Drawings_Part2.pdf

PDF 7 MB Posted

Attached to
Upgrade Doors and Hardware - Iowa City VAMC
Solicitation number
36C26325B0015_1
Issued by

About this file

This document is a Demolition Plan drawing for Buildings 1 and 50, Floor 1 at the Iowa City VA Health Care System, prepared by Fourfront Design, Inc. The architectural drawing details specific door demolition and upgrade requirements across multiple rooms and areas. Key specifications include removing existing doors, frames, and hardware for several designated doors (1CN03, 1E06, 1CN01), preparing certain doors for operators and push pads, and coordinating demolition work between trades. The plan includes a comprehensive floor layout with detailed notes instructing contractors to verify existing conditions, dimensions, and coordinate work, with a scale of 1/16" = 1'-0". The project is part of a door hardware upgrade construction document set, with the drawing dated 8/28/2024 and located in Iowa City, Iowa.

View the file

Other files

File Type Posted
36C26325B0015 0004.docx DOCX document
636A8-23-102 Upgrade Doors Hardware QA_Revised 9.5.25.docx DOCX document
ICRA DOOR SCHEDULE_20240719.xlsx XLSX spreadsheet
36C26325B0015 0003.docx DOCX document
Wage Determination IA20250068 8.22.25.pdf PDF
Site Visit Sign in Sheet.pdf PDF
Specifications Revised 9.3.25.pdf PDF
636A8-23-102 Upgrade Doors Hardware QA.docx DOCX document
JA Best Access Systems - Cormax_Redacted.pdf PDF
Final SOW_8.18.25.docx DOCX document
JA Honeywell - Lenel Fully_Redacted.pdf PDF
36C26325B0015 0002.docx DOCX document
Specifications Revised 8.18.25.pdf PDF
Updated Door Schedule Dwg No. A6.00.pdf PDF
IFB Attachment - Site Visit Campus Map.pdf PDF
36C26325B0015 0001 (Amendment 0001).pdf PDF
Questions_Answers or Clarifications (Attachment).pdf PDF
Specifications 486 pages.pdf PDF
Safety or Environmental Violations and EMR Information 2 pages.pdf PDF
Drawings_Part7.pdf PDF
SOW Final 6 pages.pdf PDF
Drawings_Part3.pdf PDF
Drawings_Part5.pdf PDF
Drawings_Part6.pdf PDF
Wage Determination 8-8-2025 7 pages.pdf PDF
Limitations on Subcontracting Certificate of Compliance 2 pages.pdf PDF
VA Handbook 6500.6 Appendix C.pdf PDF
36C26325B0015_1.docx DOCX document
Drawings_Part1.pdf PDF
Drawings_Part4.pdf PDF
TMS 20939 VA Privacy Training.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DN

UPDN

UP

DN

UP

R

EF.

1CN01A

1CN01

C

N

1W501CW07A

1CW07

1C07

1E06

W

50C101

AD1.11

AD1.11

AD1.11

AD1.11

AD1.11

AD1.11

AD1.11

AD1.11

DOOR 1CW07

SEE DOOR SCHEDULE

DOOR 1CW07A

SEE DOOR SCHEDULE.

DOOR 1W50

SEE DOOR SCHEDULE

DOOR 1CN01

SEE DOOR SCHEDULE.

DOOR 1CN01A

SEE DOOR SCHEDULE.

DOOR 1C07

PREP DOOR FOR OPERATOR AND

PUSH PAD, SEE ELECTRICAL.

DOOR 1E06

REMOVE EXISTING DOOR,

FRAME AND HARDWARE.

SEE DOOR SCHEDULE.

DOOR 1W36

SEE DOOR SCHEDULE.

DOOR 50C101

SEE DOOR SCHEDULE.

DOOR 1CN03

REMOVE EXISTING DOOR,

FRAME AND HARDWARE.

SEE DOOR SCHEDULE.

1CN03A

AD1.11

DOOR 1CN03A

REMOVE FRAME, DOOR AND HARDWARE

1. SHEET SIZE FOR PROPER SCALE IS 42X30. CONTRACTOR SHALL NOT

SCALE DRAWINGS BUT SHALL REQUEST THE DESIRED DIMENSIONS FROM

THE ARCHITECT.

2. IT IS THE RESPONSIBILITY OF THE CONTRACTOR TO FIELD VISIT THE

PROJECT AND VERIFY EXISTING CONDITIONS/DIMENSIONS AND

PROPOSED CONDITIONS. COORDINATE DEMOLITION BETWEEN ALL

TRADES. NOTIFY A/E IMMEDIATELY OF ANY CONFLICTS OR

DISCREPANCIES.

3. SEE ENLARGED AREA PLANS FOR KEYNOTES.

4. EXISTING AREAS NOT IN CONTRACT SHOWN SHADED FOR CLARITY.

POINT OF EGRESS

SHEET LEGEND:

NORTH ARROW

PLAN NORTH

TRUE NORTH

1-HOUR FIRE BARRIER

WALL RATING LEGEND:

2-HOUR FIRE BARRIER

SMOKE BARRIER

2-HOUR FIRE SMOKE

BARRIER

FIRE RATING

SMOKE AND FIRE RATING

1-HOUR FIRE SMOKE

BARRIER

SMOKE PARTITION

SMOKE RESISTIVE

CORRIDOR WALL

FOURFRONT DESIGN, INC.

517 7TH STREET

RAPID CITY, SOUTH DAKOTA 57701

PH: (605) 342-9470

FAX: (605) 342-2377

WWW.FOURFRONTDESIGN.COM

FOUR FRONT

D E S I G N I N C.

Project Number

Building Number

Drawing Number

Dwg.

DrawnCheckedDate

Location

Project TitleDrawing Title

COR / Project Engineer

CONSULTANTS:

DateRevisions:

VA FORM 08-6231

o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t th re e in c h e s o n e fo o t

F

E

D

C

B

A

1 2 3 4 5 6 7 8 9

F

E

D

C

B

A

1 2 3 4 5 6 7 8 9 of

Office of Construction and Facilities Management

Department of Veterans Affairs

Phase

STAMP: ARCHITECT/ENGINEER OF RECORD:

4F PROJECT NO: 19.2481.A26 40

/2 /2

:2

:2

P M

8/28/2024

DEMOLITION PLAN - BUILDINGS 1

AND 50, FLOOR 1 PLAN

AD1.02

UPGRADE DOORS/DOOR

HARDWARE AT IOWA CITY VA

HEALTH CARE SYSTEM

JEKP

IOWA CITY, IOWAMATTHEW RUPPENKAMP

CONSTRUCTION

DOCUMENTS

636A8-23-102

CONSTRUCTION DOCUMENTS1/16" = 1'-0"

BUILDING 1, FLOOR 1 DEMO PLAN

GENERAL NOTES:

Sheets
AD1.02 - DEMOLITION PLAN - BUILDINGS 1 AND 50, FLOOR 1 PLAN
AD1.03 - DEMOLITION PLAN - BUILDINGS 1 AND 50, FLOOR 2 PLAN
AD1.05 - DEMOLITION PLAN - BUILDING 1, FLOOR 4 PLAN
AD1.06 - DEMOLITION PLAN - BUILDING 1, FLOOR 5 PLAN
AD1.07 - DEMOLITION PLAN - BUILDING 1, FLOOR 6 PLAN

File details come from the government source that posted it. Updated .