WI_22520_Woodward_Controls_Upgrade_spec.pdf
PDF 11 KB Posted
- Attached to
- NOAA Ship RONALD H. BROWN DOCKSIDE REPAIRS Federal contract opportunity
- Solicitation number
- EA-133M-17-RP-0081
About this file
WI_22520 Woodward Controls Upgrade_spec
View the file
Other files for this federal contract opportunity
Show all 50
NOAA Ship RONALD H. BROWN DOCKSIDE REPAIRS has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NOAA SHIP RONALD H. BROWN
(R-104)
24 June 2017
ITEM NO. 22520 BASIC ITEM MED/JAL
WOODWARD CONTROLS UPGRADE
22520-1 l.0 ABSTRACT
1.1 This item describes the requirement to upgrade the existing Woodward 2301A Electronic Load Sharing and Speed Control units to new Woodward 2301E Electronic Load Sharing and Speed Control units on board the NOAA Ship RONALD
H. BROWN.
2.0 REFERENCES:
2.1 Drawing NOAA Ship BROWN 600V Switchboard Drawing
2.2 NOAA Ship BROWN 480V Switchboard Drawing
3.0 ITEM LOCATION: Switchboard Room
4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES: None.
5.0 NOTES:
5.1 The Government will provide ship’s personnel to assist testing of engines.
6.0 QUALITY ASSURANCE REQUIREMENTS: None Additional
7.0 STATEMENT OF WORK REQUIRED:
7.1 Ship force shall secure and tag out equipment and associated systems specified in 3.0.
7.2 Provide the services of a factory authorized Woodward Controls engineer to accomplish the following to upgrade the ship’s existing Woodward 2301A Electronic Load Sharing and Speed Control units to new Woodward 2301E Electronic Load Sharing and Speed Control units.
Utilize Reference 2.1 for guidance.
7.3 Disconnect and remove the existing 2301A units.
7.4 Provide and install six each new 2301E units. The new units are to utilize the existing 24VDC power source.
7.4 The new units are to work with the existing governor actuators mounted on each engine. The existing actuators are Woodward EGB-10P Part Number: 8241-513. These units are reverse acting.
7.5 Configure/program the new 2301E units to provide the same functionality as the existing 2301A units.
7.6 Accomplish alongside testing of each generator in every possible configuration of on line operation with each of the other generators. Demonstrate the operation of the new units to the satisfaction of the ABS Surveyor.
NOAA SHIP RONALD H. BROWN
(R-104)
24 June 2017
ITEM NO. 22520 BASIC ITEM MED/JAL
WOODWARD CONTROLS UPGRADE
22520-2
7.7 Provide and turn over to the ship’s crew one each spare 2301E unit and two each connection cables that connect to an external computer for trouble shooting/programming.
7.8 Install the necessary software on the ship’s engineering laptop to allow the ship’s engineers to trouble shoot the 2301E units.
7.9 Provide an eight hour crew training session on the proper operation, troubleshooting, and replacement techniques of the units.
7.10 The Woodward technician shall be on board for a one day 10 hour sea trial near the end of the contract performance period.
7.11 Provide the services of a factory trained and authorized Basler controls technician to inspect/adjust the ship’s six each Basler DECS2001L Voltage Regulators and to provide crew training on same.
The controls technician shall be on site for two days for alongside testing as well as one ten hour day underway for sea trials.
7.12 Provide a red line mark up of Reference 2.1 in pdf format showing all changes.