CN-370000-HW557-DC039i.pdf
PDF 505 KB Posted
- Contract number
- HW557
- Issued by
- Florida
About this file
This document is a Task Assignment Notification Form for Florida Department of Environmental Protection (FDEP) Contract No. HW557, issued on September 28, 2021. The task assignment (DC039i) is between FDEP and contractor Arcadis U.S., Inc., with William Vogelsong as the contractor representative and Theresa C. Pepe as the DEP Contract Manager. The work is being performed for the Dapper Dan Inc. site located at 9850 Alt A1A #501, Palm Beach Gardens, Palm Beach County, Florida (DEP Site #ERIC_5085). The document outlines the scope, deliverables, timeline, and financial arrangements for annual groundwater monitoring activities at this former dry-cleaning facility.
The task involves annual groundwater monitoring from ten select monitor wells at the site, with all activities performed according to Arcadis's September 27, 2021 Work Plan. The work is structured in three subtasks: Project Management (automatically calculated as a percentage of total labor), Annual Groundwater Sampling (sampling ten monitor wells of various depths with IDW drummed and disposed by a licensed waste hauler), and Reporting (a written report with recommendations). The total task assignment value is $7,897.54 on a fixed price basis with zero retainage. The final deliverable is an Annual Monitoring Report/IDW manifest due January 7, 2022, with invoicing authorized upon FDEP approval of these deliverables. The period of performance extends through February 4, 2022. The cost estimate details labor for 55 total hours, travel expenses of $97.00 for vehicle rental, laboratory analysis costs of $830.00, field expenses totaling $745.95, and subcontractor costs of $165.00 for IDW disposal services provided by Clark Environmental Inc.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEP CONTRACT NO.
Task Assignment #: Module #: Grant #:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
DEP Site #:
Site Name:
Address(Street, City, County):
Phase:
Task Description [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverables:
Final Deliverable Due Date:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
FIXED FEE
RETAINAGE:
TOTAL TASK ASSIGNMENT VALUE: $0.00
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93) Section Representative ________
TASK ASSIGNMENT NOTIFICATION FORM
COST PLUS FIXED FEE
COST REIMBURSEMENT
FIXED PRICE FEE SCHEDULE
Period of Performance:
Execution of Task Assignment through:
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
WCP TAFORM 01_18
HW557
D000 N/ADC039i
Arcadis U.S., Inc.
William Vogelsong
(850) 245-8705Theresa C. Pepe
ERIC_5085
Dapper Dan Inc.
9850 Alt A1A #501, Palm Beach Gardens, Palm Beach County
Monitoring
Arcadis will conduct annual groundwater monitoring from select wells at the site.
All activities will be performed according to the September 27, 2021, Work Plan submitted by Arcadis.
Annual Monitoring Report/IDW manifest
01/07/2022
02/04/2022
$ 7,897.54 $ 0.00 $ 0.00 $ 0.00
$ 0.00
Theresa C. Pepe Digitally signed by Theresa C. Pepe Date: 2021.09.28 15:21:30 -04'00'
Theresa C. Pepe Digitally signed by Theresa C. Pepe Date: 2021.09.28 15:21:43 -04'00'
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2021.09.29 10:01:09 -04'00'
William D. Vogelsong Digitally signed by William D. Vogelsong Date: 2021.09.29 13:46:17 -04'00'
$ 7,897.54
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number: HW557 Task Assignment #: DC039i
Deliverables:
Deliverable Deliverable Due Date Annual Monitoring Report 7-Jan-22
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
FDEP approval of Annual Monitoring Report/IDW manifest/Project Management $7,897.54
TOTAL COST $7,897.54
BWC TAFORM 01/18
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO: Negotiation File Dapper Dan Facility ID No. 50-9500276; ERIC_5085 Palm Beach Gardens, Palm Beach County FROM: Theresa C. Pepe, Project Manager SUBJECT: Task Assignment DC039i (HW557) DATE: September 28, 2021
Arcadis will perform annual groundwater monitoring from select wells at the site.
Additional information can be found in the September 27, 2021, Work Plan submitted by Doug McGlone of Arcadis.
The final task assignment total is $7,897.54. Arcadis may invoice according to the attached schedule.
Specific negotiated subtasks are as follows:
Subtask 1: Project Management Project Management is automatically calculated as a percentage of total labor.
Subtask 2: Annual Groundwater Sampling This subtask provides costs to sample ten monitor wells of various depths. IDW will be drummed and disposed by a licensed waste hauler according to recent FDEP guidelines.
Subtask 3: Reporting Arcadis will submit a written report as the final deliverable including recommendations for additional actions as needed.
Hours and costs are comparable to past task assignments of similar work.
FDEP COST ESTIMATE
Contractor: Arcadis U.S., Inc.
Date: 9/28/2021
Task #: SubTask 1 Project Management
Site: Dapper Dan, Inc. SubTask 2 Annual Groundwater Monitoring
Activity/Phase: Monitoring SubTask 3 Reporting
Project Manager: Doug McGlone SubTask 4
SubTask 5
Totals 1 2 3 4 5
Labor Rate Category Staff Member
$79.12 Project Manager Suarez, Gus (GS) 3 2.9
$96.76 Principal Engineer Bedessem, Jim (JMB) 0 0 0 0 0
$82.29 Principal Scientist Vogelsong, William (BV) 0 0 0 0 0
$81.24 Principal Engineer Burtnett, Susan (SB) 0 0 0 0 0
$79.12 Principal Engineer Suarez, Gus (GS) 0 0 0 0 0$75.11 Principal Scientist McManus, Andrew (ATM) 0 0 0 0 0
$61.69 Principal Scientist Burke, Brian (BRB) 0 0 0 0 0
$61.38 Principal Scientist McGlone, Douglas (DMc) 8 4 4 0 0
$61.32 Principal Scientist Dellay, Leah (LD) 0 0 0 0 0
$28.94 Scientist McBath, Brandon (BMc) 32 14 18 0 0
$39.67 Drafter/Designer Oliva, Brian (BO) 5 0 5 0 0
$30.99 Drafter/Designer Richards, Jim (JR) 0 0 0 0 0
$31.48 Drafter/Designer Berndgen, Wendy (WDB) 0 0 0 0 0
$35.00 Document Technician Ballheim, Debra (DJB) 0 0 0 0 0
$26.52 Document Technician Embras, Susan (SRE) 0 0 0 0 0
$30.96 Project Assistant McLemore, Michele (MMc) 7 3 4 0 0
Total Hours 55 3 21 31 0 0
Direct Labor $2,061.21 $229.02 $743.56 $1,088.63 $0.00 $0.00
Overhead 57.95% $1,637.98 $182.00 $590.88 $865.10 $0.00 $0.00
Gen & Admin 21.29% $950.50 $105.61 $342.88 $502.01 $0.00 $0.00
Fringe 37.13% $765.33 $85.04 $276.08 $404.21 $0.00 $0.00
Total Labor $5,415.02 $601.67 $1,953.40 $2,859.95 $0.00 $0.00
Other Direct Costs $103.06 $11.45 $37.18 $54.43 $0.00 $0.00
Travel
Vehicle Rental $97.00 $97.00 $0.00 $0.00 $0.00
Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00
Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00
Total Travel $97.00 $97.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement)
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00
Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00
Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement)
Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00
Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00
Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00
Surveying $0.00 $0.00 $0.00 $0.00 $0.00
Clark Env IDW $150.00 $150.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00
Geo-Tek Utility Locate / GPR Survey $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $150.00 $150.00 $0.00 $0.00 $0.00
Handling Fee $15.00 $15.00 $0.00 $0.00 $0.00
Total Subcontractor Cost $165.00 $165.00 $0.00 $0.00 $0.00
Laboratory
TestAmerica Analytical Costs $726.00 $726.00 $0.00 $0.00 $0.00
Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00
Sample Shipping $104.00 $104.00 $0.00 $0.00 $0.00
Total Laboratory $830.00 $830.00 $0.00 $0.00 $0.00
Field Expenses
Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00
Expendables $32.50 $32.50 $0.00 $0.00 $0.00
Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (Analytical related) $655.25 $655.25 $0.00 $0.00 $0.00
Equipment (IDW related) $58.20 $58.20 $0.00 $0.00 $0.00
Equipment (Other - MAGS, recon) $0.00 $0.00 $0.00 $0.00 $0.00
Total Field Expenses $745.95 $745.95 $0.00 $0.00 $0.00
Subtotal $7,356.03 $613.12 $3,828.53 $2,914.38 $0.00 $0.00
Completion Fee $541.51 $60.17 $195.34 $286.00 $0.00 $0.00
Total Estimated Cost $7,897.54 $673.29 $4,023.87 $3,200.38 $0.00 $0.00
REV: 02/03 CEF ARCADIS Page 1
SITE: Dapper Dan, Inc.
SUBTASK 2: Annual Groundwater Monitoring
DATE: 9/28/21
LABOR
Category/Staff Work Description Hours
(Subtask Title) Principal / DMc Property owner/tenant access, field personnel & FDEP discussions 4
Scientist / BMc Mob/demob (2 hrs), sample 10 wells (10 hrs), pack/ship damples (2 hr) 14
Project Assistant Sample container ordering, process filed notes, sample tracking 3
Technician 0
TOTAL LABOR: 21
TRAVEL
Vehicle Type Rate Unit Usage Totals
Automobile $68.00 Per Day 0 $0.00
Van/Truck $97.00 Per Day 1 $97.00
Van/Truck $420.00 Per Week 0 $0.00
Total Vehicle: $97.00
Meals Category/Staff Rate Unit Usage Totals
$36.00 Per Day 0 $0.00
$36.00 Per Day 0 $0.00
Hotel Category/Staff Rate Unit Usage Totals
$90.00 Per Day 0 $0.00
$90.00 Per Day 0 $0.00
Total Meal/Hotel: $0.00
TOTAL TRAVEL: $97.00
SUBCONTRACTOR COSTS
Equipment Procurement Name Equipment Rate Units Usage Totals
0 $0.00
Total Equip.: $0.00
Services Procurement Name Purpose Rate Units Usage TotalsNAME OF COMPANY Direct-push services $0.00 Lump Sum 0 $0.00
NAME OF COMPANY IDW $150.00 Drum 1 $150.00NAME OF COMPANY On-site Mobile Laboratory analysis $0.00 Lump Sum 0 $0.00
Handling Fee $20.00 Per Month 0 $0.00
Total Services: $150.00
TOTAL SUB: $150.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
VOH 8260 Aqueous $66.00 1.00 11 $726.00
TAT 24-hr=100% (2.0) 3-day=50% (1.5) 1-week=15% (1.15) Total Lab: $726.00
Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $104.00 Per Cooler 1 $104.00
Shipping - Small (0 to 25 lbs.) --- --- $63.00 Per cooler 0 $0.00
Total Shipping: $104.00
TOTAL LAB: $830.00
FIELD EXPENSES
Personal Protection Item Rate Unit Usage TotalsPPE Level D $28.00 Per Man Day 0 $0.00
Total PPE: $0.00
Equipment Item Rate Unit Usage Totals
Expendables Miscellaneous Expendables $32.50 Per Day 1 $32.50
Total Expendables: $32.50
Equipment ItemsPadlocks $3.40 Each 0 $0.00
Tubing, Poly/HDPE $0.25 Per Foot 350 $87.50
Tubing, Silicon 3/16x3/8 $2.00 Per Foot 5 $10.00 55-gallon Drum $58.20 Each 1 $58.20
Total Equipment Items: $155.70
Equipment Kits Shallow Groundwater Sampling Kit $208.55 Day 1 $208.55 Deep Groundwater Sampling Kit $349.20 Day 1 $349.20
Total Equipment Kits: $557.75
TOTAL EQUIPMENT: $713.45
SITE: Dapper Dan, Inc.
SUBTASK 3: Reporting
DATE: 9/28/21
LABOR
Category/Staff Work Description Hours
(Subtask Title) Principal / DMc PG review, certification of report 4
Scientist / BMc Report text (8 hrs), table generation (4 hrs), figure generation (4 hrs), coordinate IDW removal (2 hrs) 18
Project Assistant / MMc Report assembly and submittal 4
Drafter / BO Figure generation, ADaPT database entry 5
TOTAL LABOR: 31
TRAVEL
Vehicle Type Rate Unit Usage Totals
Automobile $68.00 Per Day 0 $0.00
Van/Truck $97.00 Per Day 0 $0.00
Van/Truck $420.00 Per Week 0 $0.00
Total Vehicle: $0.00
Meals Category/Staff Rate Unit Usage Totals
$36.00 Per Day 0 $0.00
$36.00 Per Day 0 $0.00
Hotel Category/Staff Rate Unit Usage Totals
$90.00 Per Day 0 $0.00
$90.00 Per Day 0 $0.00
Total Meal/Hotel: $0.00
TOTAL TRAVEL: $0.00
SUBCONTRACTOR COSTS
Equipment Procurement Name Equipment Rate Units Usage Totals
0 $0.00
Total Equip.: $0.00
Services Procurement Name Purpose Rate Units Usage TotalsNAME OF COMPANY Direct-push services $0.00 Unit pricing 0 $0.00
Total Services: $0.00
TOTAL SUB: $0.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples TotalsVOC (Halocarbons Only) 8260C Aqueous/Non $66.00 1.00 0 $0.00
TAT 24-hr=100% (2.0) 3-day=50% (1.5) 1-week=15% (1.15) Total Lab: $0.00
Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $104.00 Per Cooler 0 $0.00
Shipping - Small (0 to 25 lbs.) --- --- $63.00 Per cooler 0 $0.00
Total Shipping: $0.00
TOTAL LAB: $0.00
FIELD EXPENSES
Personal Protection Item Rate Unit Usage Totals
Total PPE: $0.00
Equipment Item Rate Unit Usage Totals
Expendables Miscellaneous Expendables $32.50 Per Day 0 $0.00
Total Expendables: $0.00
Equipment ItemsMultimeter (pH, Temp, Cond, DO, Orp) $97.00 Per Day 0 $0.00
Total Equipment Items: $0.00
Equipment KitsSite Reconnaissance Kit $81.48 Day 0 $0.00
Total Equipment Kits: $0.00
TOTAL EQUIPMENT: $0.00
Use or disclosure of information contained on this sheet is subject to the restriction and disclaimer located on the signature page of this document.
Arcadis U.S., Inc.
1500 Gateway Boulevard
Suite 200
Boynton Beach
Florida 33426
Tel 561 697 7000
Fax 561 369 4731 www.arcadis.com
Page:
1/3
Ms. Theresa Pepe Hazardous Waste Cleanup Section Florida Department of Environmental Protection 2600 Blair Stone Road, MS 4520 Tallahassee, Florida 32399
Subject:
Proposal for Annual Groundwater Monitoring & Reporting Former Dapper Dan Cleaners 9850 Alternate A1A, Palm Beach Gardens, Florida Facility ID No. ERIC_5085
Dear Ms. Pepe:
As requested, Arcadis U.S., Inc. (Arcadis) is submitting this proposal to perform annual groundwater monitoring/reporting for the subject site. A proposed scope of work, schedule and cost estimate are included herein.
SCOPE OF WORK
Based on review of the site historical groundwater quality, discussions with the FDEP and Chapters 62-780 and 62-777 FAC, the following three tasks are proposed:
Task 1: Preparation and Site Access
This task includes laboratory subcontractor coordination, site access with property owner / manager, equipment checkout, and preparation for field activities.
Task 2: Annual Groundwater Monitoring
Sampling of select existing monitor wells is proposed to monitor plume extent and concentration trends that can be used to further limit the number of wells sampled during future monitoring events. Currently, based on 2020 data, there are two plumes. Monitoring in the intermediate and deeper zones is proposed in
ENVIRONMENTAL
Date:
September 27, 2021
Contact:
William D. Vogelsong Douglas J. McGlone
Phone:
561-662-8223 561-662-7978
Email:
william.vogelsong@arcadis.com douglas.mcglone@arcadis.com
Use or disclosure of information contained on this sheet is subject to the restriction and disclaimer located on the signature page of this document.
arcadis.com C:\Users\Pepe_T\Desktop\Dapper Dan Proposal 2021-09.docx
Proposal for Annual Groundwater Monitoring & Reporting Former Dapper Dan Cleaners September 27, 2021
Page:
2/3 the monitor wells between the plumes. Annual groundwater monitoring will be performed on a total of ten monitor wells (MW001, MW002I, MW006D, MW008I, MW009D, MW010, MW0011I, MW012D, MW013D, and MW014I).
One duplicate sample will also be collected from MW002I for quality assurance purposes (total of 11 samples). Each of the ten monitor wells will be purged and sampled using low-flow sampling techniques in accordance with Standard Operating Procedures (SOP). Purge water will be drummed for offsite disposal. Field water-quality parameters (pH, temperature, conductivity, redox potential and dissolved oxygen) also will be measured in these ten wells using a flow cell. The groundwater samples will be submitted to a NELAP-accredited laboratory for analysis of chlorinated solvents per EPA Test Method 8260. For the purposes of preparing water-elevation contour maps, water levels will be measured in the ten monitor wells sampled.
Task 3: Annual Groundwater Monitoring Report
A brief report summary documenting the sampling methodology and results, including a table summarizing the groundwater analytical results, figures illustrating the extent and magnitude of the solvent plume and copies of sample lab reports will be provided to the FDEP, along with recommendations for future site activities. The report will be signed and sealed by a Florida registered professional geologist
SCHEDULE
Arrangements for the completion of the 2021 groundwater monitoring activities will be conducted immediately upon receipt of a Task Assignment from the FDEP. Initiation of these activities is expected in October 2021. The Annual Groundwater Monitoring Report will be submitted to the FDEP within 60 days of the completion of filed activities.
This proposal and its contents shall not be duplicated, used or disclosed — in whole or in part — for any purpose other than to evaluate the proposal. This proposal is not intended to be binding or form the terms of a contract. The scope and price of this proposal will be superseded by the contract. If this proposal is accepted and a contract is awarded to Arcadis as a result of — or in connection with — the submission of this proposal, Arcadis and/or the client shall have the right to make appropriate revisions of its terms, including scope and price, for purposes of the contract. Further, client shall have the right to duplicate, use or disclose the data contained in this proposal only to the extent provided in the resulting contract.
arcadis.com C:\Users\Pepe_T\Desktop\Dapper Dan Proposal 2021-09.docx
Proposal for Annual Groundwater Monitoring & Reporting Former Dapper Dan Cleaners September 27, 2021
Page:
3/3
ESTIMATED COST
Level of Effort (LOE) Forms and a Cost Estimate Form (CEF) that present estimated project costs, are enclosed.
Arcadis appreciates the opportunity to assist the Florida Department of Environmental Protection in the successful closure of the contamination in the subsurface at this site. If you have any questions or wish to discuss this proposal, please contact us.
Sincerely, Arcadis U.S., Inc.
Douglas J. McGlone Senior Hydrogeologist
William D. Vogelsong, P.G.
Project Manager/Principal Hydrogeologist
6/9/2021 Clark Environmental Inc.: Quote Builder file:///C:/Users/channa/AppData/Local/Microsoft/Windows/INetCache/Content.Outlook/55TP28C8/Arcadis 1530 1st.html 1/2
Quote Number: 18737
QUOTE
QUOTED TO: Chad Hanna QUOTE DATE: 6/9/2021 COMPANY NAME: Arcadis QUOTED BY: Steve Harris PHONE NUMBER: 813-480-8498 Ext.
FAX NUMBER: email only PROJECT REFERENCE: Transportation and Disposal of Non Haz. Water Drum.
CUSTOMER PO:
CONTACT EMAIL:
SITE ADDRESS: 1530 1st Street Sarasota FL
CLARK ENVIRONMENTAL, INC. IS PLEASED TO PROVIDE THE
FOLLOWING COST ESTIMATE FOR THE SITE/ PROJECT LISTED
ABOVE.
DESCRIPTION PRICE QTY. UNIT TOTAL
NON HAZ. "WATER" DRUM DISPOSAL W/CUSTOMER SUPPLIED
ACCEPTABLE NON HAZ. ANALYTICAL AND PROFILE STATING SAME.
$60.00 1 55 GAL $60.00
DRUM TRANSPORTTATION <100 MILES FROM CLARK ENVIRONMENTAL
INC. DRUM LOCATED ON HARD BLACK TOP OR CONCRETE SURFACE
EASILY ACCESSIBLE WITH 53 FOOT TRACTOR TRAILER WITH
LIFTGATE NO CURBS, GRASS OR DIRT TO CROSS.
$40.00 1 55 GAL $40.00
DRUM LOW VOLUME STOP CHARGE FOR 5 DRUMS OR LESS. $50.00 1 FLAT RATE $50.00
TOTAL REQUIRED ITEMS $150.00
TOTAL OPTIONAL ITEMS $0.00
GRAND TOTAL $150.00
NOTES: Quote is based on acceptable customer supplied non haz. analyticals and matching profile. TCLP Metals and Volatiles Analitical Testing will be required .Quote based on DOT shippable drums from this location easily accessable with 53 foot tractor trailer with no grass, curbs or sand to cross.If Required, I will need a signed accepted quote with purchase order and non haz. profile. Please call with any questions. Thanks. Steve Harris 863-559-
This quote will remain valid for thirty (30) days from the date listed above except for transportation which is subject to weekly change and is based on upon payment in net 30 days. Quote based on an accepted and approved profile. Please sign and return to accept this quotation and by signing agree to all terms and conditions.
| Task Assignment Notification |
| BWC Task Assignment Form (Rev 02_17).pdf |
| Task Assignment Notification |
| BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf |
| Deliverable & Invoice Schedule |
| DC039i negsum.pdf |
| Subtask 2: Annual Groundwater Sampling |
| Subtask 3: Reporting |
| Dapper Dan Proposal 2021-09.pdf |
| Scope of Work |
| Task 1: Preparation and Site Access |
| Task 2: Annual Groundwater Monitoring |
| Task 3: Annual Groundwater Monitoring Report |
| Schedule |
| Estimated Cost |
File details come from the government source that posted it. Updated .