CN-370000-HW557-DC02NCO1.pdf

PDF 1 MB Posted

Attached to
Master Agreement FL|HW557|6d20a3cd85832f58780db610589fb2f8
Contract number
HW557
Issued by
Florida

About this file

This document is a Task Assignment Notification Change Order for Florida Department of Environmental Protection (FDEP) Contract No. HW557, involving the contractor Arcadis U.S., Inc. The change order modifies Task Assignment DC002N at the Butler Cleaners site (ERIC_4573) located at 1268 South McDuff Avenue, Jacksonville, Duval County, Florida. The key personnel include Contractor Representative William Vogelsong, DEP Contract Manager Theresa C. Pepe, and Contractual Authority William E. Burns, Jr. This change order was executed on August 20, 2021, and is identified as Change Order No. 1.

The change order adds costs for the transport and disposal of one drum of purge water generated during annual groundwater sampling activities at the site. The original task assignment amount was $6,605.01, with the change order increasing the total by $110.00, resulting in a new task amount of $6,715.01. This increase covers subcontractor costs from Erwin Remediation, Inc., which provided a quote of $100.00 per drum for both transportation and disposal, plus a $10.00 handling fee. The final deliverable is an Annual Monitoring Report with a due date of July 30, 2021. Invoice requirements specify that payment of $6,715.01 is contingent upon FDEP approval of the Annual Monitoring Report and associated project management. There is no change to the task completion date, which remains September 3, 2021.

View the file

Other files

File Type Posted
CN-370000-HW557-A3.pdf PDF
CN-370000-HW557-A7.pdf PDF
CN-370000-HW557-A8.pdf PDF
CN-370000-HW557-CO1.pdf PDF
CN-370000-HW557-CO3.pdf PDF
CN-370000-HW557-CSS1A.pdf PDF
CN-370000-HW557-CSS1B.pdf PDF
CN-370000-HW557-CSS2A.pdf PDF
CN-370000-HW557-CSS2C.pdf PDF
CN-370000-HW557-CSS3B.pdf PDF
CN-370000-HW557-CSS4BCO1.pdf PDF
CN-370000-HW557-CSS4BCO1.pdf.crdownload CRDOWNLOAD file
CN-370000-HW557-CSS4BCO2.pdf PDF
CN-370000-HW557-DC009K.pdf PDF
CN-370000-HW557-DC010G.pdf PDF
CN-370000-HW557-DC013L.pdf PDF
CN-370000-HW557-DC013Q.pdf PDF
CN-370000-HW557-DC014I.pdf PDF
CN-370000-HW557-DC01A.pdf PDF
CN-370000-HW557-DC01ACO1.pdf PDF
CN-370000-HW557-DC01ACO3.pdf PDF
CN-370000-HW557-DC01C.pdf PDF
CN-370000-HW557-DC022H.pdf PDF
CN-370000-HW557-DC02J.pdf PDF
CN-370000-HW557-DC02JCO2.pdf PDF
CN-370000-HW557-DC02L.pdf PDF
CN-370000-HW557-DC02NCO2.pdf PDF
CN-370000-HW557-DC030K.pdf PDF
CN-370000-HW557-DC031A.pdf PDF
CN-370000-HW557-DC032H.pdf PDF
CN-370000-HW557-DC032M.pdf PDF
CN-370000-HW557-DC033I.pdf PDF
CN-370000-HW557-DC033O.pdf PDF
CN-370000-HW557-DC033Q.pdf PDF
CN-370000-HW557-DC038G.pdf PDF
CN-370000-HW557-DC038i.pdf PDF
CN-370000-HW557-DC039C.pdf PDF
CN-370000-HW557-DC039E.pdf PDF
CN-370000-HW557-DC03E.pdf PDF
CN-370000-HW557-DC03F.pdf PDF
CN-370000-HW557-DC03FCO1.pdf PDF
CN-370000-HW557-DC03G.pdf PDF
CN-370000-HW557-DC03GCO2.pdf PDF
CN-370000-HW557-DC03KCO2.pdf PDF
CN-370000-HW557-DC041F.pdf PDF
CN-370000-HW557-DC041K.pdf PDF
CN-370000-HW557-DC042E.pdf PDF
CN-370000-HW557-DC045B.pdf PDF
CN-370000-HW557-DC046A.pdf PDF
CN-370000-HW557-DC046D.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEP CONTRACT NO.

Task Assignment #: Change Order No.:

Contractor Name:

Contractor Representative:

DEP Contract Manager: Phone #:

Site Name:

Site ID / Facility ID::

Description of Change [use additional pages if necessary]:

The Deliverable and Invoice Schedule is attached.

Final Deliverable:

TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:

Cost Reimbursement Fixed Fee

Original Task Amount

Task Amount Prior to this Change Order Net Increase/decrease in task amount Task amount with all change orders $0.00 $0.00 $0.00 $0.00

Original Task Completion Date:

Completion Date Prior to this Change:

Net Increase/Decrease in Task Period:

Completion Date with all Change Orders:

DEP Task Manager:

DEP Contract Manager:

Contractual Authority:

Contractor Representative:

CC: Procurement Section (MS 93) Section Representative ________

FIXED PRICE

TASK ASSIGNMENT NOTIFICATION CHANGE ORDER FORM

ITEM

$0.00

$0.00

DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).

Final Deliverable Due Date:

$0.00

$0.00

CHANGE IN TASK TIME

FEE SCHEDULE

COST PLUS FIXED FEE

TOTAL

WCP TAFORM 01_18

HW557

1DC002N

Arcadis U.S., Inc.

William Vogelsong

(850) 245-8705Theresa C. Pepe

Butler Cleaners

ERIC_4573

Arcadis containerized purge water from groundwater sampling in one drum onsite. This change order adds costs for transport and disposal of the drum.

Annual Monitoring Report 07/30/2021

$ 6,605.01 $ 0.00 $ 0.00 $ 0.00

$ 6,605.01 $ 0.00 $ 0.00 $ 0.00 $ 6,605.01

$ 110.00 $ 0.00 $ 0.00 $ 0.00 $ 110.00

$ 6,715.01

09/03/2021

09/03/2021

0 days

09/03/2021

Theresa C. Pepe Digitally signed by Theresa C. Pepe Date: 2021.08.20 14:02:38 -04'00'

Theresa C. Pepe Digitally signed by Theresa C. Pepe Date: 2021.08.20 14:02:53 -04'00'

William E. Burns, Jr. Digitally signed by William E. Burns, Jr.

Date: 2021.08.23 07:41:32 -04'00'

William D. Vogelsong Digitally signed by William D. Vogelsong Date: 2021.08.23 11:42:04 -04'00'

$ 6,715.01 $ 0.00 $ 0.00 $ 0.00

$ 6,605.01

Pepe_T Cross-Out

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

Contract Number: HW557 Task Assignment #: DC002N

Change Order #: 1

Deliverables:

Deliverable Deliverable Due Date

Annual Monitoring Report 30-Jul-21

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

FDEP approval of Annual Monitoring Report/Project Management $6,715.01

TOTAL COST $6,715.01

BWC TAFORM 01_18

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Interim Secretary

Memorandum

TO: Negotiation File Butler Cleaners

FACID NO. 16-9502315; ERIC_4573

Jacksonville, Duval County FROM: Theresa C. Pepe, Project Manager SUBJECT: Task Assignment Change Order DC002N-1 (HW557) DATE: August 20, 2021

Arcadis containerized one drum of purge water during the annual sampling event. This change order adds costs for transport and disposal of the drum. For additional information, see the August 20, 2021, change order memo from Duncan Martineau of Arcadis.

The original task assignment equaled $6,605.01. This change order adds $110.00 for a new total of $6,715.01. There is no time change to the task assignment. Arcadis may invoice according to the attached schedule.

Specific negotiated subtasks are as follows:

Subtask 2: Groundwater Sampling & Reporting Costs for transport/disposal of one drum are documented in the subcontractor quote.

FDEP COST ESTIMATE

Contractor: Arcadis U.S., Inc.

Date: 2/22/2021

Task #: SubTask 1 Project Management

Site: Butler Cleaners SubTask 2 Annual Groundwater Monitoring - 2021

Activity/Phase: SubTask 3

Project Manager: Mike O'Sullivan SubTask 4

SubTask 5

Totals 1 2 3 4 5

Labor Rate Category Staff Member

$50.00 Project Manager O'Sullivan, Michael (MOS) 4 3.8

$50.00 Senior Scientist O'Sullivan, Michael (MOS) 16 16 0 0 0

$27.91 Scientist Martineau, Duncan (DWM) 20 20 0 0 0

$30.65 Drafter/Designer Berndgen, Wendy (WDB) 3 3 0 0 0

$29.91 Project Assistant McLemore, Michele (MMc) 2 2 0 0 0

Total Hours 45 4 41 0 0 0

Direct Labor $1,698.72 $188.75 $1,509.97 $0.00 $0.00 $0.00

Overhead 57.95% $1,349.91 $149.99 $1,199.92 $0.00 $0.00 $0.00

Gen & Admin 21.29% $783.34 $87.04 $696.30 $0.00 $0.00 $0.00

Fringe 37.13% $630.73 $70.08 $560.65 $0.00 $0.00 $0.00

Total Labor $4,462.70 $495.86 $3,966.84 $0.00 $0.00 $0.00

Other Direct Costs $84.94 $9.44 $75.50 $0.00 $0.00 $0.00

Travel

Vehicle Rental $194.00 $194.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00

Per diem + Hotel $162.00 $162.00 $0.00 $0.00 $0.00 Total Travel $356.00 $356.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00

Erwin Remediation IDW $100.00 $100.00 $0.00 $0.00 $0.00 Utilities $0.00 $0.00 $0.00 $0.00 $0.00

Geo-Tek Utility Locate / GPR Survey $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $100.00 $100.00 $0.00 $0.00 $0.00 Handling Fee $10.00 $10.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $110.00 $110.00 $0.00 $0.00 $0.00

Laboratory

Analytical Costs $606.50 $606.50 $0.00 $0.00 $0.00

Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00

Sample Shipping $104.00 $104.00 $0.00 $0.00 $0.00

Total Laboratory $710.50 $710.50 $0.00 $0.00 $0.00

Field Expenses

Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $65.00 $65.00 $0.00 $0.00 $0.00

Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Analytical related) $479.60 $479.60 $0.00 $0.00 $0.00

Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Other - MAGS, recon) $0.00 $0.00 $0.00 $0.00 $0.00

Total Field Expenses $544.60 $544.60 $0.00 $0.00 $0.00

Subtotal $6,268.74 $505.30 $5,763.44 $0.00 $0.00 $0.00

Completion Fee $446.27 $49.59 $396.68 $0.00 $0.00 $0.00

Total Estimated Cost $6,715.01 $554.89 $6,160.12 $0.00 $0.00 $0.00

REV: 02/03 CEF ARCADIS Page 1

SITE: Butler Cleaners

SUBTASK 2: Annual Groundwater Monitoring - 2021

DATE: 2/22/21

LABOR

Category/Staff Work Description Hours

Annual Groundwater Monitoring - 2021 Scientist Prep, local mob/demob, full round of WLs, Sample 9 MWs; manage IDW; sample delivery 20

Senior Scientist Access, GW monitoring technical oversight and offsite notice review 2

Data Evaluation and Letter Report Senior Scientist Technical review; sign and seal report 2

Senior Scientist Data evaluation and preparation of a brief letter report 12

Drafter Figures preparation 3

Document Technician Editing; Letter report preparation 2

TOTAL LABOR: 41

TRAVEL

Vehicle Type Rate Unit Usage Totals

Van/Truck $97.00 Per Day 2 $194.00

Total Vehicle: $194.00

Meals Category/Staff Rate Unit Usage Totals

Scientist $36.00 Per Day 2 $72.00

Hotel Category/Staff Rate Unit Usage Totals

Scientist $90.00 Per Day 1 $90.00

Total Meal/Hotel: $162.00

TOTAL TRAVEL: $356.00

SUBCONTRACTOR COSTS

Total Equip.: $0.00

Services Procurement Name Purpose Rate Units Usage Totals

Erwin Remediation IDW $100.00 Drum 1 $100.00

Total Services: $100.00

TOTAL SUB: $100.00

LABORATORY COSTS

Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals

VOC (Halocarbons Only) 8260C Aqueous $66.00 1.00 9 $594.00

MN 6020 Aqueous $12.50 1.00 1 $12.50

TAT 24-hr=100% (2.0) 3-day=50% (1.5) 1-week=15% (1.15) Total Lab: $606.50

Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $104.00 Per Cooler 1 $104.00

Shipping - Small (0 to 25 lbs.) --- --- $63.00 Per cooler 0 $0.00

Total Shipping: $104.00

TOTAL LAB: $710.50

FIELD EXPENSES

Personal Protection Item Rate Unit Usage Totals

PPE Level D $28.00 Per Man Day 0 $0.00

Total PPE: $0.00

Equipment Item Rate Unit Usage Totals

Expendables Miscellaneous Expendables $32.50 Per Day 2 $65.00

Total Expendables: $65.00

Equipment Items Tubing, Poly/HDPE $0.25 Per Foot 250 $62.50

Total Equipment Items: $62.50

Equipment Kits Shallow Groundwater Sampling Kit $208.55 Day 2 $417.10

Deep Groundwater Sampling Kit $349.20 Day $0.00

Total Equipment Kits: $417.10

TOTAL EQUIPMENT: $544.60

Date: 2/22/2021

Task #: SubTask 1 Project Management

Site: Butler Cleaners SubTask 2 Annual Groundwater Monitoring - 2021

Activity/Phase: SubTask 3

Project Manager: Mike O'Sullivan SubTask 4

SubTask 5

Totals 1 2 3 4 5

Labor Rate Category Staff Member

$50.00 Project Manager O'Sullivan, Michael (MOS) 0 0.0

$50.00 Senior Scientist O'Sullivan, Michael (MOS) 0 0 0 0

$27.91 Scientist Martineau, Duncan (DWM) 0 0 0 0

$30.65 Drafter/Designer Berndgen, Wendy (WDB) 0 0 0 0

$29.91 Project Assistant McLemore, Michele (MMc) 0 0 0 0

Total Hours 0 0 0 0 0 0

Direct Labor $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 57.95% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Gen & Admin 21.29% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Fringe 37.13% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Labor $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Other Direct Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Travel

Vehicle Rental $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00

Per diem + Hotel $0.00 $0.00 $0.00 $0.00 Total Travel $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00

Erwin Remediation IDW $100.00 $100.00 $0.00 $0.00 $0.00 Utilities $0.00 $0.00 $0.00 $0.00 $0.00

Geo-Tek Utility Locate / GPR Survey $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $100.00 $100.00 $0.00 $0.00 $0.00 Handling Fee $10.00 $10.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $110.00 $110.00 $0.00 $0.00 $0.00

Laboratory

Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00

Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00

Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00

Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses

Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00

Expendables $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Other - MAGS, recon) $0.00 $0.00 $0.00 $0.00 $0.00

Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $110.00 $0.00 $110.00 $0.00 $0.00 $0.00

Completion Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $110.00 $0.00 $110.00 $0.00 $0.00 $0.00

DATE: 2/22/21

LABOR

Category/Staff Work Description Hours

Annual Groundwater Monitoring - 2021 Scientist Prep, local mob/demob, full round of WLs, Sample 9 MWs; manage IDW; sample delivery

Senior Scientist Access, GW monitoring technical oversight and offsite notice review

Data Evaluation and Letter Report Senior Scientist Technical review; sign and seal report

Senior Scientist Data evaluation and preparation of a brief letter report

Drafter Figures preparation

Document Technician Editing; Letter report preparation

TOTAL LABOR: 0

TRAVEL

Vehicle Type Rate Unit Usage Totals

Van/Truck $97.00 Per Day $0.00

Total Vehicle: $0.00

Meals Category/Staff Rate Unit Usage Totals

Scientist $36.00 Per Day $0.00

Hotel Category/Staff Rate Unit Usage Totals

Scientist $90.00 Per Day $0.00

Total Meal/Hotel: $0.00

TOTAL TRAVEL: $0.00

SUBCONTRACTOR COSTS

Total Equip.: $0.00

Services Procurement Name Purpose Rate Units Usage Totals

Erwin Remediation IDW $100.00 Drum 1 $100.00

Total Services: $100.00

TOTAL SUB: $100.00

LABORATORY COSTS

Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals

VOC (Halocarbons Only) 8260C Aqueous $66.00 1.00 $0.00

MN 6020 Aqueous $12.50 1.00 $0.00

TAT 24-hr=100% (2.0) 3-day=50% (1.5) 1-week=15% (1.15) Total Lab: $0.00

Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $104.00 Per Cooler $0.00

Shipping - Small (0 to 25 lbs.) --- --- $63.00 Per cooler 0 $0.00

Total Shipping: $0.00

TOTAL LAB: $0.00

FIELD EXPENSES

Personal Protection Item Rate Unit Usage Totals

PPE Level D $28.00 Per Man Day 0 $0.00

Total PPE: $0.00

Equipment Item Rate Unit Usage Totals

Expendables Miscellaneous Expendables $32.50 Per Day $0.00

Total Expendables: $0.00

Equipment Items Tubing, Poly/HDPE $0.25 Per Foot $0.00

Total Equipment Items: $0.00

Equipment Kits Shallow Groundwater Sampling Kit $208.55 Day $0.00

Deep Groundwater Sampling Kit $349.20 Day $0.00

Total Equipment Kits: $0.00

TOTAL EQUIPMENT: $0.00

Date: 2/22/2021

Task #: SubTask 1 Project Management

Site: Butler Cleaners SubTask 2 Annual Groundwater Monitoring - 2021

Activity/Phase: SubTask 3

Project Manager: Mike O'Sullivan SubTask 4

SubTask 5

TTotals 1 2 3 4 5

Labor Rate Category Staff Member

$50.00 Project Manager O'Sullivan, Michael (MOS) 4 3.8

$50.00 Senior Scientist O'Sullivan, Michael (MOS) 16 16 0 0 0

$27.91 Scientist Martineau, Duncan (DWM) 20 20 0 0 0

$30.65 Drafter/Designer Berndgen, Wendy (WDB) 3 3 0 0 0

$29.91 Project Assistant McLemore, Michele (MMc) 2 2 0 0 0

Total Hours 45 4 41 0 0 0

Direct Labor $1,698.72 $188.75 $1,509.97 $0.00 $0.00 $0.00

Overhead 57.95% $1,349.91 $149.99 $1,199.92 $0.00 $0.00 $0.00

Gen & Admin 21.29% $783.34 $87.04 $696.30 $0.00 $0.00 $0.00

Fringe 37.13% $630.73 $70.08 $560.65 $0.00 $0.00 $0.00

Total Labor $4,462.70 $495.86 $3,966.84 $0.00 $0.00 $0.00

Other Direct Costs $84.94 $9.44 $75.50 $0.00 $0.00 $0.00

Travel

Vehicle Rental $194.00 $194.00 $0.00 $0.00 $0.00

Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00

Air Fare $0.00 $0.00 $0.00 $0.00 $0.00

Per diem + Hotel $162.00 $162.00 $0.00 $0.00 $0.00

Total Travel $356.00 $356.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement)

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00

Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00

Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement)

Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00

Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00

Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00

Surveying $0.00 $0.00 $0.00 $0.00 $0.00

Clark Env IDW $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00

Geo-Tek Utility Locate / GPR Survey $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00

Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00

Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory

Analytical Costs $606.50 $606.50 $0.00 $0.00 $0.00

Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00

Sample Shipping $104.00 $104.00 $0.00 $0.00 $0.00

Total Laboratory $710.50 $710.50 $0.00 $0.00 $0.00

Field Expenses

Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00

Expendables $65.00 $65.00 $0.00 $0.00 $0.00

Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Analytical related) $479.60 $479.60 $0.00 $0.00 $0.00

Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Other - MAGS, recon) $0.00 $0.00 $0.00 $0.00 $0.00

Total Field Expenses $544.60 $544.60 $0.00 $0.00 $0.00

Subtotal $6,158.74 $505.30 $5,653.44 $0.00 $0.00 $0.00

Completion Fee $446.27 $49.59 $396.68 $0.00 $0.00 $0.00

Total Estimated Cost $6,605.01 $554.89 $6,050.12 $0.00 $0.00 $0.00

DATE: 2/22/21

LABOR

Category/Staff Work Description Hours

Annual Groundwater Monitoring - 2021 Scientist Prep, local mob/demob, full round of WLs, Sample 9 MWs; manage IDW; sample delivery 20

Senior Scientist Access, GW monitoring technical oversight and offsite notice review 2

Data Evaluation and Letter Report Senior Scientist Technical review; sign and seal report 2

Senior Scientist Data evaluation and preparation of a brief letter report 12

Drafter Figures preparation 3

Document Technician Editing; Letter report preparation 2

TOTAL LABOR: 41

TRAVEL

Vehicle Type Rate Unit Usage Totals

Van/Truck $97.00 Per Day 2 $194.00

Total Vehicle: $194.00

Meals Category/Staff Rate Unit Usage Totals

Scientist $36.00 Per Day 2 $72.00

Hotel Category/Staff Rate Unit Usage Totals

Scientist $90.00 Per Day 1 $90.00

Total Meal/Hotel: $162.00

TOTAL TRAVEL: $356.00

SUBCONTRACTOR COSTS

LABORATORY COSTS

Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals

VOC (Halocarbons Only) 8260C Aqueous $66.00 1.00 9 $594.00

MN 6020 Aqueous $12.50 1.00 1 $12.50

TAT 24-hr=100% (2.0) 3-day=50% (1.5) 1-week=15% (1.15) Total Lab: $606.50

Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $104.00 Per Cooler 1 $104.00

Shipping - Small (0 to 25 lbs.) --- --- $63.00 Per cooler 0 $0.00

Total Shipping: $104.00

TOTAL LAB: $710.50

FIELD EXPENSES

Personal Protection Item Rate Unit Usage Totals

Total PPE: $0.00

Equipment Item Rate Unit Usage Totals

Expendables Miscellaneous Expendables $32.50 Per Day 2 $65.00

Total Expendables: $65.00

Equipment Items Tubing, Poly/HDPE $0.25 Per Foot 250 $62.50

Total Equipment Items: $62.50

Equipment Kits Shallow Groundwater Sampling Kit $208.55 Day 2 $417.10

Deep Groundwater Sampling Kit $349.20 Day $0.00

From: Martineau, Duncan To: Pepe, Theresa Cc: OSullivan, Mike Subject: TACO Butler Cleaners, 1268 South McDuff Avenue, Jacksonville, Florida; FDEP Facility Identification ERIC_4573 Date: Friday, August 20, 2021 9:33:59 AM Attachments: image001.png image003.png image004.png image005.png image006.png image002.png HW557 Butler TACO #1.pdf Final-HW557 Cost Estimate Form (ARCADIS)_Butler_ GW Mon 2021.xlsx Delta-HW557 Cost Estimate Form (ARCADIS)_Butler_ GW Mon 2021.xlsx Original-HW557 Cost Estimate Form (ARCADIS)_Butler_ GW Mon 2021.xlsx HW557 Butler TACO #1.xls

Good Morning Theresa, Please see attached TACO #1 for Butler Cleaners. Arcadis is submitting this TACO to add the transport and disposal of 1 drum of purge water associated with groundwater sampling activities at the Site. Please let me or Mike know if you have any questions.

Regards, Duncan Martineau Staff Environmental Scientist Arcadis U.S., Inc.

1705 Metropolitan Boulevard Tallahassee, FL | 32308 | USA T +1 850 895 4741 M +1 850 508 7056 www.arcadis.com

This email and any files transmitted with it are the property of Arcadis and its affiliates. All rights, including without limitation copyright, are reserved. This email contains information that may be confidential and may also be privileged. It is for the exclusive use of the intended recipient(s). If you are not an intended recipient, please note that any form of distribution, copying or use of this communication or the information in it is strictly prohibited and may be unlawful. If you have received this communication in error, please return it to the sender and then delete the email and destroy any copies of it. While reasonable precautions have been taken to ensure that no software or viruses are present in our emails, we cannot guarantee that this email or any attachment is virus free or has not been intercepted or changed. Any opinions or other information in this email that do not relate to the official business of Arcadis are neither given nor endorsed by it.

mailto:Duncan.Martineau@arcadis.com mailto:Theresa.Pepe@FloridaDEP.gov mailto:Mike.OSullivan@arcadis.com https://nam02.safelinks.protection.outlook.com/?url=http%3A%2F%2Fwww.arcadis.com%2F&data=04%7C01%7CDuncan.Martineau%40arcadis.com%7Ca41589f6e42c45c2d46208d90b09d1b4%7C7f90057d3ea046feb07ce0568627081b%7C0%7C0%7C637552959230573597%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C1000&sdata=4fqaZU%2BU0YmtYEmWTp9FlxE71v2VF2ZW544NEF7%2BNQw%3D&reserved=0 https://nam02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.linkedin.com%2Fshowcase%2Farcadis-north-america%2F&data=04%7C01%7CDuncan.Martineau%40arcadis.com%7Ca41589f6e42c45c2d46208d90b09d1b4%7C7f90057d3ea046feb07ce0568627081b%7C0%7C0%7C637552959230593584%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C1000&sdata=ilvxwcTHP4TsbJa2ZnC%2FYwJXEPahUCihz6ME3e75D2c%3D&reserved=0 https://nam02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.linkedin.com%2Fshowcase%2Farcadis-north-america%2F&data=04%7C01%7CDuncan.Martineau%40arcadis.com%7Ca41589f6e42c45c2d46208d90b09d1b4%7C7f90057d3ea046feb07ce0568627081b%7C0%7C0%7C637552959230593584%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C1000&sdata=ilvxwcTHP4TsbJa2ZnC%2FYwJXEPahUCihz6ME3e75D2c%3D&reserved=0 https://nam02.safelinks.protection.outlook.com/?url=https%3A%2F%2Ftwitter.com%2FArcadis_NA%3Fref_src%3Dtwsrc%255Egoogle%257Ctwcamp%255Eserp%257Ctwgr%255Eauthor&data=04%7C01%7CDuncan.Martineau%40arcadis.com%7Ca41589f6e42c45c2d46208d90b09d1b4%7C7f90057d3ea046feb07ce0568627081b%7C0%7C0%7C637552959230603581%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C1000&sdata=Kx2BEpsU86%2BFp%2BZzOnbcqI2yhoxgUivwlMXNVO4dnVk%3D&reserved=0 https://nam02.safelinks.protection.outlook.com/?url=https%3A%2F%2Ftwitter.com%2FArcadis_NA%3Fref_src%3Dtwsrc%255Egoogle%257Ctwcamp%255Eserp%257Ctwgr%255Eauthor&data=04%7C01%7CDuncan.Martineau%40arcadis.com%7Ca41589f6e42c45c2d46208d90b09d1b4%7C7f90057d3ea046feb07ce0568627081b%7C0%7C0%7C637552959230603581%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C1000&sdata=Kx2BEpsU86%2BFp%2BZzOnbcqI2yhoxgUivwlMXNVO4dnVk%3D&reserved=0 https://nam02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.facebook.com%2FArcadisNorthAmerica%2F&data=04%7C01%7CDuncan.Martineau%40arcadis.com%7Ca41589f6e42c45c2d46208d90b09d1b4%7C7f90057d3ea046feb07ce0568627081b%7C0%7C0%7C637552959230603581%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C1000&sdata=P10gCRTpnggkqeC1odYwWQzoFhKkimYpv91IpheZ41A%3D&reserved=0 https://nam02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.facebook.com%2FArcadisNorthAmerica%2F&data=04%7C01%7CDuncan.Martineau%40arcadis.com%7Ca41589f6e42c45c2d46208d90b09d1b4%7C7f90057d3ea046feb07ce0568627081b%7C0%7C0%7C637552959230603581%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C1000&sdata=P10gCRTpnggkqeC1odYwWQzoFhKkimYpv91IpheZ41A%3D&reserved=0 https://nam02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.instagram.com%2Farcadisglobal%2F%3Fhl%3Den&data=04%7C01%7CDuncan.Martineau%40arcadis.com%7Ca41589f6e42c45c2d46208d90b09d1b4%7C7f90057d3ea046feb07ce0568627081b%7C0%7C0%7C637552959230613573%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C1000&sdata=%2F%2F3XzetZrca2pG%2F3r66Z%2B42jcOZMstVc0XEUqvoPMag%3D&reserved=0 https://nam02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.instagram.com%2Farcadisglobal%2F%3Fhl%3Den&data=04%7C01%7CDuncan.Martineau%40arcadis.com%7Ca41589f6e42c45c2d46208d90b09d1b4%7C7f90057d3ea046feb07ce0568627081b%7C0%7C0%7C637552959230613573%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C1000&sdata=%2F%2F3XzetZrca2pG%2F3r66Z%2B42jcOZMstVc0XEUqvoPMag%3D&reserved=0

DEP CONTRACT NO. HW557

Task Assignment #: Change Order No.: 1

Contractor Name:

Contractor Representative:

DEP Contract Manager: Phone #: (850) 245-8705

Site Name:

Site ID / Facility ID::

Description of Change [use additional pages if necessary]:

The Deliverable and Invoice Schedule is attached.

Final Deliverable: 7/30/2021

TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:

Cost Reimbursement Fixed Fee

Original Task Amount $6,605.01

Task Amount Prior to this

Change Order $6,605.01

Net Increase/decrease in task amount $165.00

Task amount with all change orders $6,770.01 $0.00 $0.00 $0.00

Original Task Completion Date: 9/3/2021

Completion Date Prior to this Change: 9/3/2021

Net Increase/Decrease in Task Period: 0

Completion Date with all Change Orders: 9/3/2021

DEP Task Manager: Date:

DEP Contract Manager: Date:

Contractual Authority: Date:

Contractor Representative: Date:

CC: Procurement Section (MS 93)

Section Representative ________

FIXED PRICE

TASK ASSIGNMENT NOTIFICATION CHANGE ORDER FORM

Arcadis U.S., Inc.

William Vogelsong

Theresa C. Pepe

ERIC_4573

DC002N

Butler Cleaners

Annual Monitoring Report

ITEM

DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).

Final Deliverable Due Date:

$165.00

$6,770.01

CHANGE IN TASK TIME

FEE SCHEDULE

COST PLUS FIXED FEE

TOTAL

Arcadis containerized purge water from groundwater sampling activities in one (1) drum on-Site. This TACO is being submitted for the transport and disposal costs associated with the drum.

WCP TAFORM 01_18

Date: 2/22/2021

Task #: SubTask 1 Project Management

Site: Butler Cleaners SubTask 2 Annual Groundwater Monitoring - 2021

Activity/Phase: SubTask 3

Project Manager: Mike O'Sullivan SubTask 4

SubTask 5

Totals 1 2 3 4 5

Labor Rate Category Staff Member

$50.00 Project Manager O'Sullivan, Michael (MOS) 4 3.8

$50.00 Senior Scientist O'Sullivan, Michael (MOS) 16 16 0 0 0

$27.91 Scientist Martineau, Duncan (DWM) 20 20 0 0 0

$30.65 Drafter/Designer Berndgen, Wendy (WDB) 3 3 0 0 0

$29.91 Project Assistant McLemore, Michele (MMc) 2 2 0 0 0

Total Hours 45 4 41 0 0 0

Direct Labor $1,698.72 $188.75 $1,509.97 $0.00 $0.00 $0.00

Overhead 57.95% $1,349.91 $149.99 $1,199.92 $0.00 $0.00 $0.00

Gen & Admin 21.29% $783.34 $87.04 $696.30 $0.00 $0.00 $0.00

Fringe 37.13% $630.73 $70.08 $560.65 $0.00 $0.00 $0.00

Total Labor $4,462.70 $495.86 $3,966.84 $0.00 $0.00 $0.00

Other Direct Costs $84.94 $9.44 $75.50 $0.00 $0.00 $0.00

Travel

Vehicle Rental $194.00 $194.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00

Per diem + Hotel $162.00 $162.00 $0.00 $0.00 $0.00 Total Travel $356.00 $356.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00

Erwin Remediation IDW $150.00 $150.00 $0.00 $0.00 $0.00 Utilities $0.00 $0.00 $0.00 $0.00 $0.00

Geo-Tek Utility Locate / GPR Survey $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $150.00 $150.00 $0.00 $0.00 $0.00 Handling Fee $15.00 $15.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $165.00 $165.00 $0.00 $0.00 $0.00

Laboratory

Analytical Costs $606.50 $606.50 $0.00 $0.00 $0.00

Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00

Sample Shipping $104.00 $104.00 $0.00 $0.00 $0.00

Total Laboratory $710.50 $710.50 $0.00 $0.00 $0.00

Field Expenses

Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $65.00 $65.00 $0.00 $0.00 $0.00 Tubing, Poly/HDPE $62.50 $62.50 $0.00 $0.00 $0.00

Shallow GW Sampling Kit $417.10 $417.10 $0.00 $0.00 $0.00

Equipment (Other - MAGS, recon) $0.00 $0.00 $0.00 $0.00 $0.00

Total Field Expenses $544.60 $544.60 $0.00 $0.00 $0.00

Subtotal $6,323.74 $505.30 $5,818.44 $0.00 $0.00 $0.00

Completion Fee $446.27 $49.59 $396.68 $0.00 $0.00 $0.00

Total Estimated Cost $6,770.01 $554.89 $6,215.12 $0.00 $0.00 $0.00

DATE: 2/22/21

LABOR

Category/Staff Work Description Hours

Annual Groundwater Monitoring - 2021

Scientist Prep, local mob/demob, full round of WLs, Sample 9 MWs; manage IDW; sample delivery 20

Senior Scientist Access, GW monitoring technical oversight and offsite notice review 2

Data Evaluation and Letter Report

Senior Scientist Technical review; sign and seal report 2

Senior Scientist Data evaluation and preparation of a brief letter report 12

Drafter Figures preparation 3

Document Technician Editing; Letter report preparation 2

TOTAL LABOR: 41

TRAVEL

Vehicle

Type Rate Unit Usage Totals

Van/Truck $97.00 Per Day 2 $194.00

Total Vehicle: $194.00

Meals

Category/Staff Rate Unit Usage Totals

Scientist $36.00 Per Day 2 $72.00

Hotel

Scientist $90.00 Per Day 1 $90.00

Total Meal/Hotel: $162.00

TOTAL TRAVEL: $356.00

SUBCONTRACTOR COSTS

Total Equip.: $0.00

Services Procurement

Name Purpose Rate Units Usage Totals

Erwin Remediation IDW $150.00 Drum 1 $150.00

Total Services: $150.00

TOTAL SUB: $150.00

LABORATORY COSTS

Analytical Costs

Parameter Method Media Rate Turn Around Total Samples Totals

VOC (Halocarbons Only) 8260C Aqueous $66.00 1.00 9 $594.00

MN 6020 Aqueous $12.50 1.00 1 $12.50

TAT 24-hr=100% (2.0) 3-day=50% (1.5) 1-week=15% (1.15) Total Lab: $606.50

Rate Units Usage

Shipping - Large (25 to 50 lbs.) --- --- $104.00 Per Cooler 1 $104.00

Shipping - Small (0 to 25 lbs.) --- --- $63.00 Per cooler 0 $0.00

Total Shipping: $104.00

TOTAL LAB: $710.50

FIELD EXPENSES

Personal Protection

Item Rate Unit Usage Totals

PPE Level D $28.00 Per Man Day 0 $0.00

Total PPE: $0.00

Equipment

Expendables

Miscellaneous Expendables $32.50 Per Day 2 $65.00

Total Expendables: $65.00

Equipment Items

Tubing, Poly/HDPE $0.25 Per Foot 250 $62.50

Total Equipment Items: $62.50

Equipment Kits

Shallow Groundwater Sampling Kit $208.55 Day 2 $417.10

Deep Groundwater Sampling Kit $349.20 Day $0.00

Totals 1 2 3 4 5

$50.00 Project Manager O'Sullivan, Michael (MOS) 0 0.0

$50.00 Senior Scientist O'Sullivan, Michael (MOS) 0 0 0 0

$27.91 Scientist Martineau, Duncan (DWM) 0 0 0 0

$30.65 Drafter/Designer Berndgen, Wendy (WDB) 0 0 0 0

$29.91 Project Assistant McLemore, Michele (MMc) 0 0 0 0

Total Hours 0 0 0 0 0 0

Direct Labor $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 57.95% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Gen & Admin 21.29% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Fringe 37.13% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Labor $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Other Direct Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Vehicle Rental $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00

Per diem + Hotel $0.00 $0.00 $0.00 $0.00 Total Travel $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement)

$0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00

Erwin Remediation IDW $150.00 $150.00 $0.00 $0.00 $0.00 Utilities $0.00 $0.00 $0.00 $0.00 $0.00

Geo-Tek Utility Locate / GPR Survey $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $150.00 $150.00 $0.00 $0.00 $0.00 Handling Fee $15.00 $15.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $165.00 $165.00 $0.00 $0.00 $0.00

Analytical Costs $0.00 $0.00 $0.00 $0.00

Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00

Sample Shipping $0.00 $0.00 $0.00 $0.00

Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00

Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 Tubing, Poly/HDPE $0.00 $0.00 $0.00 $0.00

Shallow GW Sampling Kit $0.00 $0.00 $0.00 $0.00

Equipment (Other - MAGS, recon) $0.00 $0.00 $0.00 $0.00 $0.00

Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $165.00 $0.00 $165.00 $0.00 $0.00 $0.00

Completion Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $165.00 $0.00 $165.00 $0.00 $0.00 $0.00

Scientist Prep, local mob/demob, full round of WLs, Sample 9 MWs; manage IDW; sample delivery

Senior Scientist Access, GW monitoring technical oversight and offsite notice review

Senior Scientist Technical review; sign and seal report

Senior Scientist Data evaluation and preparation of a brief letter report

Drafter Figures preparation

Document Technician Editing; Letter report preparation

TOTAL LABOR: 0

Van/Truck $97.00 Per Day $0.00

Total Vehicle: $0.00

Scientist $36.00 Per Day $0.00

Scientist $90.00 Per Day $0.00

Total Meal/Hotel: $0.00

TOTAL TRAVEL: $0.00

Total Equip.: $0.00

Services Procurement

Name Purpose Rate Units Usage Totals

Erwin Remediation IDW $150.00 Drum 1 $150.00

Total Services: $150.00

TOTAL SUB: $150.00

VOC (Halocarbons Only) 8260C Aqueous $66.00 1.00 $0.00

MN 6020 Aqueous $12.50 1.00 $0.00

TAT 24-hr=100% (2.0) 3-day=50% (1.5) 1-week=15% (1.15) Total Lab: $0.00

Shipping - Large (25 to 50 lbs.) --- --- $104.00 Per Cooler $0.00

Total Shipping: $0.00

TOTAL LAB: $0.00

Miscellaneous Expendables $32.50 Per Day $0.00

Total Expendables: $0.00

Tubing, Poly/HDPE $0.25 Per Foot $0.00

Total Equipment Items: $0.00

Shallow Groundwater Sampling Kit $208.55 Day $0.00

Total Equipment Kits: $0.00

TOTAL EQUIPMENT: $0.00

Totals 1 2 3 4

$50.00 Project Manager O'Sullivan, Michael (MOS) 4 3.8

$50.00 Senior Scientist O'Sullivan, Michael (MOS) 16 16 0 0

$27.91 Scientist Martineau, Duncan (DWM) 20 20 0 0

$30.65 Drafter/Designer Berndgen, Wendy (WDB) 3 3 0 0

$29.91 Project Assistant McLemore, Michele (MMc) 2 2 0 0

Total Hours 45 4 41 0 0

Direct Labor $1,698.72 $188.75 $1,509.97 $0.00 $0.00

Overhead 57.95% $1,349.91 $149.99 $1,199.92 $0.00 $0.00

Gen & Admin 21.29% $783.34 $87.04 $696.30 $0.00 $0.00

Fringe 37.13% $630.73 $70.08 $560.65 $0.00 $0.00

Total Labor $4,462.70 $495.86 $3,966.84 $0.00 $0.00

Other Direct Costs $84.94 $9.44 $75.50 $0.00 $0.00

Vehicle Rental $194.00 $194.00 $0.00 $0.00

Mileage Costs $0.00 $0.00 $0.00 $0.00

Per diem + Hotel $162.00 $162.00 $0.00 $0.00

Total Travel $356.00 $356.00 $0.00 $0.00

Analytical Costs $606.50 $606.50 $0.00 $0.00

Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00

Sample Shipping $104.00 $104.00 $0.00 $0.00

Total Laboratory $710.50 $710.50 $0.00 $0.00

Personal Protection $0.00 $0.00 $0.00 $0.00 Expendables $65.00 $65.00 $0.00 $0.00 Tubing, Poly/HDPE $62.50 $62.50 $0.00 $0.00

Shallow GW Sampling Kit $417.10 $417.10 $0.00 $0.00

Equipment (Other - MAGS, recon) $0.00 $0.00 $0.00 $0.00

Total Field Expenses $544.60 $544.60 $0.00 $0.00

Subtotal $6,158.74 $505.30 $5,653.44 $0.00 $0.00

Completion Fee $446.27 $49.59 $396.68 $0.00 $0.00

Total Estimated Cost $6,605.01 $554.89 $6,050.12 $0.00 $0.00

Scientist Prep, local mob/demob, full round of WLs, Sample 9 MWs; manage IDW; sample delivery 20

Senior Scientist Access, GW monitoring technical oversight and offsite notice review 2

Senior Scientist Technical review; sign and seal report 2

Senior Scientist Data evaluation and preparation of a brief letter report 12

Drafter Figures preparation 3

Document Technician Editing; Letter report preparation 2

TOTAL LABOR: 41

Van/Truck $97.00 Per Day 2 $194.00

Total Vehicle: $194.00

Scientist $36.00 Per Day 2 $72.00

Scientist $90.00 Per Day 1 $90.00

Total Meal/Hotel: $162.00

TOTAL TRAVEL: $356.00

VOC (Halocarbons Only) 8260C Aqueous $66.00 1.00 9 $594.00

MN 6020 Aqueous $12.50 1.00 1 $12.50

TAT 24-hr=100% (2.0) 3-day=50% (1.5) 1-week=15% (1.15) Total Lab: $606.50

Shipping - Large (25 to 50 lbs.) --- --- $104.00 Per Cooler 1 $104.00

Total Shipping: $104.00

TOTAL LAB: $710.50

Miscellaneous Expendables $32.50 Per Day 2 $65.00

Total Expendables: $65.00

Tubing, Poly/HDPE $0.25 Per Foot 250 $62.50

Total Equipment Items: $62.50

Shallow Groundwater Sampling Kit $208.55 Day 2 $417.10

Cost Estimate

Contractor: Arcadis U.S., Inc.

Date: 2/22/2021

Task #: SubTask 1 Project Management SubTask 6

Site: Butler Cleaners SubTask 2 Annual Groundwater Monitoring - 2021 SubTask 7

Activity/Phase: SubTask 3 SubTask 8

Project Manager: Mike O'Sullivan SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10

Labor Rate Category Staff Member

$50.00 Project Manager O'Sullivan, Michael (MOS) 4 3.8

$95.33 Principal Engineer Bedessem, Jim (JMB) 0 0 0 0 0 0 0 0 0 0

$81.47 Principal Scientist Vogelsong, William (WDV) 0 0 0 0 0 0 0 0 0 0

$77.95 Principal Engineer Suarez, Gus (GS) 0 0 0 0 0 0 0 0 0 0

Principal Engineer Vacant 0 0 0 0 0 0 0 0 0 0

$71.84 Principal Scientist McManus, Andrew (ATM) 0 0 0 0 0 0 0 0 0 0

$59.89 Principal Scientist Burke, Brian (BRB) 0 0 0 0 0 0 0 0 0 0

$59.46 Principal Engineer Perella, John (JFP) 0 0 0 0 0 0 0 0 0 0

$50.00 mmclemore: mmclemore:

Capped Rate Senior Scientist O'Sullivan, Michael (MOS) 16 16 0 0 0 0 0 0 0 0

$50.00 mmclemore: mmclemore:

Capped Rate Senior Engineer Shah, Adarsh (AS) 0 0 0 0 0 0 0 0 0 0

$50.00 mmclemore: mmclemore:

Capped Rate Senior Scientist McGlone, Douglas (DMc) 0 0 0 0 0 0 0 0 0 0

$47.15 Senior Scientist Larenas, Athnony (AOL) 0 0 0 0 0 0 0 0 0 0

$44.29 Senior Scientist O'Connell, Patrick (PJO) 0 0 0 0 0 0 0 0 0 0

$44.38 Senior Scientist Jeffries, Shannon (SMJ) 0 0 0 0 0 0 0 0 0 0

$42.23 Project Engineer Romero Cotrino, Camilo (CRC) 0 0 0 0 0 0 0 0 0 0

$41.35 Project Engineer Hays, Timothy (TPH) 0 0 0 0 0 0 0 0 0 0

$39.34 Staff Engineer Hanna, Chad (CMH) 0 0 0 0 0 0 0 0 0 0

$38.24 Staff Scientist Riley, Joel (JR) 0 0 0 0 0 0 0 0 0 0

$32.37 Staff Scientist Chest, Mark (MAC) 0 0 0 0 0 0 0 0 0 0

$33.04 Staff Engineer Vail, Zachary (ZTV) 0 0 0 0 0 0 0 0 0 0

$28.94 mmclemore: mmclemore:

Capped Rate Scientist McBath, Brandon (BMc) 0 0 0 0 0 0 0 0 0 0

$27.69 Scientist Guarino, Andrew (AG) 0 0 0 0 0 0 0 0 0 0

$25.02 Scientist Thomas, Jason (JBT) 0 0 0 0 0 0 0 0 0 0

$27.91 Scientist Martineau, Duncan (DWM) 20 20 0 0 0 0 0 0 0 0

$27.60 Scientist Brooks, Eric (EAB) 0 0 0 0 0 0 0 0 0 0

$26.45 Scientist Brutscher, Katherine (KEB) 0 0 0 0 0 0 0 0 0 0

$26.06 Scientist Boros, Anthony (AB) 0 0 0 0 0 0 0 0 0 0

$27.56 Scientist Cochran, Laura 0 0 0 0 0 0 0 0 0 0

$32.59 Technician Welch, David (DJW) 0 0 0 0 0 0 0 0 0 0

$28.29 Technician Dankerl, David (DJD) 0 0 0 0 0 0 0 0 0 0

$21.32 Technician Fortner, Kendrix (KLF) 0 0 0 0 0 0 0 0 0 0

$21.28 Technician Rhodes, John (JAR) 0 0 0 0 0 0 0 0 0 0

Technician Vacant 0 0 0 0 0 0 0 0 0 0

Survey Technician Vacant 0 0 0 0 0 0 0 0 0 0

$35.93 Survey Manager Schacht, Roland (RS) 0 0 0 0 0 0 0 0 0 0

$39.67 ltmartin: ltmartin:

Capped Rate Drafter/Designer Oliva, Brian (BO) 0 0 0 0 0 0 0 0 0 0

$30.99 Drafter/Designer Richards, Jim (JR) 0 0 0 0 0 0 0 0 0 0

$30.65 Drafter/Designer Berndgen, Wendy (WDB) 3 3 0 0 0 0 0 0 0 0

$35.00 ltmartin: ltmartin:

Capped Rate mmclemore: mmclemore:

Capped Rate mmclemore: mmclemore:

Capped Rate mmclemore: mmclemore:

Capped Rate ltmartin: ltmartin:

Capped Rate mmclemore: mmclemore:

Capped Rate Document Technician Ballheim, Debra (DJB) 0 0 0 0 0 0 0 0 0 0

$25.74 Document Technician Embras, Susan (SRE) 0 0 0 0 0 0 0 0 0 0

$29.91 Project Assistant McLemore, Michele (MMc) 2 2 0 0 0 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0

$0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 45 4 41 0 0 0 0 0 0 0 0

Direct Labor $1,698.72 $188.75 $1,509.97 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 57.95% $1,349.91 $149.99 $1,199.92 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Gen & Admin 21.29% $783.34 $87.04 $696.30 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Fringe 37.13% $630.73 $70.08 $560.65 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Labor $4,462.70 $495.86 $3,966.84 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Other Direct Costs $84.94 $9.44 $75.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Travel

Vehicle Rental $194.00 $194.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Per diem + Hotel $162.00 $162.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Travel $356.00 $356.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement)

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement)

Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Erwin Remediation IDW $150.00 $150.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Geo-Tek Utility Locate / GPR Survey $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $150.00 $150.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Handling Fee $15.00 $15.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Subcontractor Cost $165.00 $165.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory

Analytical Costs $606.50 $606.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Sample Shipping $104.00 $104.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Laboratory $710.50 $710.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses

Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Expendables $65.00 $65.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Tubing, Poly/HDPE $62.50 $62.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Shallow GW Sampling Kit $417.10 $417.10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Other - MAGS, recon) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Field Expenses $544.60 $544.60 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $6,323.74 $505.30 $5,818.44 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Completion Fee $446.27 $49.59 $396.68 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $6,770.01 $554.89 $6,215.12 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

&"CG Times,Bold"&16FDEP COST ESTIMATE

&"Courier New,Bold"&10REV: 02/03 &"Courier New,Bold"&10CEF ARCADIS &"Courier New,Bold"&10Page &P

Formula Sheet

Project Management

Subtask 1 Subtask 2 Subtask 3 Subtask 4 Subtask 5 Subtask 6 Subtask 7 Subtask 8 Subtask 9 Subtask 10

Labor Costs $190.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$800.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$558.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$91.95 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$59.82 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 total labor dollars $190.00 $1,509.97 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Project Management $1,509.97 = sum of Direct Labor Costs from Subtasks 2 through 10

$188.75 =12.5% of Direct Labor Costs (Project Management)

3.775 = Hours of Project Management (based on hourly salary of the Contractor Project Manager)

Subcontractor $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Service Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$15.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$15.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

ST 2

SITE: Butler Cleaners

SUBTASK 2: Annual Groundwater Monitoring - 2021

DATE: 2/22/21

LABOR

Category/Staff Work Description Hours

Annual Groundwater Monitoring - 2021

Scientist Prep, local mob/demob, full round of WLs, Sample 9 MWs; manage IDW; sample delivery 20

Senior Scientist Access, GW monitoring technical oversight and offsite notice review 2

Data Evaluation and Letter Report

Senior Scientist Technical review; sign and seal report 2

Senior Scientist Data evaluation and preparation of a brief letter report 12

Scientist Data evaluation

Drafter Figures preparation 3

Document Technician Editing; Letter report preparation 2

(Subtask Title)

Principal 0

Senior 0

Project 0

Technician 0

(Subtask Title)

Principal 0

Senior 0

Project 0

Technician 0

TOTAL LABOR: 41

TRAVEL

Vehicle

Type Rate Unit Usage Totals

Automobile $68.00 Per Day 0 $0.00

Van/Truck $97.00 Per Day 2 $194.00

Van/Truck $420.00 Per Week 0 $0.00

Total Vehicle: $194.00

Meals

Category/Staff Rate Unit Usage Totals

Scientist $36.00 Per Day 2 $72.00

$36.00 Per Day 0 $0.00

Hotel

Category/Staff Rate Unit Usage Totals

Scientist $90.00 Per Day 1 $90.00

$90.00 Per Day 0 $0.00

Total Meal/Hotel: $162.00

TOTAL TRAVEL: $356.00

SUBCONTRACTOR COSTS

Equipment Procurement

Name Equipment Rate Units Usage Totals

0 $0.00

Total Equip.: $0.00

Services Procurement

Name Purpose Rate Units Usage Totals

NAME OF COMPANY Direct-push services $0.00 Lump Sum 0 $0.00

NAME OF COMPANY Drilling services (DPT, MAG wells, SBs, VPs) $0.00 Lump Sum 0 $0.00

Erwin Remediation IDW $150.00 Drum 1 $150.00

NAME OF COMPANY On-site Mobile Laboratory analysis $0.00 Lump Sum 0 $0.00

NAME OF COMPANY Utility Locate / GPR Survey $0.00 Lump Sum 0 $0.00

NAME OF COMPANY Utilities -Telemetry $0.00 Per Month 0 $0.00

Handling Fee $20.00 Per Month 0 $0.00

Total Services: $150.00

TOTAL SUB: $150.00

LABORATORY COSTS

Analytical Costs

Parameter Method Media Rate Turn Around Total Samples Totals

VOC (Halocarbons Only) 8260C Aqueous $66.00 1.00 9 $594.00

TRPH FL PRO Soil $84.00 1.00 0 $0.00

SVOCs 8270 Soil/Sediment $220.00 1.00 0 $0.00

7 RCRA Metals (As/Ba/Cd/Cr/Pb/Se/Ag) 6020 Soil/Sediment $87.50 1.00 0 $0.00

MN 6020 Aqueous $12.50 1.00 1 $12.50

1 RCRA Metal (Hg) 7470 Soil/Sediment $23.00 1.00 0 $0.00

Herbicides 8151 Soil $130.00 1.00 0 $0.00

Organochlorine Pesticides / PCBs 8081/8082 Soil/Sediment $150.00 1.00 0 $0.00

Dioxins/Dibenzofurans 8290 Soil $865.00 1.00 0 $0.00 total Cyanide 335.3 Soil/Sediment $35.00 1.00 0 $0.00 total Phenols 420.2 Soil $31.00 1.00 0 $0.00

Priority Pollutant Organics Full Suite Aqueous $660.00 1.00 0 $0.00

TAT 24-hr=100% (2.0) 3-day=50% (1.5) 1-week=15% (1.15) Total Lab: $606.50

Rate Units Usage

Shipping - Large (25 to 50 lbs.) --- --- $104.00 Per Cooler 1 $104.00

Shipping - Small (0 to 25 lbs.) --- --- $63.00 Per cooler 0 $0.00

Total Shipping: $104.00

TOTAL LAB: $710.50

FIELD EXPENSES

Personal Protection

Item Rate Unit Usage Totals

PPE Level D $28.00 Per Man Day 0 $0.00

PPE Level C $110.00 Per Man Day 0 $0.00

PPE Level B $172.50 Per Man Day 0 $0.00

Total PPE: $0.00

Equipment

Item Rate Unit Usage Totals

Expendables

Miscellaneous Expendables $32.50 Per Day 2 $65.00

Total Expendables: $65.00

Equipment Items

PID/FID Combo or FID $106.70 Per Day 0 $0.00

PID/FID Combo or FID $426.80 Per Week 0 $0.00

Thermal Anemometer $17.50 Per Day 0 $0.00

Vacuum Gauges (low, med & high) $19.40 Per Day 0 $0.00

Bailer, HDPE, Disp $4.85 Per Bailer 0 $0.00

Water Level: Electric Tape $19.40 Per Day 0 $0.00

Water Level: Electric Tape $77.60 Per Week 0 $0.00