This document comprises Task Assignment Change Order No. 3 under Florida Department of Environmental Protection (FDEP) Contract HW557, Task Assignment DC002N, between the FDEP and contractor Arcadis U.S., Inc. The work is being performed at the Butler Cleaners facility (ERIC_4573) in Jacksonville, Duval County, Florida. Theresa C. Pepe serves as the DEP Contract Manager, with William Vogelsong as the Arcadis contractor representative. The change order was executed on September 9, 2021, and includes supporting documentation from subcontractor Erwin Remediation, Inc.
Change Order No. 3 adds $550.00 to the task assignment cost for hazardous waste disposal of one drum of purge water from groundwater sampling that was determined to be hazardous based on laboratory results. The original task amount prior to this change order was $6,715.01; the net increase is $550.00, bringing the total task amount with all change orders to $7,265.01. This represents the difference in subcontractor costs between non-hazardous and hazardous disposal, with Erwin Remediation quoting a flat fee of $600.00 for transportation and disposal of the hazardous drum. The task completion date remains unchanged at September 17, 2021, with no extension to the task period. The deliverable is an Annual Monitoring Report due July 30, 2021, and invoicing occurs upon FDEP approval of the Annual Monitoring Report and project management services.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEP CONTRACT NO.
Task Assignment #: Change Order No.:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
Site Name:
Site ID / Facility ID::
Description of Change [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverable:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
Cost Reimbursement Fixed Fee
Original Task Amount
Task Amount Prior to this Change Order Net Increase/decrease in task amount Task amount with all change orders $0.00 $0.00 $0.00 $0.00
Original Task Completion Date:
Completion Date Prior to this Change:
Net Increase/Decrease in Task Period:
Completion Date with all Change Orders:
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93) Section Representative ________
FIXED PRICE
TASK ASSIGNMENT NOTIFICATION CHANGE ORDER FORM
ITEM
$0.00
$0.00
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
Final Deliverable Due Date:
$0.00
$0.00
CHANGE IN TASK TIME
FEE SCHEDULE
COST PLUS FIXED FEE
TOTAL
WCP TAFORM 01_18
HW557
3DC002N
Arcadis U.S., Inc.
William Vogelsong
(850) 245-8705Theresa C. Pepe
Butler Cleaners
ERIC_4573
Arcadis containerized purge water from groundwater sampling in one drum onsite. Based on laboratory results, the drum must be disposed of as hazardous. This change order adds the difference in subcontractor costs for hazardous as opposed to non-hazardous disposal.
Annual Monitoring Report 07/30/2021
$ 6,605.01 $ 0.00 $ 0.00 $ 0.00
$ 6,715.01 $ 0.00 $ 0.00 $ 0.00 $ 6,715.01
$ 550.00 $ 0.00 $ 0.00 $ 0.00 $ 550.00
$ 7,265.01
09/03/2021
09/17/2021
0 days
09/17/2021
Theresa C. Pepe Digitally signed by Theresa C. Pepe Date: 2021.09.09 15:13:03 -04'00'
Theresa C. Pepe Digitally signed by Theresa C. Pepe Date: 2021.09.09 15:13:13 -04'00'
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2021.09.10 08:08:10 -04'00'
Digitally signed by: Mike O'Sullivan DN: CN = Mike O'Sullivan email = mike.osullivan@arcadis.
com C = AD Date: 2021.09.10 08:55:54 -05'00'
Mike O'Sullivan
$ 7,265.01 $ 0.00 $ 0.00 $ 0.00
$ 6,605.01
Pepe_T Cross-Out
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number: HW557 Task Assignment #: DC002N
Change Order #: 3
Deliverables:
Deliverable Deliverable Due Date
Annual Monitoring Report 30-Jul-21
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
FDEP approval of Annual Monitoring Report/Project Management $7,265.01
TOTAL COST $7,265.01
BWC TAFORM 01_18
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO: Negotiation File Butler Cleaners
FACID NO. 16-9502315; ERIC_4573
Jacksonville, Duval County FROM: Theresa C. Pepe, Project Manager SUBJECT: Task Assignment Change Order DC002N-3 (HW557) DATE: September 9, 2021
Arcadis containerized one drum of purge water during the annual sampling event. The drum must be disposed of as hazardous based on laboratory results. This change order adds subcontractor costs for hazardous transport and disposal of the drum. For additional information, see the September 8, 2021, change order memo from Mike O’Sullivan of Arcadis.
The original task assignment equaled $6,715.01. This change order adds $550.00 for a new total of $7,265.01. There is no time change to the task assignment. Arcadis may invoice according to the attached schedule.
Specific negotiated subtasks are as follows:
Subtask 2: Groundwater Sampling & Reporting Costs for transport/disposal of one drum as hazardous waste are documented in the subcontractor quote.
FDEP COST ESTIMATE
Contractor: Arcadis U.S., Inc. FINAL
Date: 2/22/2021
Task #: SubTask 1 Project Management
Site: Butler Cleaners SubTask 2 Annual Groundwater Monitoring - 2021
Activity/Phase: SubTask 3
Project Manager: Mike O'Sullivan SubTask 4
SubTask 5
Totals 1 2 3 4 5
Labor Rate Category Staff Member
$50.00 Project Manager O'Sullivan, Michael (MOS) 4 3.8
$50.00 Senior Scientist O'Sullivan, Michael (MOS) 16 16 0 0 0
$27.91 Scientist Martineau, Duncan (DWM) 20 20 0 0 0
$30.65 Drafter/Designer Berndgen, Wendy (WDB) 3 3 0 0 0
$29.91 Project Assistant McLemore, Michele (MMc) 2 2 0 0 0
Total Hours 45 4 41 0 0 0
Direct Labor $1,698.72 $188.75 $1,509.97 $0.00 $0.00 $0.00
Overhead 57.95% $1,349.91 $149.99 $1,199.92 $0.00 $0.00 $0.00
Gen & Admin 21.29% $783.34 $87.04 $696.30 $0.00 $0.00 $0.00
Fringe 37.13% $630.73 $70.08 $560.65 $0.00 $0.00 $0.00
Total Labor $4,462.70 $495.86 $3,966.84 $0.00 $0.00 $0.00
Other Direct Costs $84.94 $9.44 $75.50 $0.00 $0.00 $0.00
Travel
Vehicle Rental $194.00 $194.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00
Per diem + Hotel $162.00 $162.00 $0.00 $0.00 $0.00 Total Travel $356.00 $356.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00
Erwin Remediation IDW $600.00 $600.00 $0.00 $0.00 $0.00 Utilities $0.00 $0.00 $0.00 $0.00 $0.00
Geo-Tek Utility Locate / GPR Survey $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $600.00 $600.00 $0.00 $0.00 $0.00 Handling Fee $60.00 $60.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $660.00 $660.00 $0.00 $0.00 $0.00
Laboratory
Analytical Costs $606.50 $606.50 $0.00 $0.00 $0.00
Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00
Sample Shipping $104.00 $104.00 $0.00 $0.00 $0.00
Total Laboratory $710.50 $710.50 $0.00 $0.00 $0.00
Field Expenses
Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $65.00 $65.00 $0.00 $0.00 $0.00
Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (Analytical related) $479.60 $479.60 $0.00 $0.00 $0.00
Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (Other - MAGS, recon) $0.00 $0.00 $0.00 $0.00 $0.00
Total Field Expenses $544.60 $544.60 $0.00 $0.00 $0.00
Subtotal $6,818.74 $505.30 $6,313.44 $0.00 $0.00 $0.00
Completion Fee $446.27 $49.59 $396.68 $0.00 $0.00 $0.00
Total Estimated Cost $7,265.01 $554.89 $6,710.12 $0.00 $0.00 $0.00
REV: 02/03 CEF ARCADIS Page 1
SITE: Butler Cleaners
SUBTASK 2: Annual Groundwater Monitoring - 2021
DATE: 2/22/21
LABOR
Category/Staff Work Description Hours
Annual Groundwater Monitoring - 2021 Scientist Prep, local mob/demob, full round of WLs, Sample 9 MWs; manage IDW; sample delivery 20
Senior Scientist Access, GW monitoring technical oversight and offsite notice review 2
Data Evaluation and Letter Report Senior Scientist Technical review; sign and seal report 2
Senior Scientist Data evaluation and preparation of a brief letter report 12
Drafter Figures preparation 3
Document Technician Editing; Letter report preparation 2
TOTAL LABOR: 41
TRAVEL
Vehicle Type Rate Unit Usage Totals
Van/Truck $97.00 Per Day 2 $194.00
Total Vehicle: $194.00
Meals Category/Staff Rate Unit Usage Totals
Scientist $36.00 Per Day 2 $72.00
Hotel Category/Staff Rate Unit Usage Totals
Scientist $90.00 Per Day 1 $90.00
Total Meal/Hotel: $162.00
TOTAL TRAVEL: $356.00
SUBCONTRACTOR COSTS
Total Equip.: $0.00
Services Procurement Name Purpose Rate Units Usage Totals
Erwin Remediation IDW $600.00 Drum 1 $600.00
Handling Fee $60.00 0 $0.00
Total Services: $600.00
TOTAL SUB: $600.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
VOC (Halocarbons Only) 8260C Aqueous $66.00 1.00 9 $594.00
MN 6020 Aqueous $12.50 1.00 1 $12.50
TAT 24-hr=100% (2.0) 3-day=50% (1.5) 1-week=15% (1.15) Total Lab: $606.50
Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $104.00 Per Cooler 1 $104.00
Shipping - Small (0 to 25 lbs.) --- --- $63.00 Per cooler 0 $0.00
Total Shipping: $104.00
TOTAL LAB: $710.50
FIELD EXPENSES
Personal Protection Item Rate Unit Usage Totals
Total PPE: $0.00
Equipment Item Rate Unit Usage Totals
Expendables Miscellaneous Expendables $32.50 Per Day 2 $65.00
Total Expendables: $65.00
Equipment Items Tubing, Poly/HDPE $0.25 Per Foot 250 $62.50
Total Equipment Items: $62.50
Equipment Kits Shallow Groundwater Sampling Kit $208.55 Day 2 $417.10
Deep Groundwater Sampling Kit $349.20 Day $0.00
Total Equipment Kits: $417.10
TOTAL EQUIPMENT: $544.60
Contractor: Arcadis U.S., Inc. DELTA
Date: 2/22/2021
Task #: SubTask 1 Project Management
Site: Butler Cleaners SubTask 2 Annual Groundwater Monitoring - 2021
Activity/Phase: SubTask 3
Project Manager: Mike O'Sullivan SubTask 4
SubTask 5
Totals 1 2 3 4 5
Labor Rate Category Staff Member
$50.00 Project Manager O'Sullivan, Michael (MOS) 0 0.0
$50.00 Senior Scientist O'Sullivan, Michael (MOS) 0 0 0 0 0
$27.91 Scientist Martineau, Duncan (DWM) 0 0 0 0 0
$30.65 Drafter/Designer Berndgen, Wendy (WDB) 0 0 0 0 0
$29.91 Project Assistant McLemore, Michele (MMc) 0 0 0 0 0
Total Hours 0 0 0 0 0 0
Direct Labor $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 57.95% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Gen & Admin 21.29% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Fringe 37.13% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Labor $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Other Direct Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Travel
Vehicle Rental $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00
Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00
Erwin Remediation IDW ($100.00) ($100.00) $0.00 $0.00 $0.00 Erwin Remediation IDW $600.00 $600.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 Geo-Tek Utility Locate / GPR Survey $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $500.00 $500.00 $0.00 $0.00 $0.00 Handling Fee $50.00 $50.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $550.00 $550.00 $0.00 $0.00 $0.00
Laboratory
Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00
Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00
Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00
Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses
Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00
Expendables $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (Other - MAGS, recon) $0.00 $0.00 $0.00 $0.00 $0.00
Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $550.00 $0.00 $550.00 $0.00 $0.00 $0.00
Completion Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $550.00 $0.00 $550.00 $0.00 $0.00 $0.00
DATE: 2/22/21
LABOR
Category/Staff Work Description Hours
Annual Groundwater Monitoring - 2021 Scientist Prep, local mob/demob, full round of WLs, Sample 9 MWs; manage IDW; sample delivery 0
Senior Scientist Access, GW monitoring technical oversight and offsite notice review 0
Data Evaluation and Letter Report Senior Scientist Technical review; sign and seal report 0
Senior Scientist Data evaluation and preparation of a brief letter report 0
Drafter Figures preparation 0
Document Technician Editing; Letter report preparation 0
TOTAL LABOR: 0
TRAVEL
Vehicle Type Rate Unit Usage Totals
Van/Truck $97.00 Per Day $0.00
Total Vehicle: $0.00
Meals Category/Staff Rate Unit Usage Totals
Scientist $36.00 Per Day $0.00
Hotel Category/Staff Rate Unit Usage Totals
Scientist $90.00 Per Day $0.00
Total Meal/Hotel: $0.00
TOTAL TRAVEL: $0.00
SUBCONTRACTOR COSTS
Total Equip.: $0.00
Services Procurement Name Purpose Rate Units Usage Totals
Erwin Remediation IDW $100.00 Drum -1 ($100.00)
Erwin Remediation IDW $600.00 Lump Sum 1 $600.00NAME OF COMPANY Utility Locate / GPR Survey $0.00 Lump Sum 0 $0.00
Total Services: $500.00
TOTAL SUB: $500.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
VOC (Halocarbons Only) 8260C Aqueous $66.00 1.00 0 $0.00
MN 6020 Aqueous $12.50 1.00 0 $0.00
TAT 24-hr=100% (2.0) 3-day=50% (1.5) 1-week=15% (1.15) Total Lab: $0.00
Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $104.00 Per Cooler 0 $0.00
Shipping - Small (0 to 25 lbs.) --- --- $63.00 Per cooler 0 $0.00
Total Shipping: $0.00
TOTAL LAB: $0.00
FIELD EXPENSES
Personal Protection Item Rate Unit Usage Totals
Total PPE: $0.00
Equipment Item Rate Unit Usage Totals
Expendables Miscellaneous Expendables $32.50 Per Day 0 $0.00
Total Expendables: $0.00
Equipment Items Tubing, Poly/HDPE $0.25 Per Foot 0 $0.00
Total Equipment Items: $0.00
Equipment Kits Shallow Groundwater Sampling Kit $208.55 Day 0 $0.00
Deep Groundwater Sampling Kit $349.20 Day $0.00
Total Equipment Kits: $0.00
TOTAL EQUIPMENT:
Contractor: Arcadis U.S., Inc.
Date: 2/22/2021
Task #: SubTask 1 Project Management
Site: Butler Cleaners SubTask 2 Annual Groundwater Monitoring - 2021
Activity/Phase: SubTask 3
Project Manager: Mike O'Sullivan SubTask 4
SubTask 5
Totals 1 2 3 4 5
Labor Rate Category Staff Member
$50.00 Project Manager O'Sullivan, Michael (MOS) 4 3.8
$50.00 Senior Scientist O'Sullivan, Michael (MOS) 16 16 0 0 0
$27.91 Scientist Martineau, Duncan (DWM) 20 20 0 0 0
$30.65 Drafter/Designer Berndgen, Wendy (WDB) 3 3 0 0 0
$29.91 Project Assistant McLemore, Michele (MMc) 2 2 0 0 0
Total Hours 45 4 41 0 0 0
Direct Labor $1,698.72 $188.75 $1,509.97 $0.00 $0.00 $0.00
Overhead 57.95% $1,349.91 $149.99 $1,199.92 $0.00 $0.00 $0.00
Gen & Admin 21.29% $783.34 $87.04 $696.30 $0.00 $0.00 $0.00
Fringe 37.13% $630.73 $70.08 $560.65 $0.00 $0.00 $0.00
Total Labor $4,462.70 $495.86 $3,966.84 $0.00 $0.00 $0.00
Other Direct Costs $84.94 $9.44 $75.50 $0.00 $0.00 $0.00
Travel
Vehicle Rental $194.00 $194.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00
Per diem + Hotel $162.00 $162.00 $0.00 $0.00 $0.00 Total Travel $356.00 $356.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00
Erwin Remediation IDW $100.00 $100.00 $0.00 $0.00 $0.00 Utilities $0.00 $0.00 $0.00 $0.00 $0.00
Geo-Tek Utility Locate / GPR Survey $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $100.00 $100.00 $0.00 $0.00 $0.00 Handling Fee $10.00 $10.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $110.00 $110.00 $0.00 $0.00 $0.00
Laboratory
Analytical Costs $606.50 $606.50 $0.00 $0.00 $0.00
Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00
Sample Shipping $104.00 $104.00 $0.00 $0.00 $0.00
Total Laboratory $710.50 $710.50 $0.00 $0.00 $0.00
Field Expenses
Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $65.00 $65.00 $0.00 $0.00 $0.00
Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (Analytical related) $479.60 $479.60 $0.00 $0.00 $0.00
Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00
Equipment (Other - MAGS, recon) $0.00 $0.00 $0.00 $0.00 $0.00
Total Field Expenses $544.60 $544.60 $0.00 $0.00 $0.00
Subtotal $6,268.74 $505.30 $5,763.44 $0.00 $0.00 $0.00
Completion Fee $446.27 $49.59 $396.68 $0.00 $0.00 $0.00
Total Estimated Cost $6,715.01 $554.89 $6,160.12 $0.00 $0.00 $0.00
DATE: 2/22/21
LABOR
Category/Staff Work Description Hours
Annual Groundwater Monitoring - 2021 Scientist Prep, local mob/demob, full round of WLs, Sample 9 MWs; manage IDW; sample delivery 20
Senior Scientist Access, GW monitoring technical oversight and offsite notice review 2
Data Evaluation and Letter Report Senior Scientist Technical review; sign and seal report 2
Senior Scientist Data evaluation and preparation of a brief letter report 12
Drafter Figures preparation 3
Document Technician Editing; Letter report preparation 2
TOTAL LABOR: 41
TRAVEL
Vehicle Type Rate Unit Usage Totals
Van/Truck $97.00 Per Day 2 $194.00
Total Vehicle: $194.00
Meals Category/Staff Rate Unit Usage Totals
Scientist $36.00 Per Day 2 $72.00
Hotel Category/Staff Rate Unit Usage Totals
Scientist $90.00 Per Day 1 $90.00
Total Meal/Hotel: $162.00
TOTAL TRAVEL: $356.00
SUBCONTRACTOR COSTS
Total Equip.: $0.00
Services Procurement Name Purpose Rate Units Usage Totals
Erwin Remediation IDW $100.00 Drum 1 $100.00
Total Services: $100.00
TOTAL SUB: $100.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
VOC (Halocarbons Only) 8260C Aqueous $66.00 1.00 9 $594.00
MN 6020 Aqueous $12.50 1.00 1 $12.50
TAT 24-hr=100% (2.0) 3-day=50% (1.5) 1-week=15% (1.15) Total Lab: $606.50
Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $104.00 Per Cooler 1 $104.00
Shipping - Small (0 to 25 lbs.) --- --- $63.00 Per cooler 0 $0.00
Total Shipping: $104.00
TOTAL LAB: $710.50
FIELD EXPENSES
Personal Protection Item Rate Unit Usage Totals
PPE Level D $28.00 Per Man Day 0 $0.00
Total PPE: $0.00
Equipment Item Rate Unit Usage Totals
Expendables Miscellaneous Expendables $32.50 Per Day 2 $65.00
Total Expendables: $65.00
Equipment Items Tubing, Poly/HDPE $0.25 Per Foot 250 $62.50
Total Equipment Items: $62.50
Equipment Kits Shallow Groundwater Sampling Kit $208.55 Day 2 $417.10
Deep Groundwater Sampling Kit $349.20 Day $0.00
Total Equipment Kits: $417.10
TOTAL EQUIPMENT: $544.60
From: OSullivan, Mike To: Pepe, Theresa Cc: Martineau, Duncan Subject: RE: Butler time extension TACO for signature Date: Wednesday, September 8, 2021 12:08:26 PM Attachments: image001.png image002.png image003.png image004.png image005.png image006.png
Theresa, We have been quoted $600 for the transportation and disposal of the drum of purge water that has been classified as hazardous waste based on laboratory results. It will cost more to mobilize to the Site, collect a groundwater sample, and conduct laboratory analysis. I recommend that we dispose of the drum as haz. Please advise and I will submit a TACO (#3). This also applies to Herman Jackson which has a TA that expires on 9/10/21.
Thanks, Mike
Mike O’Sullivan PG Senior Geologist Arcadis U.S., Inc.
1705 Metropolitan Boulevard Tallahassee, FL | 32308 | USA T +1 850 895 4739 M +1 850 491 2346 www.arcadis.com
Professional Geologist / PG-FL, 2468
From: Pepe, Theresa <Theresa.Pepe@FloridaDEP.gov> Sent: Friday, September 3, 2021 10:15 AM To: OSullivan, Mike <Mike.OSullivan@arcadis.com> Cc: Martineau, Duncan <Duncan.Martineau@arcadis.com> Subject: Butler time extension TACO for signature
Good morning Mike, Please see attached time extension for Butler for Arcadis signature. Please make sure this is signed today due to expiration date.
If the drum must be disposed of as Haz, please submit a TACO for the increase in costs. Thanks.
Theresa C. Pepe Florida Department of Environmental Protection Waste Site Cleanup Section mailto:Mike.OSullivan@arcadis.com mailto:Theresa.Pepe@FloridaDEP.gov mailto:Duncan.Martineau@arcadis.com https://nam02.safelinks.protection.outlook.com/?url=http%3A%2F%2Fwww.arcadis.com%2F&data=04%7C01%7C%7C207aab84dc954cc18b0308d8b4066518%7C7f90057d3ea046feb07ce0568627081b%7C0%7C0%7C637457286965667089%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C1000&sdata=o72ZsbrswpvDLlEIuzTlH6qj%2BNaPYFi9CI3V8hSudnY%3D&reserved=0 https://www.linkedin.com/showcase/arcadis-north-america/ https://www.linkedin.com/showcase/arcadis-north-america/ https://twitter.com/Arcadis_NA?ref_src=twsrc%5Egoogle%7Ctwcamp%5Eserp%7Ctwgr%5Eauthor https://twitter.com/Arcadis_NA?ref_src=twsrc%5Egoogle%7Ctwcamp%5Eserp%7Ctwgr%5Eauthor https://www.facebook.com/ArcadisNorthAmerica/ https://www.facebook.com/ArcadisNorthAmerica/ https://www.instagram.com/arcadisglobal/?hl=en https://www.instagram.com/arcadisglobal/?hl=en
408 Ditmar Street
Pensacola, FL 32503
ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562
(850) 292-6511
To: Mr. Mike O’Sullivan
Arcadis U.S., Inc.
1705 Metropolitan Blvd
Tallahassee, FL 32308
September 8, 2021
Re: Hazardous Drum Disposal Quote – Butlers Cleaners - TL006003.0045-FDEP (30081895)
Mr. O’Sullivan:
The price for the disposal of a single (1) drum of hazardous groundwater located at the Butlers
Cleaners Jacksonville, FL will be a flat fee of $600.00 per drum total, for both transportation and disposal.
Respectfully, Jonathan Erwin
Erwin Remediation, Inc.
Email: ErwinRemediation@Gmail.com
Office: (850) 292-6511 mailto:Remediation@Gmail.com
DEP CONTRACT NO.
Task Assignment #: Change Order No.:
Contractor Name:
Contractor Representative:
DEP Contract Manager: Phone #:
Site Name:
Site ID / Facility ID::
Description of Change [use additional pages if necessary]:
The Deliverable and Invoice Schedule is attached.
Final Deliverable:
TASK ASSIGNMENT TYPE AND NOT TO EXCEED AMOUNTS:
Cost Reimbursement Fixed Fee
Original Task Amount
Task Amount Prior to this Change Order Net Increase/decrease in task amount Task amount with all change orders $0.00 $0.00 $0.00 $0.00
Original Task Completion Date:
Completion Date Prior to this Change:
Net /Decrease in Task Period:
Completion Date with all Change Orders:
DEP Task Manager:
DEP Contract Manager:
Contractual Authority:
Contractor Representative:
CC: Procurement Section (MS 93) Section Representative ________
FIXED PRICE
TASK ASSIGNMENT NOTIFICATION CHANGE ORDER FORM
ITEM
$0.00
$0.00
DEP will review the deliverables to verify that they meet the specifications of this contract and task description. DEP’s Contract Manager shall notify the Contractor of any deficiencies in the deliverable(s) and shall give the Contractor reasonable opportunity to correct noted deficiencies and provide a revised deliverable(s).
Final Deliverable Due Date:
$0.00
$0.00
CHANGE IN TASK TIME
FEE SCHEDULE
COST PLUS FIXED FEE
TOTAL
WCP TAFORM 01_18
HW557
2DC002N
Arcadis U.S., Inc.
William Vogelsong
(850) 245-8705Theresa C. Pepe Butler Cleaners
ERIC_4573
This change order adds a time extension of 14 days to the completion date for disposal of one drum of IDW onsite.
Annual Monitoring Report 07/30/2021
$ 6,605.01 $ 0.00 $ 0.00 $ 0.00
$ 6,715.01 $ 0.00 $ 0.00 $ 0.00 $ 6,715.01
$ 0.00 $ 0.00 $ 0.00 $ 0.00 $ 0.00
$ 6,715.01
09/03/2021
09/03/2021
14 days
09/17/2021
Theresa C. Pepe Digitally signed by Theresa C. Pepe Date: 2021.09.02 16:00:08 -04'00'
Theresa C. Pepe Digitally signed by Theresa C. Pepe Date: 2021.09.02 16:00:20 -04'00'
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2021.09.03 10:12:10 -04'00'
Digitally signed by: Mike O'Sullivan DN: CN = Mike O'Sullivan email = mike.osullivan@arcadis.
com C = AD Date: 2021.09.03 10:17:44 -05'00'
Mike O'Sullivan
$ 6,715.01 $ 0.00 $ 0.00 $ 0.00
$ 6,605.01
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number: HW557 Task Assignment #: DC002N
Change Order #: 2
Deliverables:
Deliverable Deliverable Due Date
Annual Monitoring Report 30-Jul-21
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
FDEP approval of Annual Monitoring Report/Project Management $6,715.01
TOTAL COST $6,715.01
BWC TAFORM 01_18
| Task Assignment CHANGE ORDER |
| BWC Task Assignment Change Order Form (Rev 02-17).pdf |
| Task Assignment CHANGE ORDER |
| BWC Task Assignment Form - Page 2 (Rev 08_10) - Rev 1.pdf |
| Deliverable & Invoice Schedule |
| nergsum.pdf |
| Subtask 2: Groundwater Sampling & Reporting |
File details come from the government source that posted it. Updated .