This document provides details on a draft solicitation for Depot Level Maintenance Support Services. The United States Navy is seeking these services for aircraft, engines, components and materials undergoing maintenance at Fleet Readiness Center Southwest in North Island, California. The anticipated contract type is a single-award Indefinite Delivery/Indefinite Quantity contract with cost-plus-fixed-fee and cost reimbursable CLINs. The period of performance is expected to be a five-year ordering period. The incumbent contractor is Aircraft Readiness Alliance, LLC under contract N68936-17-C-0081. Industry feedback on the draft solicitation is requested by December 22, 2021 prior to formal solicitation planned for the first quarter of fiscal year 2022, with contract award targeted for the first quarter of fiscal year 2023. This acquisition is being competed as a 100% 8(a) small business set-aside.

View the file

Other files

File Type Posted
DLM Attachment 5 - Level Of Effort.pdf PDF
OT-22-20017 - Ground Operation Procedures.pdf PDF
DLM Attachment 10 - CBA Lemoore - 2018-2022.pdf PDF
DLM Attachment L-3_Vol_2_PP-1_.xlsx XLSX spreadsheet
DLM Attachment 18 - Data Item Transmittal Form.docx DOCX document
DLM Attachment 2 - Trade Specialties.docx DOCX document
DLM Attachment 20 - Applicable Wage Determination.docx DOCX document
DLM Attachment 1 - Work Task Guidance.xls XLS spreadsheet
DLM Attachment 9 - CBA FRCSW Center Barrel NAS North Island 2018-2021.pdf PDF
DLM Attachment 17 - TASK ORDER CLOSEOUT.docx DOCX document
Exhibit A - CDRLs (1 Dec 2021).docx DOCX document
DLM Attachment 3 - Trade Skills Training Plans and Outlines.docx DOCX document
N68520-21-R-0007.docx DOCX document
DLM Attachment 12 - CBA - NI Miramar Pendelton.pdf PDF
DLM Attachment 13 - CBA Cannon AFB.pdf PDF
DLM Attachment L-5_Vol_4_ AFBL.xlsx XLSX spreadsheet
DLM Attachment L-4_Vol_4_CS-1.xls XLS spreadsheet
DLM Attachment 4 - Trade Specialty Functional Req.xlsx XLSX spreadsheet
DLM Attachment 11 - CBA Yuma 12-15-2017 to 12-14-2022.pdf PDF
DLM Attachment 14 - CBA FRCNW -Whidbey Island.pdf PDF
DLM Attachment 6 - Key Personnel.docx DOCX document
DLM Attachment 7 - Minimum Tool Box Requirements.xlsx XLSX spreadsheet
DLM Attachment L-1_Vol_1_ES_Tables.xlsx XLSX spreadsheet
DLM Attachment 19 - OCI List.docx DOCX document
DLM Attachment 8 - DD 254 Security Classification.pdf PDF
DLM Attachment L-2_Vol_2_PPQ.docx DOCX document
DLM Attachment 15 - CBA North Island F-18 Center Barrel.pdf PDF
DLM Attachment 16 - Contractor Surveillance Plan (CSP).doc DOC document
DLM pre-solicitation attendance list.pdf PDF
FRCSW DLM FY22 Industry QA responses (13 Jan 22).pdf PDF
FRC SW DLM Pre-Prop Conf Brief final.pptx PPTX presentation
DLM Attachment 8 - CBA - 2019 FRCSW Center Barrel CBA FE.pdf PDF
Exhibit A - CDRLs (1 Dec 2021).docx DOCX document
DLM Attachment L-3_Vol_2_PP-1_.xlsx XLSX spreadsheet
DLM Attachment 11 - Contractor Surveillance Plan (CSP).doc DOC document
DLM Attachment L-5_Vol_4_ AFBL.xlsx XLSX spreadsheet
DLM Attachment 3 - Trade Skills Training Plans and Outlines.docx DOCX document
DLM Attachment 7 - DD 254 Security Classification.pdf PDF
DLM Attachment L-2_Vol_2_PPQ.docx DOCX document
DLM Attachment 5 - Level Of Effort.xlsx XLSX spreadsheet
RFP Question Submittal Form - N68520-21-R-0007.xlsx XLSX spreadsheet
DLM Attachment 2 - Trade Specialties.docx DOCX document
DLM Attachment 4 - Trade Specialty Functional Req.xlsx XLSX spreadsheet
DLM Attachment 9 - CBA - North Island F-18 Center Barrel CBA 8-31-2018 to 8-31-2021.pdf PDF
DLM Attachment 15 - AWDs.pdf PDF
DLM Attachment 14 - OCI List.docx DOCX document
DLM Attachment L-4_Vol_4_CS-1.xls XLS spreadsheet
DLM Attachment 10 - CBA - Lemoore - 2018-2023.pdf PDF
draft - N68520-21-R-0007.docx DOCX document
DLM Attachment 1 - Work Task Guidance.xls XLS spreadsheet
Show 40 more

Latest 50 of 53 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Instructions **NOTE: This tab contains instructions for completing Tables ES-1 and ES-2** Instructions for the ES-1 Offeror Summary Table

Row 3 Fill in the Offeror's Name.

Column A List all entities (See Section L, Part A, Section 1. - General, Paragraph 4) who will be involved with performance or management of the requirements of this solicitation. Add rows as necessary.

Column B List the physical location of the entity.

Column C Provide the CAGE Codes/DUNS numbers associated with the entity that is proposing to perform the work for this solicitation.

Note: Past performance and corporate experience of any principal entity with multiple CAGE codes/DUNS will be considered for the same physical location if the respective entity has distinct roles and responsibilities. If multiple CAGE codes/DUNS for the same physical location will be involved with performance or management of the requirements of this solicitation, ensure they are identified on separate lines in Table ES-1 (Offeror Summary).

Column D Provide brief work description and Program Role and Responsibility for each entity identified. If there is more than one CAGE Code/DUNs identified for an entity, ensure that a separate work descriptions/Role and Responsibility is provided for each.

Note: Within Volume 1, provide a definition of the legal relationship between the entities if it is other than a Prime/subcontractor relationship.

Column EProvide the percentage of total proposed cost/price being careful to include all entities so that the total proposed price adds up to 100% of the contract price. If there are current and previous CAGE codes/DUNS as a result of a corporate acquisition, reorganization, merger, or other administrative reason, that refer to the same division in the same physical location for where the work is being performed or from where the work is being directed place N/A in this column and ensure the proposed price/work for this effort is covered under the current CAGE codes/DUNs.
Column FIndicate if the entity is considered a "Principal Entity" as defined in Section L, Part A, Section 1. - General, Paragraph 4.
Instructions for the ES-2 Relevant Contract Summary Table
Row 3Fill in the Offeror's Name.

Column A List the names of the Principal Entities proposing for this solicitation. The Principal entities are defined in Section L, Part A, Section 1. - General, Paragraph 4. Add rows as necessary.

Column B Provide a unique contract reference number for all contracts proposed as relevant for Past Performance and/or Corporate Experience. Utilize P1...Pn for the prime or Joint Venture Team proposing for this solicitation (regardless if the referenced contract was performed as a Prime or subcontractor),and utilize T1...Tn for each JV team member proposed as part of a Joint Venture for this solicitation (only include contract references labeled as T1…Tn where the same Joint Venture Team members previously performed as a Joint Venture Team).

Note (1): Group the references by each entity where entity is defined as the Prime or JV Team Member.

Note (2): 'n' is defined as the total number of contracts referenced for each type of entity.

Note (3): The contract references shall be numbered consecutively across all JV Team Members (as illustrated in the example tab) so that they are unique (e.g., there is only one P1, T1).

Column C Provide the Contract Number (e.g., N00019-12-R-0001) for the referenced contract.

Column D Include the Contract Type (CPIF etc) for the referenced contract.

Column E Include the Contract Name for the referenced contract.

Column F As part of the Initial Proposal submittal, provide a description of any changes or additions from the information that was submitted with the "Early Past Performance Information Submittal". In addition, if there were any deletions, please provide a brief narrative, in Volume 1, following Table ES-2.

Note: Ensure that contracts identified in Past Performance are numbered consistently with those identified in Corporate Experience (i.e. P1 in Past Performance is the same as P1 in Corporate Experience, etc.). The references designated in Table ES-2 Relevant Contract Summary, shall be used in completing Volume 2 Table PP-1 Past Performance Contract Data and Volume 3 (Technical) Corporate Experience Element evaluation, and should be consistent throughout.

Executive Summary

&P &"Times New Roman,Regular"&12Instructions

ES-1 Offeror Summary ES-1 Offeror Summary Table

Offeror:
Entity NamePhysical Location of EntityCAGE Codes/DUNSRoles and Responsibilities with Work Description% Total Proposed Cost/PricePrincipal Entity Yes or No?

Total Proposed cost/price (must add up to 100%) 100%

&KFF0000L-1 Table ES-1 Offeror Summary &KFF0000Solicitation #:

&P

ES-2 Relevant Contract Summary ES-2 Relevant Contract Summary Table

Offeror:
Contractor NameContract
ReferenceContract NumberContract TypeContract Title*Description of Changes/Additions from Early Information
Prime or Joint Venture CompanyP1
P2
P3
JV team member A (where applicable)T1
T2
T3
T4

JV team member N (where applicable) T5

* Contracts deleted should be identified in a narrative paragraph following Table ES-2.

&KFF0000L-1 Table ES-2 Relevant Contract Summary &KFF0000Solicitation #:

&P

Relevant Contract Example Example ES-2 Relevant Contract Summary Table

Offeror:
Contractor NameContract
ReferenceContract NumberContract TypeContract Title*Description of Changes/Additions from Early Information
Prime or Joint Venture CompanyP1XXXXXX-XX-X-XXXXFFP
P2XXXXXX-XX-X-XXXXCPFF
P3XXXXXX-XX-X-XXXXFFP
JV team member A (where applicable)T1XXXXXX-XX-X-XXXXFFP
T2XXXXXX-XX-X-XXXXFPI
T3XXXXXX-XX-X-XXXXFFP
T4XXXXXX-XX-X-XXXXCPFF

JV team member N (where applicable) T5 XXXXXX-XX-X-XXXX FFP

* Contracts deleted should be identified in a narrative paragraph following Table ES-2.

&KFF0000L-1 Table ES-2 Relevant Contract Summary &KFF0000Solicitation #

&P &"Times New Roman,Regular"&12EXAMPLE