the definitions relating in work item10420.

7.2 Remove and renew the rubber expansion joints with retaining rings and rods for the following systems using reference 2.2 for guidance. New expansion joints are Government Furnished Material.

New expansion joints are General Rubber Inc, Part No. 1015 CL II, neoprene. Provide and install new stainless fasteners with the new expansion joints. Prior to removal of existing joints, the system is to be tagged out by the ship’s force. No water is to be allowed to drain into the bilge or spaces. Catch and dispose of water as necessary.

7.2.1 Z Drive Cooling Water Sytems, Aft Pump Room.

QTY SIZE

16 3 in

7.2.2 Renew all insulation, including cloth wrap, for all new and disturbed areas in way of this work.

14 July 2017

MED/JAL ITEM NO. 12560 BASIC ITEM

12560-2

7.3 Accomplish the following to renew the AFFF System bilge

distribution piping. Refer to Reference 2.3 for guidance.

7.3.1 Remove the existing AFFF bilge distribution piping from the aft bulkhead of the Generator Room in its entirety. NOTE that the bronze nozzles are to be retained for re-use.

7.3.2 Install new piping to replace the existing in the same

configuration utilizing Reference 2.3 for guidance.

7.3.3 Renew all pipe brackets and hardware.

7.3.4 Install temporary plugs in place of the nozzles and

accomplish a pressure test of the system to satisfaction of the ABS Surveyor.

7.3.5 Upon successful completion of testing, install the bronze nozzles that were removed in paragraph 7.2.1

7.3.6 Paint all new and disturbed piping with two each coats of epoxy primer and one top coat to match the color of the original piping.

7.3.7 Update the ship’s existing Fire Plan in Auto Cad showing the AFFF system and components.

7.4 Renew the drain piping for the sinks located in the Bio Analytical

Lab and the Hydro Lab Autosal. Three (3) sinks total. Renew from the sink to the main gray water drain line. New piping is to be PVC. Refer to Reference 2.4 Detail 34-B.

7.5 Renew the #3 port fuel tank vent. Renewal is to include from the flange on the 01 Level weather deck, frame 41 port, to approximately two foot below the deck, 5 inch schedule 80 steel pipe. See Reference 2.5 for guidance, detail “40E” applies.

7.5.1 The ship will transfer fuel from the #3 port FO tank to other tanks to loss of suction only.

7.5.2 Renewal to include deck penetration pipe sleeve.

7.5.3 Re-utilize the existing tank vent valve with new gasket and stainless steel flange fasteners.

7.5.4 Testing new piping to the satisfaction of the ABS surveyor.

7.5.5 Note that below the deck of this pipe penetration is the overhead of Climate Control Chamber 1-41-2. Access to the the underdeck piping can be gained by removing the sheetmetal flashing on the front overhead of the Climate Control Chamber on the main deck.

7.6 Renew the fuel oil manifold valves located in the lower level of the generator room, frame 88 aft. Refer to Reference 2.1. Valves are 4 inch, 200# butterfly wafer type. Total Quantity is twenty seven (27) each valves.

7.7 Remove the existing P trap on the 4”, schedule 80 gray water drain located in the lower level of the Generator Room, port side, forward at frame 65. Install a new flanged P trap in way of removed trap.

14 July 2017

MED/JAL ITEM NO. 12560 BASIC ITEM

12560-3

7.8 Renew the saltwater ballast manifold valves located in the lower level of the generator room. Refer to Reference 2.6. Valves are 4 inch, 200# butterfly wafer type. Total quantity is twenty six (26) each valves.

14 July 2017

MED/JAL ITEM NO. 13200 BASIC ITEM

SWITCHBOARD AND ELECTRICAL EQUIPMENT CLEANING

13200-1

1.1 This item describes maintenance of the switchboards and major motor controllers on board the NOAA Ship RONALD H. BROWN.

2.1 REFERENCES:

2.2 NOAA Ship BROWN 600V Switchboard Drawing

2.3 NOAA Ship BROWN 480V Switchboard Drawing

2.4 NOAA Ship BROWN Electrical Motor & Generator Inventory

2.5 NOAA Ship BROWN Breaker Listing

2.6 US Standard Bus Connection Bolt Torque Values

3.2 Location: Switchboard Room, Main Control Station, and the Emergency

Generator Room.

3.3 Description: Two each 600V switch boards, one each ship service 480v switchboard, one each motor control center in main control, and one each emergency switchboard.

4.0GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES: None.

5.2 The Contractor shall comply with all requirements of the vessel’s equipment tag out program prior starting work.

5.3 Prior to the start of work, the Contractor shall contact the Chief for the entire performance period of this item. The Prime

6.1 QUALITY ASSURANCE REQUIREMENTS:

6.2 All work is to be inspected and approved by the COR. The COR is to inspect for cleanliness after cleaning and prior to closing up of enclosures.

7.2 Furnish labor, material and equipment to thoroughly vacuum with

HEPA vacuum cleaners all dust, dirt, film, etc., from all internal electrical/electronic components and all interior surfaces of subject switchboards and motor control centers listed in paragraph 3.0.

7.2.1 Cleaning is to be accomplished in such a manner as to

mitigate re-contamination of cleaned areas.

14 July 2017

MED/JAL ITEM NO. 13200 BASIC ITEM

13200-2

7.3 Open up switches, rheostats and breaker enclosures, vacuum, wipe down, clean blow dry and close up units per original.

7.4 Next, clean by wiping all interior surfaces, wiring, bus bars, circuit breakers, and components of the equipment listed in paragraph 3.0. This cleaning is also to include the interior surfaces of the actual enclosure and covers for subject equipment.

7.4.1 The use of cleaning solvents, the type of cleaning solvents, and what components are being cleaned with solvents of any type is to be coordinated with the COR prior to use of such materials. No solvents or chemicals containing chlorides will be permitted.

7.4.2 Cleaning is to be accomplished with lint-free rags.

7.5 Visually inspect all electrical connections and components.

7.6 The ship’s service 480V section of the switchboard will require that the ship’s power be secured. This section of the switchboard is to be cleaned on weekend day time hours only. Cleaning is to be coordinated with the COR. Contractor is to provide temporary lighting, ventilation, and a generator to power those devices and other contractor required equipment while that power is secured to clean this section.

7.7 Dress up and tighten bus bars, lug connections, terminals, relays, trips, and all contact points and tighten all electrical connections using torque wrenches to match rated torque values for various sized bolts, screws, and other fittings. Use extraordinary care and do not over-tighten connections. Fittings are to be torqued in accordance with Reference 2.5.

7.7.1 Submit as a report calibration documentation for each torque wrench on the job site.

7.8 Temporarily remove the breakers listed in Reference 2.4 from the ship to an authorized General Electric breaker service facility.

The breaker service facility is to accomplish the following requirements for the switchboard large metal frame propulsion, tie, transformer, and generator switchboard breakers, seventeen (17) breakers total.

7.8.1 Conduct detailed cleaning of all components to remove all traces of dust and debris. Disassemble/reassemble breaker components as necessary to accomplish below requirements.

7.8.2 Inspect and test electrical and mechanical components, assemblies, subassemblies, internal circuitry, and hardware to design characteristics and for missing and defective parts.

14 July 2017

MED/JAL ITEM NO. 13200 BASIC ITEM

13200-3

7.8.3 Test internal wiring, coils and transformers for open and shorted circuits and insulation resistance to ground.

Record readings. Minimum acceptable resistance to ground is one megohm.

7.8.4 Clean each mechanical part with lint-free cloths moistened with solvent to remove all dirt, lubricants, and other foreign particles. Do not let solvent come in contact with varnished surfaces.

7.8.5 Provide an as found condition report with recommendations on further repairs, if any.

7.8.6 Lubricate all operating mechanisms with OEM grease.

7.8.7 Test, adjust, calibrate, and certify the trip units of each circuit breaker for time delay and instantaneous trip settings.

7.8.8 Reinstall the breakers back on the ship.

7.8.9 After all inspections have been completed and the

switchboards have been energized, test each circuit breaker's trip setting for reverse current and low voltage trip. Make required adjustments and prove satisfactory.

7.8.10 Close and trip each circuit breaker electrically from the local and remote stations. The circuit breaker must operate correctly four consecutive times to be acceptable.

7.9 The contractor is to conduct a thermographic survey of all the components listed in paragraph 3.0, as well as the motor controllers/starters for the motors and generators listed in Ref.

2.3, during the ship’s sea trial from/to the contractor’s facility near the end of the repair period.

7.9.1 The person accomplishing the thermographic survey shall be properly trained and experienced with the equipment and know how to correctly interpret the scans.

7.9.2 Submit a detailed written report. The report is to contain color images that show the source of heat, all pertinent information and suggestions for correction, if any, for each piece of equipment.

End of Specification

ITEM NO. 14370 BASIC ITEM MED/JAL

TANK LEVEL INDICATORS REPAIRS

14370-1

1.1 This item describes the requirements for renewing and repairing various tank level indicators throughout the ship. furbishing the exterior ladders throughout the ship.

2.2 Technical Manual RB-437-00

3.2 Throughout the ship, see paragraph 7.0.

4.2 Four (4) each Gems Tank Level Indicating Assemblies:

Two (2) Part Number XM -35485-50-01 500 - 0 – L Two

(2) Part Number XM -36475-46- 01 500-030 -BL-0.5 but not limited to 10420 to determine their effect on the work required under this work item. Many of the definitions relating

5.3 Do not open or transfer any liquids to/from tanks without approval from the COR.

7.2 Open, clean, ventilate, and take all other action needed to make the following tanks safe for hot work. Post a gas-free certificate, issued by a Marine Chemist certified by the National Fire Protection Association, near the access opening to each tank. Provide a copy of each gas-free certificate to the COTR.

The tanks are:

7.2.1 No. 4 Salt Water Ballast Tanks Port and Starboard.

7.2.2 No. 5 Salt Water Ballast Tanks Port and Starboard.

7.3 Remove the existing tank level indicators including all cabling from the tanks.

7.4 Install new GFE tank level indicators and cabling.

7.5 Accomplish operational test of the new indicators prior to closing tanks.

ITEM NO. 14370 BASIC ITEM MED/JAL

TANK LEVEL INDICATORS REPAIRS

14370-2

7.6 Prior to closing tanks, the COR is to inspect each tank and be present for securing of the tank lids. Install tank lids utilizing new stainless steel hardware and rubber gaskets.

03 April 2017

MED/JAL ITEM NO. 15040 BASIC ITEM

GAUGE CALIBRATION

15040-1

1.2 This item describes the requirement to inspect and calibrate the ship’s pressure gauges, thermometers, and other devices.

2.2 NOAA Ship Ronald H. Brown Gauge and Thermometer List (excel file)

3.0 ITEM LOCATION/DESCRIPTION: Refer to 7.0

advised to review other work items under this contract to determine their effect on the work required under this work item.

5.3 The Contractor shall comply with all requirements of the vessel’s equipment tag out program prior starting calibration of devices on subject equipment.

7.2 Prior to the start of work, the Contractor shall contact the Chief for the entire performance period of this item. The Prime

7.3 Conduct a complete survey of the vessel within the first 25% of the contract availability to inspect and verify all gauges, thermometers, electrical meters, rpm indicators, pyrometers, thermocouples, salinity indicators, and flow meters that exist on board the ship and on each piece of equipment on board the ship.

Utilize Reference 2.1 for guidance.

7.3.1 Submit a condition report identifying any devices that are not listed on Reference 2.1 and all devices that will require replacement or repair prior to being able to be calibrated with an estimate for each item.

7.4 Calibrate and adjust all the devices listed in Reference 2.1.

Replace with new all seals, gaskets, defective terminal lugs and fasteners where applicable.

7.4.1 Gages, meters, thermometers and all other devices are to be calibrated to a transfer measurement standard, traceable to the National Institute of Standards and technology (NIST) and in accordance with the manufacturer’s specifications.

The Contractor shall utilize standards which have an

03 April 2017

MED/JAL ITEM NO. 15040 BASIC ITEM

GAUGE CALIBRATION

15040-2 accuracy level at least four times that of the instrument being calibrated.

7.4.2 The contractor shall provide a certificate of calibration for each instrument which shall include the date, manufacture, model and serial number, full name of the individual performing the calibration, and traceability number of the standard used in the calibration.

7.3.3Affix a tamper proof calibration label denoting the name of the calibrating facility, the date of the calibration.

Labels shall be placed over calibration adjusting screws where applicable.

7.3.4 All gages, meters, thermometers, and accessories shall be calibrated in place where possible.

7.4 Prove all gages, meters, and thermometers that were worked are operational and connections tight to the satisfaction of the COR.

03 APRIL 2017

MED/JAL ITEM NO. 15120 BASIC ITEM

15120-1

VENTILATION REPAIRS

1.2 This item describes the repairs to various ventilation systems.

2.2 Drawing RB-512-6932958, Hvac Arrg't. & Details Generator Room

2.3 Drawing RB-514-6932961, HVAC General Notes and Construction Details

3.0 ITEM LOCATION/DESCRIPTION: Refer to paragraph 7.0

but not limited to 10420 to determine their effect on the work required under this work item. Many of the definitions relating

7.2 Renew the ducting for Supply System S01-66-2 in the upper level of the Generator Room Port side. Renew from the plenum at approx.

Frame 66 to and including the ducting terminuses. Refer to Reference 2.1 which is red lined to show the ducting to be worked.

7.2.1 New ducting is to be 16 gauge galvanized steel ducting.

7.2.2 New ducting is to be inclusive all attachments such as

screens, dampers, terminus bells, etc.

7.2.3 Renew all ducting straps and hangers.

7.3 Paint all new ducting exterior surfaces with one each coat of epoxy primer and one top coat to match existing.

7.4 In the presence of the COR, adjust the balance dampers to provide the proper air flow at each terminus as shown in reference 2.1.

Permanently secure the balance damper arm with sheet metal screws.

03 APRIL 2017

MED/JAL ITEM NO. 15160 BASIC ITEM

REEFER BOXES REPAIRS

15160-1

1.1 This item describes the renewal of the existing insulated deck system for the ship’s chill box stores and new surface decking for the ship’s freeze box stores.

2.2 Drawing RB-638-6932868, REEFER SPACES & REEFER DRS ARRG'T & DETAILS

3.2 Chilled Stores (3-55-1)

3.3 Frozen Store (3-48-1)

but not limited to 10420 to determine their effect on the work required under this work item. Many of the definitions relating

5.3 The ship will arrive with both the chill and freeze stores near empty. The ship will require one week to complete offloading of the remaining stores prior to the start of work on this item.

7.1. Temporarily remove all shelving, removable stanchions, and grating from the chill and freeze store boxes.

7.2. Accomplish the following for the Chill Stores box. Reference 2.1 applies. The existing decking system in this box has failed.

7.2.1. Remove the existing entire decking system utilizing reference 2.1 for guidance. Remove the perimeter Z flashing, and remove the decking system from that point down to the steel deck.

7.2.2. Prepare the steel deck to SSPC-SP-11. Coat with two each coats of marine epoxy primer.

7.2.3. While the deck is exposed, accomplish ultrasonic testing of the steel deck, for estimating purposes assume 200 shots. Readings are to be accomplished by an ABS certified facility. Submit report. Do not install any further decking until approved by the COR.

7.2.4. Install new decking system in accordance with Reference 2.1 for guidance.

03 APRIL 2017

MED/JAL ITEM NO. 15160 BASIC ITEM

REEFER BOXES REPAIRS

15160-2

7.3. Accomplish the following for the freeze Stores box. Reference 2.1 applies.

7.3.1. Remove the existing PRC Deck coverings.

7.3.2. Remove all loose mastic from the deck to a tight deck. Conduct an inspection of the deck with the COR.

7.3.3. Patch the mastic decking where required. For estimating purposes, assume the entire deck will require mastic repairs ½” deep.

7.3.4. After mastic dries, install Proreco PRC decking system, or equal, on the entire deck.

7.4. Reinstall all interferences removed in paragraph 7.1.

24 June 2017

MEB/JAL ITEM NO. 15550 BASIC ITEM

ANNUAL FIRE FIGHTING SYSTEMS CERTIFICATION

15550-1

1.2 This item describes the annual inspection and test of the fire extinguishing systems on board the NOAA Ship RONALD H. BROWN.

2.2 DRAWING 555-6932945 AFFF SYSTEM

2.3 DRAWING 555-02 REV C, FIRE PLAN

2.4 Fire Hose Inventory

3.1 ITEM LOCATION/DESCRIPTION

3.2 CO2 Fixed Fire Extinguishing Systems

3.2.1 Engine Room System

Twenty-four (24) each 100 lb. cylinders Bottle Location: Scientific Storage Room (2-90-0)

3.2.2 Forward Paint Locker (02-46-1) System

One (1) each 35 lb bottle

3.2.3 Aft Paint Locker (02-67-1)

One (1) each 35 lb bottle

3.2.4 Propulusion Motor Room System

Eight (8) each 100 lb. cylinders Bottle Location: Aft Winch Room (2-99-0)

3.2.5 Stbd. Propulsion Motor Enclosure

One (1) each 50 lb. cylinder

3.2.6 Port Propulsion Motor Enclosure

3.2.7 Bow Thruster Room System

3.2.8 Haz Mat Locker System

3.2.9 Incinerator Room

3.2.10 Emergency Generator Room

One (1) each 100 lb. cylinder

3.2.11 Galley Deep Fat Fryer

One (1) Ansul R-102

24 June 2017

MEB/JAL ITEM NO. 15550 BASIC ITEM

15550-2

3.2.12 Galley Griddle

One (1) Ansul R-102

3.3 Galley Hood Sytems

Mfr: Gaylord Industries Over oven: Model NAD-CA-48 Over fryer: Model NAB-24 Over griddle: Model NAB-24 Vent Control Cabinet: Model NGPL-200

3.4 Aqueous Film Forming Foam (AFFF) System

3.4.1 One each 100 Gallon tank (Located in Pump Room (3-90-0).

3.4.2 Single Agent Hose Stations

No. of Stations: 4

• Two (2) in Engine Room

• Two (2) in Propulsion Motor Room

Location: See reference 2.3.

3.5 Portable Fire Extinguishers

3.5.1 Type Size Quantity

CO2 15 lb 51 BC 10 lb 2 PK 10 lb 19 ABC 10 lb 50 ABC 2.5 lb 03

TOTAL = 125

3.6 SCBA Equipment

3.6.1 Sixteen (16) Each Scott Air Packs

3.6.2 Twenty four (24) each bottles.

4.2 The Government will provide the services of an ABS Surveyor.

5.2 The ship is to be left with adequate fire protection at all times during the performance of this item. No more than 30% of the portable extinguishers are to be removed from the vessel at any one time. No fixed fire fighting system shall be left in an inoperable condition overnight without prior approval of the

COTR.

5.3 The Government shall provide the services of an ABS Surveyor. The contractor is to give the COR and ABS Surveryor an opportunity to witness all testing by providing 24 hour notice prior to all testing.

24 June 2017

MEB/JAL ITEM NO. 15550 BASIC ITEM

15550-3

5.4 Note that the AFFF piping in the Generator Room is being renewed in Work Item 12560.

6.1 QUALITY ASSURANCE REQUIREMENTS:

6.2 Personnel, shop or sub-contractor are to be trained at a

manufacturer’s approved school and specialized in the inspection, and repair of fixed and portable CO2, Halon, AFFF, dry chemical, fire main and sprinkling system and equipment and be certified by the American Bureau of Shipping to conduct these inspections.

7.2 PORTABLE EXTINGUISHERS: Inspect and weigh all portable

extinguishers identified in 3.4, including the discharge hose and check the condition of the powder in dry chemical type extinguishers using Ref. 2.4 for guidance.

7.2.1 Submit a report to the COTR identifying the size and number of additional extinguishers requiring recharging or hydrostatic testing.

7.2.2 Any extinguisher found to be rejected, for whatever reason, shall be set aside. Submit a report to the COTR identifying the extinguisher(s) found to be rejected and the reason(s) why.

7.2.3 Upon completion, all portable extinguishers shall be

returned to their designated stations or stowage locations in the case of spares.

7.3 FIXED CO2 Systems

7.3.1 Examine and weigh fixed CO2 cylinders as identified in 3.1.

7.3.1.1 Submit a report to the COTR identifying the size

and number of cylinders requiring recharging or hydrostatic testing (If any). Costs associated with recharging or hydrostatic testing will be the subject of a change order.

7.3.1.2 Any cylinder found to be rejected, for whatever

cause, shall be set aside. Submit a report to the COTR identifying the number and reason(s) as to why the cylinder(s) is not fit for further service.

7.3.2 Inspect hoses between fixed cylinders and the distribution piping. Any hoses found to be rejected shall be set aside and a report submitted to the COTR identifying the quantity

24 June 2017

MEB/JAL ITEM NO. 15550 BASIC ITEM

15550-4 and the reason(s) as to why the hose(s) is not fit for further service.

7.3.3 Examine, test and demonstrate all time delays, alarms, shutdowns, automatic fire dampeners, and controls for ABS.

All components shall be proven to function in their prescribed manner.

7.3.4 Examine all fixed piping, nozzles and valves to ensure

their satisfactory material condition. Connect an inert gas (nitrogen) to the system and blow-out the piping to prove it clear to ABS. Ensure that all safety precautions including, but not limited to, posting of warning notices on the space(s) affected, announcements of tests being conducted, venting of the space(s) affected and having appropriate safety equipment on site and ready for use, are exercised.

7.3.5 Modify the existing Fixed CO2 system for the forward paint locker by accomplishing the following:

7.3.5.1 Install a time delay, siren, and associated piping

and fittings into the existing CO2 piping for this space.

7.3.5.2 All new components shall be USCG and ABS certified.

Provide a copy of the certifications to the COR.

7.3.5.3 Pressure test all new and disturbed piping to the

satisfaction of the ABS Surveyor.

7.4 FIRE DETECTION SYSTEM

7.4.1 Test all smoke and/or fire detection systems and

demonstrate their proper functioning to ABS. Upon completion of tests and demonstrations, all systems shall be restored to normal operating configuration and left in a ready…