Updated Door Schedule Dwg No. A6.00.pdf
PDF 431 KB Posted
- Attached to
- Upgrade Doors and Hardware - Iowa City VAMC
- Solicitation number
- 36C26325B0015_1
About this file
This document is a door schedule for an upgrade project at the Iowa City VA Health Care System, detailing door replacements and modifications across multiple buildings and levels. The comprehensive schedule covers Buildings 1, 2, 7, and 50, with specific details for each door including fire rating, panel dimensions, materials, finishes, hardware groups, and installation requirements. The project involves replacing, modifying, and upgrading doors with various specifications such as adding operators, access control, Personal Identity Verification (PIV), and maintaining egress paths. Work is to be performed during routine work hours, nights, or weekends, with careful coordination required to minimize disruption. The door upgrades include different types of doors (hollow metal, wood, aluminum, fiberglass) with various finishes and functional requirements, such as fire-rated glass, lead-lined doors, and integration with existing access control systems.
View the file
Other files
Show all 31
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ALUM ALUMINUM
F FLUSH FULL
FG FULL GLASS
FRP FIBERGLASS REINFORCED POLYMER
FTF FACTORY TRANSPARENT FINISH
HM HOLLOW METAL
ME MATCH EXISTING
NV NARROW VIEW
PTE PAINT TO MATCH EXISTING
SG SPLIT GLASS
STE STAIN TO MATCH EXISTING
PIV PERSONAL IDENTITY VERIFICATION
VV VISION VIEW
WD WOOD
DOOR LEGEND:
FOURFRONT DESIGN, INC.
517 7TH STREET
RAPID CITY, SOUTH DAKOTA 57701
PH: (605) 342-9470
FAX: (605) 342-2377
WWW.FOURFRONTDESIGN.COM
FOUR FRONT
D E S I G N I N C.
Project Number
Building Number
Drawing Number
Dwg.
DrawnCheckedDate
Location
Project TitleDrawing Title
COR / Project Engineer
CONSULTANTS:
DateRevisions:
VA FORM 08-6231
o n e e ig h th in c h o n e fo o t o n e q u a rt e r in c h o n e fo o t th re e e ig h th s in c h o n e fo o t o n e h a lf in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t o n e in c h o n e fo o t o n e a n d o n e h a lf in c h e s o n e fo o t th re e in c h e s o n e fo o t
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9 of
Office of Construction and Facilities Management
Department of Veterans Affairs
Phase
STAMP: ARCHITECT/ENGINEER OF RECORD:
4F PROJECT NO: 19.2481.A26 40
/2 /2
:2
:1
P M
8/28/2024
DOOR SCHEDULES
A6.00
UPGRADE DOORS/DOOR
HARDWARE AT IOWA CITY VA
HEALTH CARE SYSTEM
JEKP
IOWA CITY, IOWAMATTHEW RUPPENKAMP
CONSTRUCTION
DOCUMENTS
636A8-23-102
CONSTRUCTION DOCUMENTS
DOOR SCHEDULE - BUILDING 1
Level
DOOR
NUMBER FIRE RATING
PANEL
WIDTH
PANEL
HEIGHT
PANEL
THICKNESS
PANEL
COUNT PANEL TYPE
PANEL
MATERIAL
PANEL
FINISH
GLAZING
TYPE
FRAME
TYPE
FRAME
MATERIAL FRAME FINISH HEAD JAMB SILL
HARDWARE
GROUP
NEW
OPERATOR
NEW
PIV PHASING* NOT USED COMMENTS
BUILDING 1
BASEMENT BC07 --- 3' - 8" 7' - 0" --- 1 HG ALUM FTF --- AL-002 ALUM FTF 5/A6.01 10/A6.01 11/A6.01 02 NO NO ROUTINE WORK HOURS NEW ALUM DOOR AND FRAME REUSE ACCESS CONTROL AND OPERATOR, ADD INSIDE ACTUATOR / MAINTAIN MOTION SENSORS IN THE
PATH OF EGRESS
BASEMENT BCS03B 90 MIN. 3' - 0" 7' - 0" 1 3/4" 1 NV EXISTING PTE --- EXISTING HM PTE --- --- --- 03 NO NO NIGHT OR WEEKEND AND NOT AT THE
SAME TIME AS BW107, BW101, BCW02
ADD NEW MOTION SENSOR / MAINTAIN MOTION SENSORS IN THE PATH OF EGRESS
BASEMENT BCW02 90 MIN. 7' - 0" 7' - 0" 1 3/4" 2 NV HM PTE --- HM-001 HM PTE 1/A6.01 6/A6.01 04 NO NO START FRIDAY NIGHT AND FINISH BY
SUNDAY NIGHT AND NOT AT THE SAME
TIME AS BCS03B, BW107, BW101
NEW DOOR, FRAME AND HARDWARE
BASEMENT BE00 --- 3' - 0" 6' - 0" 1 3/4" 1 F HM PTE --- HM-001 HM PTE 3/A6.01 8/A6.01 --- 01 NO NO ROUTINE WORK HOURS NEW DOOR, FRAME AND HARDWARE FRAME SET IN BRICK VENEER WITH CONCRETE WALLS
BASEMENT BE01 --- 3' - 0" 7' - 0" 1 3/4" 1 F HM PTE --- 4 - SIDED HM PTE 4/A6.01 9/A6.01 --- 01 NO NO ROUTINE WORK HOURS NEW DOOR, FRAME AND HARDWARE FRAME SET IN BRICK VENEER WITH CONCRETE WALLS
BASEMENT BE24 45 MIN. 6' - 0" 7' - 0" 1 3/4" 2 NV HM PTE --- HM-001 HM PTE 1/A6.01 6/A6.01 --- 05 NO NO ROUTINE WORK HOURS NEW DOOR, FRAME AND HARDWARE RECONNECT ACCESS CONTROL
BASEMENT BS04 --- 4' - 0" 7' - 0" 1 3/4" 1 F WD STE --- HM-001 HM PTE 1/A6.01 6/A6.01 --- 06 NO NO ROUTINE WORK HOURS NEW DOOR, FRAME AND HARDWARE
BASEMENT BW12A --- 3' - 0" 7' - 0" 1 3/4" 1 F HM PTE --- HM-001 HM PTE 3/A6.01 8/A6.01 --- 07 NO NO ROUTINE WORK HOURS NEW DOOR, FRAME AND HARDWARE FRAME SET IN BRICK VENEER WITH CONCRETE WALLS
BASEMENT BW101 --- 7' - 0" 7' - 0" 1 3/4" 2 NV EXISTING EXISTING --- EXISTING EXISTING EXISTING --- --- --- 03 NO NO NIGHT OR WEEKEND AND NOT AT THE
SAME TIME AS BCS03B, BW107, BCW02
ADD NEW MOTION SENSOR
BASEMENT BW107 --- 6' - 0" 7' - 0" 1 3/4" 2 NV EXISTING PTE --- EXISTING EXISTING FTF --- --- --- 03 NO NO NIGHT OR WEEKEND AND NOT AT THE
SAME TIME AS BW101, BCW02, BCS03B
ADD NEW MOTION SENSOR / PAINT EXISITING HM DOOR AND FRAME
BASEMENT BW110C 45 MIN. 3' - 0" 7' - 0" 1 3/4" 1 F HM PTE --- HM-001 HM PTE 1/A6.01 6/A6.01 --- 08 NO NO ROUTINE WORK HOURS NEW DOOR, FRAME AND HARDWARE RECONNECTING ACCESS CONTROL, NEW ELECTRIC STRIKE
BASEMENT BW114 45 MIN. 3' - 8" 7' - 0" 1 3/4" 1 NV HM PTE --- HM-001 HM PTE 1/A6.01 6/A6.01 --- 08 NO NO ROUTINE WORK HOURS NEW DOOR, FRAME AND HARDWARE RECONNECTING ACCESS CONTROL, NEW ELECTRIC STRIKE, NARROW LIGHT GLASS
BASEMENT BW115 45 MIN. 3' - 8" 7' - 0" 1 3/4" 1 NV HM PTE --- HM-001 HM PTE 1/A6.01 6/A6.01 --- 08 NO NO ROUTINE WORK HOURS NEW DOOR AND FRAME / TO MATCH WARD / FIRE RATED GLASS / CLASSROOM W/ NARROW LIGHT
LEVEL 1 1C07 --- 3' - 6" 7' - 0" 1 3/4" 1 F EXISTING STE --- EXISTING EXISTING PTE --- --- --- 09 YES NO ROUTINE WORK HOURS ADD OPERATOR AND PUSH BUTTON OPENER AND TIE INTO EXISTING ACCESS CONTROL
LEVEL 1 1CN01 --- 12' - 6" 7' - 0" --- 2 ME ALUM ME --- AL-101 ALUM ME 2/A6.01 7/A6.01 --- SLIDER NO NO NIGHT OR WEEKEND, MAINTAIN EGRESS, FIREWATCH
NEW AUTO SLIDING DOORS / MAINTAIN MOTION SENSORS IN THE PATH OF EGRESS
LEVEL 1 1CN01A --- 12' - 6" 7' - 0" --- 2 ME ALUM ME --- AL-101 ALUM ME 2/A6.01 7/A6.01 --- SLIDER NO NO NIGHT OR WEEKEND, MAINTAIN EGRESS, FIREWATCH
NEW AUTO SLIDING DOORS / MAINTAIN MOTION SENSORS IN THE PATH OF EGRESS
LEVEL 1 1CN03 --- 5' - 8" 7' - 0" 1 3/4" 2 UNEVEN HG WD STE --- HM-001 HM PTE 1/A6.01 6/A6.01 --- 10 YES YES ROUTINE WORK HOURS NEW DOOR AND FRAME AND HARDWARE- 3'-8" PANEL WITH HALF GLASS AND SOLID PANEL FOR 2'-0" FLUSH PANEL WITH ELEC EXIT
DEVICE
LEVEL 1 1CN03A --- 4' - 0" 7' - 0" 1 3/4" 1 VV WD STE --- HM HM PTE 1/A6.01 6/A6.01 --- 28 YES YES ROUTINE WORK HOURS REPLACE DOOR AND FRAME ADD ACCESS CONTROL ADD OPERATOR
LEVEL 1 1CW07 --- 6' - 0" 7' - 0" 1 3/4" 2 FG EXISTING PTE --- EXISTING ALUM ALUM --- --- --- 15 YES NO NIGHT, MAINTAIN EGRESS REMOVE AND REPLACE OPERATOR / MAINTAIN MOTION SENSORS IN THE PATH OF EGRESS
LEVEL 1 1CW07A --- 6' - 4" 7' - 0" 1 3/4" 2 FG EXISTING PTE --- EXISTING ALUM FTF --- --- --- 15 YES NO NIGHT, MAINTAIN EGRESS REMOVE AND REPLACE OPERATOR / MAINTAIN MOTION SENSORS IN THE PATH OF EGRESS
LEVEL 1 1E06 --- 3' - 0" 7' - 0" 1 3/4" 1 F WD STE --- HM-001 HM PTE 1/A6.01 6/A6.01 --- 16 NO NO ROUTINE WORK HOURS NEW DOOR, FRAME AND HARDWARE
LEVEL 1 1W36 SMOKE
BARRIER
3' - 6" 7' - 0" 1 3/4" 1 F EXISTING PTE --- EXISTING HM PTE --- --- --- 09 YES NO ROUTINE WORK HOURS ADD OPERATOR AND PUSH BUTTON OPENER AND TIE INTO EXISTING ACCESS CONTROL / MAINTAIN MOTION SENSORS IN THE PATH OF
EGRESS
LEVEL 1 1W50 --- 6' - 5 1/2" 7' - 0" 1 3/4" 2 FG EXISTING PTE --- EXISTING ALUM ALUM --- --- --- 15 YES NO NIGHT OR WEEKEND, MAINTAIN EGRESS, FIREWATCH
REMOVE AND REPLACE OPERATOR / MAINTAIN MOTION SENSORS IN THE PATH OF EGRESS
LEVEL 2 2CS08 --- 4' - 0" 7' - 0" 1 3/4" 1 FG EXISTING STE --- EXISTING HM PTE --- --- --- N/A YES NO NIGHT OR WEEKEND ADD OPERATOR, MOVE EXISTING SENSOR, ADD HIDDEN PUSH BUTTON AT RECEPTION DESK, COORDINATE LOCATION WITH COR. /
MAINTAIN MOTION SENSORS IN THE PATH OF EGRESS
LEVEL 2 2W41 --- 5' - 8" 9' - 0" 1 3/4" 2 UNEVEN F WD - LEAD
LINED
STE --- HM - LEAD
LINED
HM PTE --- --- --- 21 NO NO NOT AT THE SAME TIME AS 2W44 REPLACE WOOD SLAB DOORS AND HARDWARE
LEVEL 2 2W44 --- 5' - 8" 9' - 0" 1 3/4" 2 UNEVEN F WD - LEAD
LINED
STE --- HM - LEAD
LINED
HM PTE --- --- --- 21 NO NO NOT AT THE SAME TIME AS 2W41 REPLACE WOOD SLAB DOORS AND HARDWARE
LEVEL 4 4C10 --- 4' - 0" 7' - 0" 1 3/4" 1 F EXISTING STE --- EXISTING HM PTE --- --- --- 18 YES NO MAINTAIN EGRESS REMOVE AND REPLACE OPERATOR / MAINTAIN MOTION SENSORS IN THE PATH OF EGRESS
LEVEL 4 4CE05 SMOKE
BARRIER
7' - 0" 7' - 0" 1 3/4" 2 F EXISTING STE --- EXISTING HM PTE 1/A6.01 6/A6.01 --- 24 YES NO MAINTAIN EGRESS REMOVE AND REPLACE OPERATOR ADD SMOKE SEALS
LEVEL 4 4CS03 SMOKE
BARRIER
7' - 0" 7' - 0" 1 3/4" 2 F EXISTING STE --- EXISTING HM PTE 1/A6.01 6/A6.01 --- 25 YES NO NIGHT OR WEEKEND AND NOT AT THE
SAME TIME AS 4CS04
REMOVE AND REPLACE OPERATOR / ADD NEW UL ARMOR PLATES / SHIM DOOR TO MEET NFPA101 REQUIREMENTS / MAINTAIN MOTION
SENSOR IN THE PATH OF EGRESS
LEVEL 4 4CS04 --- 7' - 0" 7' - 0" --- 2 F EXISTING STE --- EXISTING HM PTE --- --- --- 25 YES NO NIGHT OR WEEKEND AND NOT AT THE
SAME TIME AS 4CS03
REMOVE AND REPLACE OPERATOR / MAINTAIN MOTION SENSOR IN THE PATH OF EGRESS
LEVEL 4 4CS05 SMOKE
BARRIER
7' - 0" 7' - 0" --- 2 F EXISTING STE --- EXISTING HM PTE --- --- --- 23 YES NO NIGHT OR WEEKEND AND NOT AT THE
SAME TIME AS 4CS06 OR 4CS05A,
MAINTAIN EGRESS
REMOVE AND REPLACE OPERATOR / MAINTAIN MOTION SENSOR IN THE PATH OF EGRESS
LEVEL 4 4CS05A --- 7' - 0" 7' - 0" --- 2 F EXISTING STE --- EXISTING HM PTE --- --- --- 23 YES NO NIGHT OR WEEKEND AND NOT AT THE
SAME TIME AS 4CS06 OR 4CS05,
MAINTAIN EGRESS
REMOVE AND REPLACE OPERATOR
LEVEL 4 4CS06 --- 7' - 0" 7' - 0" 1 3/4" 2 F EXISTING STE --- EXISTING HM PTE --- --- --- 26 YES NO NIGHT OR WEEKEND AND NOT AT THE
SAME TIME AS 4CS05 OR 4CS05A,
MAINTAIN EGRESS
REMOVE AND REPLACE OPERATOR AND ARMOR PLATES / MAINTAIN MOTIONSENSORS IN THE PATH OF EGRESS
LEVEL 4 4CS07A SMOKE
BARRIER
7' - 0" 7' - 0" 1 3/4" 2 F EXISTING STE --- EXISTING HM PTE --- --- --- 27 NO NO NIGHT OR WEEKEND AND NOT AT THE
SAME TIME AS 4CS05, 4CS05A, 4CS06,
MAINTAIN EGRESS
REMOVE AND REPLACE ARMOR PLATE
LEVEL 4 4CW07 --- 7' - 0" 7' - 0" 1 3/4" 2 NV EXISTING PTE --- EXISTING HM PTE --- --- --- 23 YES NO NIGHT OR WEEKEND AND NOT AT THE
SAME TIME AS 4W39, MAINTAIN EGRESS
REMOVE AND REPLACE OPERATOR
LEVEL 4 4CW10 --- 7' - 6" 7' - 0" 1 3/4" 2 F EXISTING PTE --- EXISTING HM PTE --- --- --- N/A NO NO ANYTIME REMOVE AND REPLACE OPERATOR / MAINTAIN MOTION SENSOR IN THE PATH OF EGRESS
LEVEL 4 4S05 --- 3' - 0" 7' - 0" 1 3/4" 1 VV WD - LEAD
LINED
STE LEAD LINED
TO MATCH
DOOR
HM - LEAD
LINED
HM PTE 1/A6.01 6/A6.01 --- 28 YES NO ROUTINE WORK HOURS REPLACE DOOR AND FRAME ACCESS CONTROL ADD OPERATOR LEAD LINED DOOR / 4'-7", ENSURE LEAD LINER OVERLAPS DRY WALL.
LEVEL 4 4W39 SMOKE
BARRIER
7' - 0" 7' - 0" 1 3/4" 2 F EXISTING PTE --- EXISTING HM PTE --- --- --- 15 YES NO NIGHT OR WEEKEND AND NOT AT THE
SAME TIME AS 4CW07, MAINTAIN
EGRESS
REMOVE AND REPLACE OPERATOR
LEVEL 4 4W52 --- 3' - 0" 7' - 0" 1 3/4" 1 NV WD STE --- HM-001 HM PTE 1/A6.01 6/A6.01 --- 32 NO YES ROUTINE WORK HOURS NEW FRAME, DOOR AND HARDWARE
LEVEL 4 4W54 45 MIN. 4' - 0" 7' - 0" 1 3/4" 1 F HM PTE --- EXISTING HM PTE --- --- --- 31 NO YES ROUTINE WORK HOURS EXISTING FRAME NEW DOOR AND HARDWARE
LEVEL 5 5CS02 --- 5' - 7 5/8" 7' - 0" 1 3/4" 2 UNEVEN NV HM PTE --- HM-002 HM PTE 1/A6.01 6/A6.01 --- 33 NO NO NIGHT OR WEEKEND, MAINTAIN EGRESS REPLACE DOOR FRAME AND HARDWARE RECONNECT ACCESS CONTROL
LEVEL 5 5E03 45 MIN. 3' - 0" 7' - 0" 1 3/4" 1 F EXISTING STE --- EXISTING HM PTE --- --- --- 18 YES NO ANYTIME REMOVE AND REPLACE OPERATOR
LEVEL 6 6CW03 --- 3' - 8" 7' - 0" 1 3/4" 1 SG EXISTING PTE --- EXISTING HM PTE --- --- --- 18 YES NO MAINTAIN EGRESS REMOVE AND REPLACE OPERATOR
LEVEL 9 9ST02 90 MIN. 3' - 8" 7' - 0" 1 3/4" 1 NV EXISTING PTE CLEAR AND
RATED
EXISTING HM PTE 1/A6.01 6/A6.01 --- N/A NO NO MAINTAIN EGRESS REMOVE AND REPLACE FIRE RATED GLASS / 90 MIN.
LEVEL 9 9ST03 90 MIN. 3' - 8" 7' - 0" 1 3/4" 1 NV EXISTING PTE CLEAR AND
RATED
EXISTING HM PTE 3/A6.01 8/A6.01 --- N/A NO NO MAINTAIN EGRESS REMOVE AND REPLACE FIRE RATED GLASS / 90 MIN., ADD NEW SEALS
DOOR SCHEDULE - BUILDINGS 2, 7, AND 50
Level
DOOR
NUMBER FIRE RATING
PANEL
WIDTH
PANEL
HEIGHT
PANEL
THICKNESS
PANEL
COUNT PANEL TYPE
PANEL
MATERIAL
PANEL
FINISH
GLAZING
TYPE
FRAME
TYPE
FRAME
MATERIAL FRAME FINISH HEAD JAMB SILL
HARDWARE
GROUP
NEW
OPERATOR
NEW
PIV PHASING* NOT USED COMMENTS
BUILDING 2
LEVEL 1 1C03 45 MIN. 7' - 4" 7' - 0" 1 3/4" 2 NV EXISTING PTE --- EXISTING HM PTE --- --- --- N/A YES NO NIGHT OR WEEKEND, MAINTAIN EGRESS REMOVE AND REPLACE OPERATOR
LEVEL 1 103 45 MIN. 7' - 0" 7' - 0" 1 3/4" 2 F HM PTE --- HM-001 HM PTE 1/A6.01 6/A6.01 --- YES YES NIGHT OR WEEKEND, MAINTAIN EGRESS NEW DOOR, FRAME AND OPERATOR
LEVEL 1 113 --- 3' - 0" 7' - 0" 1 3/4" 1 NV EXISTING STE --- EXISTING HM PTE --- --- --- 18 YES NO NIGHT OR WEEKEND REMOVE AND REPLACE OPERATOR
LEVEL 1 113A --- 3' - 0" 7' - 0" 1 3/4" 1 FG WD STE --- EXISTING HM PTE --- --- --- 34 NO NO ANYTIME REPLACE EXISTING DOOR WITH NEW SOLID CORE DOOR WITH NO WINDOW
BUILDING 7
LEVEL 1 03-7 --- 3' - 0" 7' - 0" 1 3/4" 1 F HM PTE --- HM-001 HM PTE 4/A6.01 9/A6.01 --- 35 NO NO MAINTAIN EGRESS REPLACE EXISTING DOOR, FRAME AND HARDWARE
BUILDING 50
LEVEL 1 50C101 --- 7' - 6 1/4" 7' - 0" 1 3/4" 1 AL-FG ALUM ALUM --- AL-001 ALUM ALUM 2/A6.01 7/A6.01 --- - YES YES MAINTAIN EGRESS NEW ALUMINUM DOOR W/ OPERATORS ADD PIV AND ACCESS CONTROL
*All Phasing Must Be Coordinated With COR
*All Phasing Must Be Coordinated With COR
| Sheets |
| G0.00 - COVER SHEET |
| G0.01 - CAMPUS MAP |
| G1.00 - INFECTION CONTROL RISK ASSESSMENT |
| AD1.01 - DEMOLITION PLAN - BUILDING 1 - BASEMENT PLAN |
| AD1.02 - DEMOLITION PLAN - BUILDINGS 1 AND 50, FLOOR 1 PLAN |
| AD1.03 - DEMOLITION PLAN - BUILDINGS 1 AND 50, FLOOR 2 PLAN |
| AD1.05 - DEMOLITION PLAN - BUILDING 1, FLOOR 4 PLAN |
| AD1.06 - DEMOLITION PLAN - BUILDING 1, FLOOR 5 PLAN |
| AD1.07 - DEMOLITION PLAN - BUILDING 1, FLOOR 6 PLAN |
| AD1.08 - DEMOLITION PLAN - BUILDING 1, FLOOR 9 |
| AD1.09 - DEMOLITION PLAN - BUILDING 2, FLOOR 1 PLAN |
| AD1.10 - DEMOLITION PLAN - BUILDING 7 FLOOR PLANS |
| AD1.11 - DEMOLITION PLANS - ENLARGED |
| AD1.12 - DEMOLITION PLANS - ENLARGED |
| A1.01 - BUILDING 1 - BASEMENT PLAN |
| A1.02 - BUILDINGS 1 AND 50, FLOOR 1 PLAN |
| A1.03 - BUILDINGS 1 AND 50, FLOOR 2 PLAN |
| A1.05 - BUILDING 1, FLOOR 4 PLAN |
| A1.06 - BUILDING 1, FLOOR 5 PLAN |
| A1.07 - BUILDING 1, FLOOR 6 PLAN |
| A1.08 - BUILDING 1, FLOOR 9 PLAN |
| A1.09 - BUILDING 2, FLOOR 1 PLAN |
| A1.10 - BUILDING 7 FLOOR PLANS |
| A1.11 - NEW CONSTRUCTION PLANS - ENLARGED |
| A1.12 - NEW CONSTRUCTION PLANS - ENLARGED |
| A6.00 - DOOR SCHEDULES |
| A6.01 - DOOR ELEVATIONS AND DETAILS |
| Untitled |
| Untitled |