This document is a Task Assignment Notification Form (DC054B) under DEP Contract No. HW557, issued by the Florida Department of Environmental Protection (FDEP). The contract involves Arcadis U.S., Inc. as the contractor, with William Vogelsong serving as the Contractor Representative and Theresa C. Pepe as the DEP Contract Manager. The work is being performed at the former Cotney's All Pro Cleaners facility (ERIC_4704) located at 15305 Amberly Drive, Tampa, Hillsborough County, Florida. The task assignment was executed on October 2, 2020, with digital signatures from all authorized parties including Jennifer Farrell (Contractual Authority) and Gus Suarez, P.E. (Contractor Representative).
The task assignment provides $67,449.69 in fixed-price compensation for a site assessment at the drycleaning facility to be completed in accordance with an approved Work Plan. Work is divided into three subtasks: Project Management ($3,464.73), Site Assessment ($53,650.08), and Site Assessment Report/IDW Manifests ($10,334.88), with a final deliverable due date of February 26, 2021. The assessment includes soil and groundwater investigation, Modified Active Gas Sampling (MAGS), monitoring well installation and sampling, professional surveying, utility location, sewer line video inspection, laboratory analytical services, and field expenses. Subcontractors selected through competitive bidding include Groundwater Protection (drilling at $12,029.00), ALF (mobile laboratory at $4,250.00), Landmark Surveying ($1,000.00), GeoView (utility locate and sewer video at $1,750.00), and various analytical and laboratory services. Invoicing occurs upon FDEP approval of fieldwork activities and the final Site Assessment Report with Investigative Derived Waste (IDW) manifests.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEP CONTRACT NO.
Task Assignment #: Module #: Grant #:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
DEP Site #:
Site Name:
Address(Street, City, County):
Phase:
Task Description [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverables:
Final Deliverable Due Date:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
FIXED FEE
RETAINAGE:
TOTAL TASK ASSIGNMENT VALUE: $0.00
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93) Section Representative ________
TASK ASSIGNMENT NOTIFICATION FORM
COST PLUS FIXED FEE
COST REIMBURSEMENT
FIXED PRICE FEE SCHEDULE
Period of Performance:
Execution of Task Assignment through:
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
WCP TAFORM 01_18
HW557
D000 N/ADC054B
Arcadis U.S., Inc.
William Vogelsong
(850) 245-8705Theresa C. Pepe
ERIC_4704
Cotney's All Pro Cleaners Inc.
15305 Amberley Dr, Tampa, Hillsborough County
Assessment
Arcadis will complete a Site Assessment according to the approved Work Plan.
Site Assessment Report/IDW manifests
02/26/2021
03/26/2021
$ 67,449.69 $ 0.00 $ 0.00 $ 0.00
$ 0.00
Theresa C Pepe Digitally signed by Theresa C Pepe Date: 2020.10.02 07:58:55 -04'00'
Theresa C Pepe Digitally signed by Theresa C Pepe Date: 2020.10.02 07:59:07 -04'00'
Digitally signed by Jennifer Farrell Date: 2020.10.02 08:12:08 -04'00'
Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.
Date: 2020.10.02 13:11:27 -04'00'
$ 67,449.69
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number: HW557 Task Assignment #: DC054B
Deliverables:
Deliverable Deliverable Due Date
Completion of Fieldwork Activities 31-Dec-20
Site Assessment Report/IDW manifests 26-Feb-21
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
FDEP approval of Fieldwork Activities $53,650.08
FDEP approval of Site Assessment Report/IDW manifests/Project Management $13,799.61
TOTAL COST $67,449.69
BWC TAFORM 01/18
FDEP COST ESTIMATE
Contractor: Arcadis U.S., Inc.
Date: 6/26/2020
Task #: DC054B SubTask 1 Project Management
Site: Cotney's All Pro Cleaners SubTask 2 Site Assessment
Activity/Phase: Assessment SubTask 3 Reporting
Project Manager: Bill Vogelsong SubTask 4
SubTask 5
Totals 1 2 3 4 5
Labor Rate Category Staff Member
$81.47 Project Manager Vogelsong, William (WDV) 15 14.5
$95.33 Principal Engineer Bedessem, Jim (JMB) 0 0 0 0 0
$81.47 Principal Scientist Vogelsong, William (WDV) 12 4 8 0 0$77.95 Principal Engineer Suarez, Gus (GS) 0 0 0 0 0
$59.89 Principal Scientist Burke, Brian (BRB) 35 18 17 0 0
$59.46 Principal Engineer Perella, John (JFP) 8 4 4 0 0$50.00 Senior Scientist O'Sullivan, Michael (MOS) 0 0 0 0 0
$39.34 Staff Engineer Hanna, Chad (CMH) 12 12 0 0 0$38.24 Staff Scientist Riley, Joel (JR) 0 0 0 0 0
$27.60 Scientist Brooks, Eric (EAB) 119 91 28 0 0$26.45 Scientist Brutscher, Katherine (KEB) 0 0 0 0 0
$32.59 Technician Welch, David (DJW) 34 34 0 0 0
$39.67 Drafter/Designer Oliva, Brian (BO) 12 0 12 0 0$30.99 Drafter/Designer Richards, Jim (JR) 0 0 0 0 0
$29.91 Project Assistant McLemore, Michele (MMc) 18 6 12 0 0
$0.00 0 0 0 0 0
$0.00 0 0 0 0 0
Total Hours 265 15 169 81 0 0
Direct Labor $10,606.98 $1,178.55 $5,912.94 $3,515.49 $0.00 $0.00
Overhead 57.95% $8,429.03 $936.56 $4,698.82 $2,793.65 $0.00 $0.00
Gen & Admin 21.29% $4,891.24 $543.47 $2,726.66 $1,621.11 $0.00 $0.00
Fringe 37.13% $3,938.37 $437.60 $2,195.47 $1,305.30 $0.00 $0.00
Total Labor $27,865.62 $3,096.18 $15,533.89 $9,235.55 $0.00 $0.00
Other Direct Costs $530.35 $58.93 $295.65 $175.77 $0.00 $0.00
Travel
Vehicle Rental $779.00 $779.00 $0.00 $0.00 $0.00
Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00
Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00
Total Travel $779.00 $779.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement)
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00
Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00
Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement)
Drillpro Drilling (Conventional) $12,029.00 $12,029.00 $0.00 $0.00 $0.00
Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00
ALF Mobile Laboratory $4,250.00 $4,250.00 $0.00 $0.00 $0.00
Landmark Surveying $1,000.00 $1,000.00 $0.00 $0.00 $0.00
Clark Env IDW $600.00 $600.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00
GeoView Utility Locate / GPR Survey $1,750.00 $1,750.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $19,629.00 $19,629.00 $0.00 $0.00 $0.00
Handling Fee $1,962.90 $1,962.90 $0.00 $0.00 $0.00
Total Subcontractor Cost $21,591.90 $21,591.90 $0.00 $0.00 $0.00
Laboratory
TestAmerica Analytical Costs $8,806.00 $8,806.00 $0.00 $0.00 $0.00
Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00
Sample Shipping $334.00 $334.00 $0.00 $0.00 $0.00
Total Laboratory $9,140.00 $9,140.00 $0.00 $0.00 $0.00
Field Expenses
Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00
Expendables $227.50 $227.50 $0.00 $0.00 $0.00
Equipment (Drilling related) $1,137.85 $1,137.85 $0.00 $0.00 $0.00
Equipment (Analytical related) $1,117.10 $1,117.10 $0.00 $0.00 $0.00
Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (Other - MAGS, recon) $2,273.80 $2,273.80 $0.00 $0.00 $0.00
Total Field Expenses $4,756.25 $4,756.25 $0.00 $0.00 $0.00
Subtotal $64,663.12 $3,155.11 $52,096.69 $9,411.32 $0.00 $0.00
Completion Fee $2,786.57 $309.62 $1,553.39 $923.56 $0.00 $0.00
Total Estimated Cost $67,449.69 $3,464.73 $53,650.08 $10,334.88 $0.00 $0.00
REV: 02/03 CEF ARCADIS Page 1
SITE: Cotney's All Pro Cleaners
SUBTASK 2: Site Assessment
DATE: 6/26/20
LABOR
Category/Staff Work Description Hours
Site Owner Meeting, Utility Locate, Stake Locations, Field Kick-off Principal Sci (BRB) Meet site owners, mark locations, field kick-off / property mgr contacts & cood (4 hrs); subs contracting/coord (4 hrs) 8
Soil & GW Investigation, MAGs Principal Sci (WDV) Access/communications; field prep/H&S; PG oversight/review of field staff and SA results; FDEP telecons 4
Principal Sci (BRB) Field guidance and updates, plot/share/discuss field results; suggestions/recommendations with FDEP 8
Principal Eng (JP) PE review of field MAGs results/biogeo - recommendations 4
Staff Engineer (CH) MAGS field implementation, sample collection, communications 12
Staff Sci (EB) Prep (4), Sewer video (5), VP soil/GW oversight & sample collection (5 days x 12 hours = 60 hrs), 69
Technician (DJW) Soil Sampling assistance (18 hrs), MAGS well install and MAGS Tesing (16 Hrs) 34
Project Assistant / MMc Sample tracking / database mgmt; organize filed notes/field figures 6
Monitor Well Sampling & Survey Oversight Principal Sci (BRB) Field guidance and contractor coordination 2
Staff Sci (EB) Prep (2), Sample 10 wells, WLs, oversight of survey crew (2 days x 10 hours = 20 hrs), 22
TOTAL LABOR: 169
TRAVEL
Vehicle Type Rate Unit Usage Totals
Automobile BB $68.00 Per Day 1 $68.00
Van/Truck CH/DJW-MAGS, EB-GW, Survey $97.00 Per Day 3 $291.00
Van/Truck EB- Assessment $420.00 Per Week 1 $420.00
Total Vehicle: $779.00
Meals Category/Staff Rate Unit Usage Totals
$36.00 Per Day 0 $0.00
$36.00 Per Day 0 $0.00
Hotel Category/Staff Rate Unit Usage Totals
$90.00 Per Day 0 $0.00
$90.00 Per Day 0 $0.00
Total Meal/Hotel: $0.00
TOTAL TRAVEL: $779.00
SUBCONTRACTOR COSTS
Equipment Procurement Name Equipment Rate Units Usage Totals
0 $0.00
Total Equip.: $0.00
Services Procurement Name Purpose Rate Units Usage Totals
Drillpro Direct-push services $12,029.00 Lump Sum 1 $12,029.00 Landmark Survey $1,000.00 Lump Sum 1 $1,000.00
Clark IDW $150.00 Drum 4 $600.00
ALF On-site Mobile Laboratory analysis $4,250.00 Lump Sum 1 $4,250.00
GeoView GPR and Sewer Inspection Video $1,750.00 Lump Sum 1 $1,750.00
Total Services: $19,629.00
TOTAL SUB: $19,629.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
VOC (Halocarbons Only) 8260 Aqueous $66.00 1.00 17 $1,122.00
VOC (Halocarbons Only) 8260 Soil/Sediment $66.00 1.00 72 $4,752.00
VOC (Halocarbons SPLP) 8260 Soil/Sediment $40.00 1.00 10 $400.00
Biogeochem (TOC, nitrate, sulfate, total iron, CO2, M/E/E) Aqueous $400.00 1.00 3 $1,200.00
VOC (Halocarbons Only)- IDW 8260C Aqueous/Non $66.00 1.00 1 $66.00
VOC (Halocarbons Only)- IDW 8260C Soil $66.00 1.00 1 $66.00
VOC Soil Vapor TO-15 Aqueous/Non $200.00 1.00 6 $1,200.00
TAT 24-hr=100% (2.0) 3-day=50% (1.5) 1-week=15% (1.15) Total Lab: $8,806.00
Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $104.00 Per Cooler 2 $208.00
Shipping - Small (0 to 25 lbs.) --- --- $63.00 Per cooler 2 $126.00
Total Shipping: $334.00
TOTAL LAB: $9,140.00
FIELD EXPENSES
Personal Protection Item Rate Unit Usage TotalsPPE Level D $28.00 Per Man Day 0 $0.00
Total PPE: $0.00
Equipment Item Rate Unit Usage Totals
Expendables Miscellaneous Expendables $32.50 Per Day 7 $227.50
Total Expendables: $227.50
Equipment ItemsPID/FID Combo or FID $106.70 Per Day 0 $0.00
Vacuum Gauges (low, med & high) $19.40 Per Day 1 $19.40
Water Level: Electric Tape $19.40 Per Day 1 $19.40Water Level: Electric Tape $77.60 Per Week 0 $0.00
Encore Sampler $8.75 Each 72 $630.00Survey Station transit/rod/level/tape $41.75 Per Day 0 $0.00
Tubing, Poly/HDPE $0.25 Per Foot 200 $50.00
Tubing, Silicon 3/16x3/8 $2.00 Per Foot 10 $20.00Miscellaneous Expendables $32.50 Per Day 0 $0.00
PID (ppbRae) $87.30 Per Day 3 $261.9055-gallon Drum $58.20 Each 0 $0.00Regenerative Blower $92.15 Per Day 0 $0.00
MAGS Rental Trailer (EWE) $1,750.00 Each 1 $1,750.00
Total Equipment Items: $2,750.70
Equipment Kits Monitor Well Installation Kit $184.30 Day 2 $368.60
Shallow Groundwater Sampling Kit $208.55 Day 2 $417.10
Soil Assessment Kit $139.70 Day 2 $279.40
Soil Vapor Sampling Kit $213.40 Day 1 $213.40
Soil Sampling Kit (through concrete) $208.55 Day 1 $208.55
Construction/O&M/Pilot Test Kit $291.00 Day 1 $291.00
Total Equipment Kits: $1,778.05
TOTAL EQUIPMENT: $4,756.25
SITE: Cotney's All Pro Cleaners
SUBTASK 3: Reporting
DATE: 6/26/20
LABOR
Category/Staff Work Description Hours
SAR
Principal / BV PG review/certification of draft/final SAR; communication of results/risk-based mngt options with FDEP 8
Project Engineer / JP PE review of SAR; remedial characterization data/preliminary remedial options evaluation 4
Principal Sci / BRB SAR review, technical input (8 hrs); SAR figures/graphs generation (2 hrs); SAR tables (2 hrs); IDW mgmt (5 hrs) 17
Staff Sci / EB SAR writing (16 hrs); SAR figures/graphs generation (6 hrs); SAR tables (6 hrs) 28
Designer - Database Mgr / BO SAR figures/graphs generation (8 hrs); data mgmt, import to CAD (4 hrs) 12
Project Assistant / MMc Process field notes, sample tracking, database entry, report assembly, reprt submittal 12
TOTAL LABOR: 81
TRAVEL
Vehicle Type Rate Unit Usage Totals
Automobile $68.00 Per Day 0 $0.00
Van/Truck $97.00 Per Day 0 $0.00
Van/Truck $420.00 Per Week 0 $0.00
Total Vehicle: $0.00
Meals Category/Staff Rate Unit Usage Totals
$36.00 Per Day 0 $0.00
$36.00 Per Day 0 $0.00
Hotel Category/Staff Rate Unit Usage Totals
$90.00 Per Day 0 $0.00
$90.00 Per Day 0 $0.00
Total Meal/Hotel: $0.00
TOTAL TRAVEL: $0.00
SUBCONTRACTOR COSTS
Equipment Procurement Name Equipment Rate Units Usage Totals
0 $0.00
Total Equip.: $0.00
Services Procurement Name Purpose Rate Units Usage TotalsNAME OF COMPANY Direct-push services $0.00 Unit pricing 0 $0.00
Total Services: $0.00
TOTAL SUB: $0.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples TotalsVOC (Halocarbons Only) 8260C Aqueous/Non $66.00 1.00 0 $0.00
Other 1.00 0 $0.00
TAT 24-hr=100% (2.0) 3-day=50% (1.5) 1-week=15% (1.15) Total Lab: $0.00
Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $104.00 Per Cooler 0 $0.00
Shipping - Small (0 to 25 lbs.) --- --- $63.00 Per cooler 0 $0.00
Total Shipping: $0.00
TOTAL LAB: $0.00
FIELD EXPENSES
Personal Protection Item Rate Unit Usage TotalsPPE Level D $28.00 Per Man Day 0 $0.00PPE Level C $110.00 Per Man Day 0 $0.00
Total PPE: $0.00
Equipment Item Rate Unit Usage Totals
Expendables Miscellaneous Expendables $32.50 Per Day 0 $0.00
Total Expendables: $0.00 Equipment Items
Total Equipment Items: $0.00
Equipment KitsSite Reconnaissance Kit $81.48 Day 0 $0.00
Total Equipment Kits: $0.00
TOTAL EQUIPMENT: $0.00
Florida Department of
Memorandum Environmental Protection
“Protect, Conserve and Manage Florida’s Environment and Natural Resources”
Printed on recycled paper.
TO: Negotiation File Cotney’s All Pro Cleaners Inc.
Facility ID No. 29-9500710; ERIC_4704 Tampa, Hillsborough County
FROM: Theresa C. Pepe, Project Manager
DATE: October 1, 2020
SUBJECT: Task Assignment DC054B (HW557)
This Task Assignment is for the Site Assessment at the former Cotney’s All Pro Cleaners site.
The fieldwork will be completed in approximately seven days and a Site Assessment Report (SAR) will be submitted as the final deliverable. All work will be performed in accordance with the approved work plan.
The final task assignment total is $67,449.69. Arcadis may invoice according to the attached schedule.
Specific negotiated subtasks are as follows:
Subtask 1: Project Management Project Management is automatically calculated as a percentage of total labor.
Subtask 2: Site Assessment This subtask provides funds for soil, vapor and groundwater screening and monitor well installation at the facility. FDEP’s geologist approved sampling locations and the overall approach to the assessment presented in the updated August 2020 Work Plan.
Landmark will provide a professional site survey of all sampling locations.
Geoview will provide a GPR survey/Sewer camera video based on their low bid of three bids solicited. One subcontractor could not provide the sewer camera.
Groundwater Protection was selected as the drilling subcontractor based on their low bid of three bids solicited. ALF was chosen as the mobile lab based on their low bid of two bids solicited. A third mobile lab could not be located in Florida.
Subtask 3: Site Assessment Report (SAR) All activities and analytical results obtained during site assessment work will be submitted to FDEP as a written report. This report will include appropriate figures, graphs, data tables, etc.
Additionally, Arcadis will provide electronic deliverables in the approved FDEP format. IDW manifests will also be provided to FDEP as part of the final deliverable.
Initial Site Assessment Work Plan
Arcadis .com \\arcadis-us.com\officedata\Tampa-FL\ENV\TF\FDEP Drycleaners\FDEP Drycleaner Program\Cotneys\Cotney's_ISA_WP_06192020 Final_Rev1_08.2020_.docx 5 water and sanitary sewer collection for the Site and that no septic systems currently exist. Natural gas, telephone, and electric is also supplied to the Site. No onsite private supply wells were observed. The current Site layout is provided on Figure 3.
The location of the 1998 soil sample remains unpaved near the former boiler room. The location of the former drycleaning machine was apparent based on the floor markings. Floor drains were present in the bathroom and just outside the bathroom to the northeast. A copy of the completed Site Visit Checklist, current Site photographs, and survey received from the property owner representative are presented in Appendix F.
5 INITIAL SITE ASSESSMENT WORK PLAN
A flexible assessment approach will be used to create a site-specific unsaturated soil and groundwater database capable of determining the absence/presence and extent of chlorinated drycleaning solvents above soil and groundwater CTLs. In addition, potential risks and exposure pathways will be identified and a preliminary recommendations and design provided for remedial action, if justified. The proposed assessment activities will be completed in accordance with FDEP’s Standard Operating Procedures (SOP) (001/01), the site-specific HASP, FDEP’s Considerations for Assessment of Drycleaning Solvent Contaminated Sites (FDEP, 2002), and Conducting Contamination Assessment Work at Drycleaning Sites (SCRD, 2010).
Based on the reported historical PCE contamination in the shallow soil near the outside of the southwest corner of the building and presumed shallow water (~5 ft bg) based on the adjacent wetlands, multiple assessment methodologies are proposed. Unsaturated soil assessment will be completed by the installation of soil borings to two feet into the water table, soil field screening using a PID capable of detecting to parts per billion (ppb), commonly referred to as a ppbRAE®, soil sampling in conjunction with field screening analysis utilizing a National Environmental Laboratory Accreditation Program (NELAP)-accredited fixed base laboratory; and Modified Active Soil Gas Survey (MAGS) methodology. Assessment of the groundwater will be completed utilizing vertical profiling, direct-push technology (DPT) in conjunction with field analysis utilizing the NELAP-accredited mobile laboratory, microwell installations, sampling/analysis of microwells for fixed-based laboratory analysis of volatile organic halocarbons (VOH);
surveying of elevation of wells/water level measurements to confirm groundwater flow direction, and biogeochemical characterization of Site groundwater. Site assessment methods and techniques are described in detail below.
5.1 Site Preparation, Utility Locate, and Sewer Line Scan
Arcadis will contact the current Site operator and current property owner representative to share proposed sampling locations and advise schedule/notification requirements prior to completing field work.
Arcadis will then conduct a Site visit to oversee a subsurface private utility locate at the Site. The purpose of the utility locate will be to establish/confirm the suspected locations of underground utilities (Sunshine State One Call will initially locate utilities on and surrounding the Site).
At the commencement of field activities Arcadis will contract with a vendor to video scan the sewer lateral beginning at the southwestern corner of the facility to the northeast connection with the main shopping plaza sewer lateral. The intent of the scan is to locate potential integrity issues in the sewer pipe where
\\arcadis-us.com\officedata\Tampa-FL\ENV\TF\FDEP Drycleaners\FDEP Drycleaner Program\Cotneys\Cotney's_ISA_WP_06192020 Final_Rev1_08.2020_.docx 6 drycleaning solvents may have historically been released to the subsurface. Locations of observed deficiencies will be targeted for further soil/groundwater assessment if warranted.
5.2 Soil Assessment and Sub-Slab Soil-Gas Sampling
5.2.1 Unsaturated Soil Assessment
One continuous soil boring (SB001) will be installed to a depth of approximately 40 ft bg, or into the top of the confining clay layer, to characterize lithology and for field screening of the unsaturated zone for synthetic organic vapors. Lithologic log of the general geology at the Site will be developed from the soil samples collected from this soil boring. Soil samples from each boring will be described by an on-Site Arcadis geologist.
To confirm if past drycleaning operations at the Site had an adverse impact to unsaturated soil quality conditions, 12 soil borings (SB001-SB012) for collection of soil samples are proposed for installation at the locations shown on Figure 4. The initial sample location will be placed in vicinity of the confirmed PCE release (former C.C. – 2B sample collected from two feet below land surface outside the rear of the facility, next to the boiler room). Additional boring/sample locations will be placed inside the building, outside the building, former boiler room, near the storm sewer grate, and dumpster. The field results from these initial sample locations will be used to direct/select additional sample locations, if necessary.
The soil borings will be installed using hand auger and/or DPT. A concrete coring machine will be used to bore through the concrete floor inside the building to access the underlying soils. Soil samples will be collected immediately below the asphalt/concrete surface cover and at one-foot depth intervals to a depth of one foot into the water table (estimate 6 ft bg – water table assumed to be approximately 5 ft bg). Soil samples designated for field-testing (up to 6 samples/boring x 12 initial boring locations or a total of up to 72 soil samples) will be transferred to mason jars, covered with aluminum foil and screened with a ppbRAE equipped with a photo-ionization detector to determine if the soils contain the presence of synthetic organic vapors. All 72 soil samples will be collected and submitted to a fixed-based laboratory for analysis of VOHs by EPA Method 8260. In addition, split samples from all soil borings will be collected and placed on hold for Synthetic Precipitation Leaching Procedure (SPLP) analysis. After receiving the initial results, the laboratory will be instructed to analyze target SPLP samples as necessary (assumes 10 analyzed). Following the sampling, the boreholes will be sealed with cement grout or converted to a well (MAGS or microwell) as described below.
5.2.2 Modified Active Gas Sampling
MAGS is proposed for completion inside and outside the building. MAGS will be completed in general agreement with the Modified Active Gas Sampling Manual, dated October 12, 2004. Six MAGS wells (MAG01 – MAG06), constructed of 2-inch diameter PVC with 0.010-inch slotted screen set from 0.5 to 5 ft bg, will be installed using a hand auger. In addition, the concrete slab inside the building appears to provide adequate surface cover seal. Final MAGS well construction will be field determined. One vapor sample will be collected from each MAGS well for analysis of VOHs by EPA Test Method TO-15.
Proposed MAGS well layout locations are depicted on Figure 4.
\\arcadis-us.com\officedata\Tampa-FL\ENV\TF\FDEP Drycleaners\FDEP Drycleaner Program\Cotneys\Cotney's_ISA_WP_06192020 Final_Rev1_08.2020_.docx 7
5.3 Groundwater Assessment
5.3.1 Groundwater Vertical Profiling
Groundwater assessment will be conducted utilizing vertical profiling (VP) by a DPT drill rig and portable gas chromatograph (mobile laboratory) screening of water samples for VOHs. Initially, eight VP locations (VP001 – VP008) are proposed at or near reported and suspected source areas and downgradient as shown on Figure 5. VP assessment will be conducted using an “inside – out” strategy by beginning at the historical on-Site “hot spot” soil sample location.
Assuming the water table will be encountered at approximately 5 ft bg, samples starting at the water table and at 10-ft depth intervals using a 4-ft long screen sampler to a total depth of the confining unit, expected to be no deeper than 30 ft bg. The sample intervals are anticipated to be approximately 5-9, 15- 19, and 25-29 ft bg. Lithologic information from Soil Boring SB001 will be used to determine exact sample intervals. Each VP water sample will be screened by the mobile laboratory (total 24 groundwater samples
– 3 samples/VP x 8 VPs) for on-Site VOH analysis. Termination depths of VPs will be based upon sample results (two consecutive depth interval samples that indicate VOHs are below GCTLs) or contact with an underlying confining layer. Five samples will be submitted to a fixed-based laboratory for confirmatory analysis of VOHs by EPA Method 8260. Following sampling, each vertical profile borehole will be sealed with cement grout or completed with a microwell as summarized below.
5.3.2 Microwell Installation and Sampling
Arcadis will install microwells at select locations based on VP groundwater results to provide permanent groundwater sample/monitoring locations. For purposes of this work plan, it has been assumed that 12 one-inch diameter microwells (MW001 – MW012) will be installed to help delineate vertical and lateral extents of solvent-impacted groundwater. Up to two shallow wells (MW001 and MW002) will be installed using a hand auger inside the facility by hand. An additional five shallow microwells (MW003 through MW007) will be installed with 10-ft of 0.010-inch slot pre-pack screen, between 2-12 ft bg to help delineate the horizontal extent of the shallow plume. Also, five deep (MW008 through MW012) microwells will be installed with 5-ft of 0.010-inch slot pre-pack screens at the base of the surficial aquifer, between 25-30 ft bg to delineate the vertical extent of the plume. Final well locations, dimensions, including depth, screen interval and diameter will be determined based upon VP results and groundwater elevations encountered during assessment activities; however, the initial conceptual well locations are presented on Figure 5.
Arcadis will sample the 12 newly installed microwells for VOHs. Additionally, groundwater samples for biogeochemical characterization of groundwater will be collected from three wells (upgradient, source area, and leading edge of plume) and analyzed by a fixed-based lab (Florida Testing Services, Inc.) for total organic carbon, nitrate, sulfate, sulfide, total iron, ferrous iron, carbon dioxide, methane, ethane, and ethene; assuming detection of solvent contamination above GCTLs.
5.4 Well Location/Elevation Survey and Area Reconnaissance
Well survey latitude, longitude and top of casing elevations to the nearest 0.01 ft-NGVD will be collected by a licensed professional surveyor from the newly-installed microwells to determine current groundwater
\\arcadis-us.com\officedata\Tampa-FL\ENV\TF\FDEP Drycleaners\FDEP Drycleaner Program\Cotneys\Cotney's_ISA_WP_06192020 Final_Rev1_08.2020_.docx 8 flow direction, including horizontal and vertical gradients. Soil boring, MAGS wells, and VP locations will be surveyed for latitude, longitude, and ground surface elevations to the nearest 0.01-ft NGVD.
Arcadis will attempt to identify any changes in reported current land use, potential future land use, and potential exposure pathways (direct and indirect) on or near the Site. Additionally, Arcadis will perform a windshield survey of public and private supply wells within one-quarter mile of the Site.
6 SITE ASSESSMENT REPORT
A draft SAR that describes the results of the proposed site assessment tasks described herein will be delivered to FDEP within 60 days of completion of the field work. The SAR will contain tables and figures summarizing the results of assessment activities and include conclusions and recommendations based upon findings. A draft SAR will be submitted to FDEP for review and comment. A final SAR will be submitted to FDEP within a few days of receipt of FDEP comments.
7 INVESTIGATIVE DERIVED WASTE
Investigative derived wastes (IDW - drill cuttings and purge water) generated during site assessment activities will be drummed, labeled and temporarily staged on-Site in Department of Transportation (DOT)-approved, 55-gallon steel drums. Arcadis will coordinate with a waste disposal contractor for non-hazardous disposal of the IDW and provide copies of final disposal manifests to FDEP.
8 QUALITY ASSURANCE & QUALITY CONTROL
All fieldwork will be performed in accordance with FDEP’s SOP (001/01) and the site-specific HASP included under separate cover. Additionally, sample analyses will be performed by NELAP-certified laboratories to method practical quantitation limits. Appropriate QA/QC samples will be collected during the assessment.
9 PROJECT SCHEDULE AND COST
Cost estimate/level of effort (CEF-LOE) worksheets and subcontractor bid copies for the implementation of this ISAWP are provided separately. The proposed resource loaded schedule for the site assessment and SAR document package, is presented in Appendix G.
10 REFERENCES
FDEP. 1998. Site Assessment Work Plan Development Task List. July 1998.
FDEP. 2017. Considerations for Assessment of Drycleaning Solvent Contaminated Sites. Tallahassee:
Bureau of Waste Cleanup. September.
Ryder, Paul D., USGS. 1985. The Hydrology of The Floridan Aquifer System in West-Central Florida.
Earth Systems, Inc. 2001. Supplemental Site Assessment Report, Amerada Hess Station No. 09418.
Subcontractor Bid Summary
Cotney’s Cleaners
Driller Quotes:
Groundwater Protection $12,029.00 (Drillpro)
Preferred Drilling Solutions $12,075.00
Earth Tech $17,060.00
Mobile Lab Quotes:
ALF $4,250.00
Pace $6,150.00
Utility Locate:
Site Lines $1,100.00 (no sewer video)
GeoView $1,750.00
GPRS $2,300.00
Surveying:
Landmark $1,000.00
IDW:
Clark $150.00 per drum
Sonic Auger DPT Horizontal Directional Drilling
DATE: 6/23/2020
ESTIMATE #: 620078
Project Description:
3 Days of DPT Soil Borings/GW Sampling (Client Requested)
2 Days of DPT Well Installation (Client Requested)
ID QTY Unit Rate TOTAL
1 1 ls 500.00$ 500.00$
2 4 night 200.00$ 800.00$
3 Daily Rate: DPT Rig and Crew 5 day 1,450.00$ 7,250.00$
4 GW Sampling Tubing (Standard-1,000' Roll) 2 each 100.00$ 200.00$
5 Materials: 1" Well Installation 260 foot 3.00$ 780.00$
6 Materials: (2) 1"x5' .010 Slot Prepack Screen, 3" Expendable Point 5 each 150.00$ 750.00$
7 Materials: (1) 1"x5' .010 Slot Prepack Screen, 3" Expendable Point 5 each 85.00$ 425.00$
8 2' x 2' Concrete Pad w/8" BD Manhole 10 each 100.00$ 1,000.00$
9 Well Development (Up to 1/2 hour with pump) 10 each 75.00$ Included
10 Additional Well Development (Up to 1/2 hour with pump) 1/2 hour 75.00$ -$
11 4 each 55.00$ 220.00$
12 0 each 55.00$ -$
13 2 each 52.00$ 104.00$
Completion: Subtotal 12,029.00$
Todd Hodgson
Todd Hodgson TOTAL 12,029.00$ Partner
(813) 353-5765 DPT Soil Borings and GW Sampling
If you have any questions concerning this proposal contact Todd Hodgson at (407) 426-7885 or todd@drillprollc.com.
"Actual quantities used and days on site will be invoiced"
THANK YOU FOR YOUR BUSINESS!
Assume (4) Drums for IDW
**Damages to utilities on private property during borehole clearance are the responsibility of the client"
Drums Water (As Needed)
***Utility Locates on Private Property is the responsibility of the client**
5 Days
Permits: SWFLWMD
DPT GW Sampling at starting at 10', w/GW Grabs at 10', 20', 30' and 40' w/Continuous Soil Sampling
Drums Soil (Estimated by client)
CUSTOMER
Tampa, Florida 33607
Brian Burke Arcadis
PROJECT
Former Cotney's Cleaners 15305 Amberly Drive
3109 W. Dr. Martin Luther King Jr. Blvd. Suite 350 Tampa, Florida 33647
Per Diem (2 Man Crew)
Mobilization/Demobilization DPT Rig
DESCRIPTION
(1) DPT Soil Borings with Continuous Soil Sampling to 50' bls.
Grout all Borings and Patch.
(5) 1' x 12' PVC Well w/10' of .010 Slot Prepack Screens, 8" Flush Boltdown Completion (No Soil Sampling)
(5) 1' x 40' PVC Well w/5' of .010 Slot Prepack Screens, 8" Flush Boltdown Completion (No Soil Sampling)
Note: It is Groundwater Protection policy that if 'Pea Gravel' is encountered, ANY type of boring/drilling will be terminated immediately and the boring location will need to be relocated to a clear location by the client.
2300 Silver Star Road, Orlando, Florida (407) 426-7885 fax (407) 426-7586
Preferred Drilling Solutions, Inc.
11747 87th St. North, Largo, FL 33773 Ph: 727-561-7477 Fax: 727-561-9028 www.pdsflorida.com
DIRECT PUSH TECHNOLOGY QUOTE FORM
Consultant Name: Arcadis
Site Name and Location: Former Cotney's Cleaners Date: 6/26/20 FAC ID#:
15305 Amberly Dr, Tampa, FL
PROPOSED SCOPE OF WORK:
2 Days +/- of discrete water sampling borings to 50' with grab groundwater samples at 10' intervals
Grout borings upon completion, restore grade with asphalt or concrete
(5) 1" x 12' MW's withn 10' prepacked screen, soil sampling as needed, pad and 8" bolt down manhole
(5) 1" x 40' MW's withn 5' prepacked screen, soil sampling as needed, pad and 8" bolt down manhole
Drum soil & water, decon with alconox/liquinox
*Note: It is against PDS policy to drill in Pea Gravel. Borings in Pea Gravel will be terminated or can proceed solely at the risk of the consultant, DEP or Property Owner
Unit Unit Rate Number of Units Extended Price
Equipment Type: Geoprobe 7822DT, Geoprobe 7720DT
Direct Push Daily Rate 1 - on-site day whole day $1,575.00 5 $7,875.00 Direct Push Half-Day Rate 1 - on-site half day half day $1,100.00 $0.00 Auger Attachment, 2" Well Install per foot $12.50 $0.00 Pre-Packed Well Screen (includes all materials) ID 1" 5' Length Pack OD 3.5" each $75.00 15 $1,125.00 Slotted PVC Well Screen (includes all materials) 5' Length Pack OD 3.5" each $25.00 $0.00 Well Riser (includes all materials) ID 1" 5' Length each $15.00 40 $600.00 Well Completion (includes manhole w/ cover, concrete pad, and locking well cap) per well $100.00 10 $1,000.00
Mobilization roundtrip $675.00 1 $675.00 Per Diem per crew / per night $0.00 $0.00 DOT Approved 55-gal Drum each $50.00 4 $200.00 Permits each $75.00 2 $150.00 Geoprobe Consumables (disposable points, tubing, grout) lump sum $450.00 1 $450.00 Other (specify) $0.00 Other (specify) $0.00
TOTAL QUOTE PRICE $12,075.00
Notes:
1. Includes expendables, tubing, points, liners, caps, plugs, sawcuts, development, standby time, steamcleaning decon, and grouting.
Days to Complete Scope of Work: 5 Project No.:
Subcontract Company Name: Preferred Drilling Solutions, Inc. (727) 561-7477
Subcontract Mailing Address:8820 66th Street North, Pinellas Park, FL 33782
Signature and Title of Person Submitting Quote: ___________________________________Kevin Bonacum, Estimator Date: 6/26/20
DIRECT PUSH TECHNOLOGY
MISCELLANEOUS
EARTH TECH DRILLING
2703 NW 19TH STREET, POMPANO BEACH, FL 33069
954.974.2424 FAX:954.974.2423
Date: 6/23/2020
FAC ID#:
PROPOSED SCOPE OF WORK:
(5) MW 1"x40' w/ 5' Pre-Pack Screen & 8" BD Completion - No Soil Sampling
Client requested 4 drums
Unit Unit Rate Number of Units Extended Price
Equipment Type: DPT Track Rig
Direct Push Daily Rate 1 - on-site day whole day $1,500.00 5 $7,500.00
Direct Push Half-Day Rate 1 - on-site half day half day $0.00 2" Well Installation per foot $0.00 Auger Attachment, 4" Surface Casing each $0.00 Pre-Packed PVC Well Screen (includes all materials) 5' Length Pack OD ___1"____ each $85.00 15 $1,275.00 Well Riser (includes all materials) ID ___1"___ 5' Length each $30.00 40 $1,200.00 Well Completion (includes 30 Min Dev. 8" B-D MH & locking well cap) per well $175.00 10 $1,750.00
Mobilization roundtrip $875.00 1 $875.00 Per Diem per crew / per night $375.00 4 $1,500.00 DOT Approved 55-gal Drum each $60.00 4 $240.00 Permits 2 (Drilling or abandonment only; cost according to WMD & Local Municipalities) each $60.00 2 $120.00 Water Samples each $65.00 40 $2,600.00
$0.00
$0.00
TOTAL QUOTE PRICE $17,060.00
Notes:
Days to Complete Scope of Work: 5 Days Project No.: ___________________________
Subcontract Company Name: EARTH TECH DRILLING. Inc.
Subcontract Mailing Address: 2703 NW 19th Street, Pompano Beach, FL 33069
Signature and Title of Person Submitting Quote: Charles Bucher Date: 6/23/2020
DIRECT PUSH TECHNOLOGY
MISCELLANEOUS
Contractor Name: Arcadis / Brian Burke / 813 353-5755
Site Name: Cotney's Cleaners / 15305 Amberly Dr. Tampa, FL
(1) DPT Soil Boring to 50' Using Piston Point Macro Core Sampler (HAND CLEAR ALL LOCATIONS TO 5' or REFUSAL)
(3) Days Soil Borings w/ DPT Water Sampling to 40' with Samples taken every 10' (~ 4 Samples per boring) - Grout Borings (Estimated 40 Water Samples)
(5) MW 1"x12' w/ 10' Pre-Pack Screen & 8" BD Completion - No Soil Sampling
Monitoring Wells Sparge Wells Horizontal and Vertical Extraction Wells Geotechnical Drilling Direct Push
9225.Arcadis.Tampa, FL.CVOC Page 3 of 4
COST PROPOSAL
The cost estimate is based on the proposed technical approach described above.
GENERAL TERMS AND CONDITIONS
The number of days shown in the cost proposal is for planning purposes only. Pace operates on a 10-hour day. Anything over 10 hours in a single day will be billed at $200/hour/person. Overtime will only be performed at your explicit direction. Partial days, i.e., anything less than 5 hours, are also billed at one-tenth the daily rate. Costs as shown include all containers and supplies.
Pace will arrive on site approximately one full day prior to your first sample delivery to secure power, and calibrate the systems needed for the project. This is included in the mobilization fee.
ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE AMOUNT
1 Mobilization and demobilization of staff and lab from Ormond Beach, FL, to Tampa, FL.
1 LS $900 $ 900
2 Staff of one chemist, on-site instrumentation and supplies, with a capacity to analyze 20 samples per day for 8260 VOCs. Includes per diem.
3 Day $1,600 $4,800
3 Power (cost as shown includes on-board generator).
3 Day $150 $ 450
TOTAL $6,150
P.O. Box 349, Cape Canaveral, Florida 32920 E mail: dale.schamp@alf1992.info Cell phone: 321–258-1355
Analytical Laboratories of Florida, Inc.
Quotation Number: 20-112 NELAC Laboratories No.: E83934 & 831090 June 22, 2020
Brian Burke ARCADIS U.S., Inc.
3109 West Dr. MLK, Blvd. Suite 350 Tampa, Fl. 33607
(813) 298-2838©
To Mr. Burke:
Per the communication request for a proposal for the analysis of environmental samples by EPA 8260 with a mobile laboratory, I am submitting the following proposal:
Target Compounds: Vinyl chloride, 1,1-DCE, trans/ cis-1,2-Dichlorothene, TCE, and PCE.
Matrix: water Limit of Quantitation (LOQ):water-1 ppb vinyl chloride all others 1-3 ppb ;soils 3-5X greater.
Sample Load/day: Up to 20 per day or 10 hrs. onsite whichever comes first Location: Tampa, Florida (Fmr Cotney’s Cleaners @ 15305 Amberly Drive) Mobilization Date: unknown Costs:
Mobilization (one roundtrip) $ 500.00 (fixed) Mobile Laboratory (3-day reservation) $3300.00 (fixed) Chemist Labor @$ 150.00/day $ 450.00 (variable) Total Cost: Up to $ 4250.00 (Up to 3 days; Mon-Wednesday) (1 day is up to 10 hrs. or 20 samples per day whichever comes first.)
*Subject to availability. Containers available for lab days onsite. Net 90 days. Add $1400.00/day for additional days. Over 20 samples/day add $150.00/each. No partial day charges. If you have any questions, I can be reached on my mobile phone at 321-258-1355.
Please send all written correspondences to P.O. Box 349, Cape Canaveral, Florida 32920.
Sincerely, ANALYTICAL LABORATORIES OF FLORIDA, INC.
Dale Schamp Chemist mailto:dale.schamp@alf1992.info
SITE LINES PROPOSAL ACCEPTANCE
SIGNATURE PAGE
Site Lines Proposal Number: 0763p Proposal Date: June 23, 2020
Project Site: Former Cotney’s Cleaners Site – 15305 Amberly Dr., Tampa, FL
Project Fee: $1,100.00
Payment Terms: [PAYABLE WITHIN 30-DAYS OF INVOICE]
INVOICE TO:
Client: ARCADIS Address: 3109 West Dr. Martin Luther King Jr. Blvd., Tampa, FL 33607 Attention: Chad Hanna Phone: 813-353-5765 Email: chad.hanna@ARCADIS.com
Special Instructions:
In witness thereof, the parties hereto have made and executed this agreement
FOR [CLIENT] FOR SITE LINES LLC
Signature: Signature:
By: By: William L. Hardy II
Title: Title: President
Date Signed: Date Signed: June 23, 2020
Pepe_T Highlight
GEOVIEW, INC.
PROPOSAL ACCEPTANCE SHEET
Project Name: Former Scott’s Custom Cleaners, Inc.
Project Location Tampa, Florida GeoView Proposal #: 8703p Proposal Date: June 23, 2020 Description of Services Provide Utility Designating Services and Video
Pipeline Inspection Project Cost: see compensation, page 3 Payment Terms: Payable within 30 days of receipt of invoice
CHARGE INVOICE TO THE ACCOUNT OF:
Client: ARCADIS Address: 3109 West Dr. Martin Luther King Jr. Boulevard, Suite 350
Tampa, FL 33607 Attention: Mr. Chad Hanna Phone (Office): (813) 353-5765 Phone (Cell): (813) 480-8498 Email: chad.hanna@arcadis-us.com
FOR APPROVAL OF CHARGES:
Firm:
Address:
Phone No.: Fax No:
Attention:
Special Instructions and/or Mutually Agreed Upon Changes to the Proposal:
In witness thereof, the parties hereto have made and executed this Agreement
Client: GeoView, Inc.
Signature
By: By: Michael J. Wightman
Title: Title: President
Date Signed: Date Signed: June 23, 2020 suspected cracking in the pipes will be identified on the site map which will be performed as part of the final report. A video record of the inspection will also be provided. The sewer line will be accessed through a cleanout location within the building.
Based on information provided by ARCADIS, it does not appear that the work at any of the sites will require MOT (traffic calming efforts). This proposal does not include the costs for the design or implementation of a MOT program. If necessary, GeoView can design and implement a MOT program for an additional charge.
Presentation of Results
The location and estimated depths of underground utilities or any other identified structures shall be indicated on the ground surface using spray paint or other methods as specified by ARCADIS. Designated utilities will also be provided on a scaled AutoCAD site map which will be prepared as part of a final report for the investigation. The site map will provide the location, depth and purpose of any underground utilities or other structures identified by the survey. A digital copy of the pipeline inspection will also be provided if a decision is made to include the video inspection of the sanitary sewer line within the investigation.
Compensation
Cost to complete the survey will be as follows:
Utility Designation Study and Preparation of AutoCAD Site Map: $1,250 Video Inspection of Sewer Pipeline Inside of Building: $500
These prices are inclusive of all charges associated with the project. Unless otherwise agreed upon, GeoView shall be compensated for all services within 30 days of invoice date. GeoView shall be paid in full regardless of whether the results of the geophysical survey are what ARCADIS anticipated. If it is determined during the survey that the geophysical survey will not achieve the objectives of the project, ARCADIS will immediately be notified. If a decision is made to discontinue the survey, only charges for time and materials costs to that point will be submitted.
If the pipeline video system cannot be advanced through the designated sanitary sewer line due to site limitations (multiple 90 degree turns, etc.) the video inspection will not be performed. For this portion of the study ARCADIS will only be charged for the mobilization charge of the video inspection system which will not exceed $150.
Pepe_T Highlight
Micah Slankard | Project Coordinator | Southeast | (407) 335-6588 |micah.slankard@gprsinc.com www.gprsinc.com | Corporate Headquarters: 5217 Monroe St, Toledo, OH 43623 | EIN #: 31-1803412
PROJECT COSTS
SERVICE SCOPE PRICE
SCANNING/FIELD MARKINGS See description on previous pages $1,200
MOBILIZATION Included at no charge $INCL
ADDITIONAL TIME ON SITE Changes in scope of work or delays incurred on site will result in additional fees
$200/hour
GPS MAP Findings collected with GPS and overlaid in Google Earth. Results are not survey-grade accuracy.
$400
ESTIMATED TOTAL *$1,600
OPTIONAL SERVICES (INITIAL IF DESIRED)
WRITTEN REPORT Detailed report of findings with several photos and several comparative data shots.
Initial
$400
CAD DRAWING Findings will be drafted in AutoCAD with an aerial image background. A linework version will also be provided if the client provides an existing drawing. Results are not survey-grade accuracy.
Initial
$700
SEWER CAMERA Trace accessible cleanouts and storm drains Initial
$700
HYDROEXCAVATION/POTHOLING GRPS will subcontract professional potholing and hydroexcavation services should your project deem it necessary.
Initial
$TBD
PROFESSIONAL LAND SURVEYING GRPS will subcontract professional land surveying and mapping services should your project deem it necessary.
Initial
$TBD
* This price assumes that we will be given access to perform the work during normal weekday business hours (6am-5pm). As-builts and any other applicable drawings should be made available to GPRS prior to the project. A thorough utility search can only be completed if GPRS is given access to all utility structures, interior and exterior. This service is never a replacement for the use of the state One Call system (811). All of our technicians have OSHA-10 safety training or greater. Site-specific safety training is not included in this quote. Please notify us if this project requires additional safety training.
TERMS & CONDITIONS
1. Customer agrees to meet and perform all requirements described in this document and has fully read and understands all items listed within this document.
2. Customer understands that our results are based upon the quality of the data retrieved which is determined by a variety of fa ctors, including but not limited to the limitations listed in the “Equipment” section below. These limitations are inherent to all locating equipment. The decision to proceed with drilling, excavation or any destructive methods is left entirely up to the customer. GPRS does not and cannot guarantee, warrant or represent that it will locate all items on site.
3. Customer agrees that GPRS’s liability to customer is limited to the price paid by customer to GPRS, and that GPRS is not liab le for any other damages, including but not limited to compensatory, consequential or incidental damages. Customer agrees to release and indemnify GPRS and its owners, employees and agents from all losses and damages from all alleged negligence, contract, environmental or other claims by any third party.
4. It is the customer’s responsibility to prepare the site for scanning, including clearly identifying areas to be scanned, securing access to all areas required for scanning, and keeping these areas clear and free of obstructions. Delays caused by customer’s failure to do so may result in an increased price.
5. If GPRS provides maps or CAD drawings, please note that they are not survey quality. These are representations of GPRS’ utility findings performed on a previous date. The GPRS scan performed was of limited scope and utilities outside this scope are not shown.
6. GPRS does not conduct an investigation, analysis, or interpretation of soil composition, soil conditions, or geophysical, geological, engineering, or land surveying information. Customer acknowledges it understands that we are merely reporting retrieved data and that we do NOT provide geophysical, geological, engineering, or land surveying services. Customer should contact a professional in those fields if such services are needed.
7. These terms and conditions supersede any other previous terms and conditions, or representations, either oral or written.
8. If for some reason the technician arrives on site and the work is cancelled there will be a charge of $500.00 per requested technician.
ACCEPTED AND AGREED:
Billing Company Name:
Billing Address:
Company Phone/Email: PO#: Job#:
Print Name: Signature: Date:
mailto:micah.slankard@gprsinc.com http://www.gprsinc.com/ Pepe_T Highlight
June 26, 2020
Mr. Chad Hanna
Arcadis U.S. Inc.
3109 West Martin Luther King Jr. Boulevard
Suite 350
Tampa, Florida 33607
RE: 15305 AMBERLY DRIVE
Tampa, Florida
Dear Mr. Hanna:
Landmark Engineering & Surveying Corporation is pleased to present this proposal for surveying services for the above referenced property. As requested in your email dated Tuesday June 23, 2020, Landmark will locate up to ten (10) monitoring wells as shown on your attachment. We will record and report the horizontal position (latitude and Longitude) of the wells only and shoot elevations for ground and monitoring well top of casings.
FEE: $1000.00
Time Frame: The work will be completed within three (3) weeks from receipt of the signed
Authorization to Proceed.
Landmark thanks you for the opportunity to present this proposal and looks forward to your favorable response. If you should have any questions or comments, please do not hesitate to let me know.
Sincerely, LANDMARK ENGINEERING
& SURVEYING CORPORATION
Scott R. Fowler, LS
Vice President/Partner
AUTHORIZATION TO PROCEED
Signature: _____________________________________________________________________
Print Name & Title: _____________________________________________________________
Firm: _________________________________________________________________________
Billing Address: ________________________________________________________________
City, State, Zip: ________________________________________________________________
Preferred Invoice via _____ U.S. Mail _____ E-Mail
ID Task Name Duration Start Finish
1 TA Receipt 0 days Mon 8/3/20 Mon 8/3/20
2 Site Owner & Property Mgr Contact/Subcontractor Scheduling
1 day Mon 8/3/20 Mon 8/3/20
3 Utility Locate & Kick-off Meeting 0.5 days Mon 8/17/20 Mon 8/17/20
4 Soil & Groundwater Assessment, MAGS 5 days Mon 8/17/20 Fri 8/21/20
5 Monitor Well Sampling (12 Wells) & Site Survey
2 days Mon 8/24/20 Tue 8/25/20
6 SA Report 45 days Wed 8/26/20 Tue 10/27/20
8/3
Bill Vogelsong,Brian Burke
Eric Brooks,Brian Burke
Mobile Lab,Driller,Chad Hanna,Eric Brooks
Surveyors,Eric Brooks
Bill Vogelsong,Brian Burke,Eric Brooks,Chad Hanna
5/31 6/7 6/14 6/21 6/28 7/5 7/12 7/19 7/26 8/2 8/9 8/16 8/23 8/30 9/6 9/13 9/20 9/27 10/410/1110/1810/2511/1 11/8 June July August September October November
Task
Milestone
Summary
Rolled Up Task
Rolled Up Milestone
Rolled Up Progress
Split
External Tasks
Project Summary
Group By Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Progress
Deadline
Former Cotneys All Pro Cleaners Resource Loaded Schedule
Cotneys Schedule Page 1 Arcadis
Project: Former Cotneys All Pro Cleaner FDEP Facility ID No.: ERIC_4704 Date: Fri 6/26/20
| Task Assignment Notification |
| BWC Task Assignment Form (Rev 02_17).pdf |
| Task Assignment Notification |
| BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf |
| Deliverable & Invoice Schedule |
| Cotney's proposal.pdf |
| Driller Bids.pdf |
| Direct Push |
| Direct Push |
| Subcontractor Bid Summary-Cotneys SAR.pdf |
| Driller Quotes: |
| Mobile Lab Quotes: |
| Utility Locate: |
| Surveying: |
| IDW: |
| neg sum.pdf |
| Subtask 2: Site Assessment |
| Subtask 3: Site Assessment Report (SAR) |
File details come from the government source that posted it. Updated .