CN-370000-CN229-T21 CO1.pdf
PDF 938 KB Posted
- Contract number
- CN229
- Issued by
- Florida
About this file
This document is a Task Assignment Change Order (Change Order No. CO1) issued by the Florida Department of Environmental Protection (FDEP) to WGI, Inc., a consulting firm based in West Palm Beach, Florida. The change order modifies Task Assignment No. 21 under FDEP Contract No. CN229, which was originally executed on May 11, 2016, with an amendment dated February 4, 2021. The project, titled "Trail Connect – Toms Harbor Channel to Toms Harbor Cut and Toms Harbor Cut to Long Key," is located in Monroe County, Florida, and involves design services for improvements to the Florida Keys Overseas Heritage Trail.
The change order authorizes unforeseen additional services consisting of Subsurface Utility Engineering (SUE) work, which includes Subtask 5 for Utility Designating (ASCE 38-22 Quality Level B) with survey and CADD services totaling $16,634.70 in fixed price costs plus $5,826.00 in reimbursable expenses, and Subtask 5A for Utility Test Holes (ASCE 38-22 Quality Level A) with survey services. The net increase to the task amount is $22,460.70, bringing the total task amount from $217,134.34 to $239,595.04. Work is to be completed within 45 calendar days from the execution date, with a task end date of January 19, 2025. The change order was approved and digitally signed by all required FDEP and consultant representatives on September 9-19, 2024.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Florida Department of Environmental Protection
TASK ASSIGNMENT CHANGE ORDER FORM
( ) Page 1 of 1
Required Signatures: Adobe Signature
FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:
Project Location: Project Name:
Consultant Name:
Consultant Representative: Phone: Email:
FDEP Contract Manager: Phone: Email:
Description and Justification of Change:
Change in Task Amount:
Item Reimbursement Fixed Fee Total
Original Task Amount:
Task amount including all previous Change Orders:
Net increase/decrease in task amount for this Change Order:
Total Amounts with all Change Orders:
Change in Task Time:
Original Task Execution Date:
Original Task End Date:
Present Task End Date:
Net Change in Days:
New Task End Date:
Approval Signatures:
Budget Representative, FDEP Signature Date
Project Manager, FDEP Signature Date
Contract Manager, FDEP Signature Date
Consultant Signature Date
Contract Authority, FDEP Signature Date
Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount
29 Digit FLAIR Code: Total:
CN229 21 CO1 61520C
FKOHT Toms Harbor Cut/Channel and Toms Harbor Cut to Long Key
WGI
Brett Oldford 561.839.1715 brett.oldford@wginc.com
Ralph Perkins or successor 850.245.2460 Ralph.Perkins@FloridaDEP.gov
Trail Connect – Toms Harbor Channel to Toms Harbor Cut and Toms Harbor Cut to Long Key Unforeseen Additional Services – Subsurface Utility Exploration (SUE) per proposal dated 9/3/24.
$ 15,367.00 $ 201,767.34 $ 217,134.34 $ 15,367.00 $ 201,767.34 $ 217,134.34 $ 5,826.00 $ 16,634.70 $ 22,460.70 $ 21,193.00 $ 218,402.04 $ 239,595.04
06/22/2023
01/19/2025
01/19/2025
01/19/2025
Tamika Bass Tamika Bass Digitally signed by Tamika Bass Date: 2024.09.09 15:33:18 -04'00'
Garland Sandel Garland Sandel Digitally signed by Garland Sandel Date: 2024.09.09 15:49:33 -04'00'
Ralph Perkins Ralph M Perkins Digitally signed by Ralph M Perkins Date: 2024.09.10 09:01:39 -04'00'
Brett Oldford Brett N Oldford Digitally signed by Brett N Oldford Date: 2024.09.10 13:27:41 -04'00'
Bryan Bradner Bryan Bradner Digitally signed by Bryan Bradner Date: 2024.09.19 11:12:58 -04'00'
61520C 37505000263 080039/23 000286 U3200 131500 AD $ 22,460.70
$ 22,460.70
2035 Vista Parkway, West Palm Beach, FL 33411 t: 561.687.2220 f: 561.687.1110 www.WGInc.com
, 2024
Garland Sandel Project Manager Florida Department of Environmental Protection Bureau of Design and Construction Division of Recreation and Parks 3900 Commonwealth Blvd., MS 520 Tallahassee, FL 32399-3000 Garland.Sandel@FloridaDEP.gov
RE: FDEP Contract Number CN 229, Change Order 1 for Task Assignment Number 21 Trail Connect – Toms Harbor Channel to Toms Harbor Cut and Toms Harbor Cut to Long Key Unforeseen Additional Services – Subsurface Utility Exploration
Dear Mr. Sandel, WGI, Inc. (WGI) is pleased to provide this additional services proposal to the Florida Department of Environmental Protection (FDEP, CLIENT) for subsurface utility exploration services due to unforeseen conditions on the above referenced project. Tasks being requested by the Department are outlined in the attached Scope of Work, along with corresponding fees. In addition, it is agreed that WGI’s services will be performed pursuant to the contract terms and conditions included in Agreement Number CN229, executed on May 11th, 2016, Amendment Number 1 dated February 4, 2021.
The project consists of the design of proposed trail improvements to the Florida Keys Overseas Heritage Trail in Monroe County, Florida. New portions of the trail will be constructed from Toms Harbor Channel to Toms Harbor Cut (an approximate length of 0.65 miles) and from Toms Harbor Cut to Long Key (an approximate length of 1.2 miles). The missing sections of the trail have mangroves along the shoulder and a shoulder that slopes towards the water.
The scope of services included in this proposal are the installation of an asphalt walkway to connect the existing trails from Long Key to Toms Harbor Channel for a total trail length of 1.85-miles. Our understanding is that the new trail will consist of a 10-foot-wide asphalt paved path with the potential use of retaining walls to support the trail.
Please let me know if you have any questions regarding the attached information.
Sincerely, WGI, Inc.
Brett Oldford, PE Vice President, Civil Engineering Brett OlOOOOOO dfdfdfdfdfdfdfdfdfdfdddfdfdffffffffffdfdfdfdfdddfddfffffffffdfdfdfffffffdffffffffffffforddddddddd PEEEEEEEEEEEEEEEEEEEEEEE
2035 Vista Parkway, West Palm Beach, FL 33411 t: 561.687.2220 f: 561.687.1110 WGInc.com
Trail Connect – Toms Harbor Channel to Toms Harbor Cut and Toms Harbor Cut to Long Key FDEP Contract Number CN 229, Change Order 1 for Task Assignment Number 21
Subtask and A: Utility Designating (ASCE 38-22 Quality Level B) and Utility Test holes (ASCE 38-22 Quality Level A) Description: WGI will perform Subsurface Utility Engineering (SUE) of the areas depicted in figure 1 below. A detailed scope of the SUE services is provided below:
Utility Designating (ASCE 38-22 Quality Level B) w/ Survey & CADD
WGI will perform an ASCE 38-22 Quality Level B (QLB) utility investigation (designates) on existing utilities for verification and horizontal alignment confirmation for QLA Investigation within project limits as shown in Exhibit A.
This QLB investigation includes direct induction of toneable subsurface utility facilities from surface accessible features, and Ground Penetrating Radar sweep for non-toneable facilities. Detected facilities will be marked with American Public Works Association (APWA) compliant colors; flags and water based paint on soft ground and washable chalk on hard surfaces.
WGI will perform survey and location of utility designates using network corrected GNSS surveying methods tied to project control – includes offsite NGS control point verification.
Utility Test holes (ASCE 38-22 Quality Level A) w/ Survey
WGI will provide an ASCE 38-22 Quality Level A (QLA) field investigation (vacuum excavation test holes) within the project limits at the proposed locations as directed by EOR, as needed for utility verification, horizontal / vertical confirmation and in support of civil design services and conflict analysis.
WGI will perform survey and location of utility test holes using network corrected GNSS surveying methods tied to project control.
Any additional QLB and/or QLA days exceeding the proposed amount can be added with written CLIENT authorization, while WGI crews are on-site during initial mobilization.
This proposal is based on two (2) test holes requested.
BASIS OF SCOPE
1. WGI proposes to provide an ASCE 38-22 QLB utility investigation (designates) in order to determine the horizontal alignment of the existing utilities within the project limits (Exhibit A).
2. Geophysical designating techniques, although highly reliable, are subject to outside interference, which are beyond the control of WGI, and may impede the effectiveness of subsurface utility investigations. Soil conditions, utility materials, size, depth, salt water and conductivity may prevent the location of some subsurface utilities. WGI utilizes state of the art equipment and methodology during all phases of utility investigations, but no guarantee is hereby expressed that all facilities will be detected.
3. Survey services are included.
4. Horizontal control will be referenced to NAD83/2011 Adjustment and vertical control referenced to NAVD88.
5. Drafting and/or other CADD services are included.
6. CLIENT shall facilitate access for WGI field staff.
7. CLIENT shall provide a list of known utilities and any drawings, as-builts or other source of information that may help in the location of said utilities.
Trail Connect Toms Harbor Channel to Toms Harbor Cut and Toms Harbor Cut to Long Key
8. Basic work zone safety includes safety road signs and traffic cones.
9. Traffic control, lane closures, if needed are included.
10. Per Diems / Hotels per 2024 GSA rates.
EXCLUSIONS
1. ASCE 38-22 Quality Level A Investigation (test holes) is limited to two (2) test holes.
2. Traffic control conduit investigation is not included.
3. Permits and permit fees, if needed, are not included and are the responsibility of the
CLIENT.
4. Mapping of irrigation lines and sprinkler heads is not included.
5. Invert elevations of storm drainage manholes, culverts, catch basins, and outfalls including pipe sizes and types are not included in the SUE scope.
6. Sanitary sewer (gravity), service laterals and secondary services (private) are excluded.
7. Off duty police not included.
DELIVERABLES
1. WGI will provide a CADD deliverable with the QLB investigations drafted in plan view.
WGI will provide a Utility Report of Subsurface Utility Investigation in PDF format.
LIMITS OF WORK
FIG 1: Toms Harbour Channel
Performance Measure: Deliverables will be reviewed by the Department to confirm they are complete, accurate, and timely.
Trail Connect Toms Harbor Channel to Toms Harbor Cut and Toms Harbor Cut to Long Ke
Utility Designating (ASCE 38-22 Quality Level B) w/ Survey & CADD
Total for Subtask 5: $ 11,870.55
Reimbursable Cost: (if applicable – provide for each task in which reimbursables are required) Postage NA Printing NA Overnight Travel (if applicable)
Hotel 5 nights @ $ x 3 people =$ .00 Meals 5 days $69.0 x 3 people =$1,035.00
Mileage (@ $0.445 per mile) 1 trip 600 miles=$267.00 Reimbursable Total Cost $ .00
Total for Subtask 5: $1 .55
Utility Test holes (ASCE 38-22 Quality Level A) w/ Survey
Total for Subtask 5A: $ 4,764.15
Reimbursable Cost: (if applicable – provide for each task in which reimbursables are required) Postage NA Printing NA Overnight Travel (if applicable)
Hotel 1 night @ $ x 3 people =$ .00 Meals 1 day $69.0 x 3 people =$207.00
Mileage (@ $0.445 per mile) 1 trip 600 miles=$267.00 Reimbursable Total Cost $1, .00
Total for Subtask 5A: $ .15
Subtask 5 Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost WGI Sr. Professional Surveyor $204.45 3 $613.35 WGI Professional Surveyor $172.20 6 $1,033.20 WGI CADD Technician $81.00 16 $1,296.00 WGI Party Chief $86.01 48 $4,128.48 WGI Instrument Person $55.74 48 $2,675.52 WGI Rod Person $44.25 48 $2,124,00
Subtask 5A Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost WGI Sr. Professional Surveyor $204.45 3 $613.35 WGI Professional Surveyor $172.20 4 $688.80 WGI CADD Technician $81.00 6 $486.00 WGI Party Chief $86.01 16 $1,376.16 WGI Instrument Person $55.74 16 $891.84 WGI Rod Person $44.25 16 $708.00
Trail Connect Toms Harbor Channel to Toms Harbor Cut and Toms Harbor Cut to Long Key
Summary of Fees:
Payment will be made upon approval of deliverables for each subtask by the FDEP in the amount specified.
Project Schedule:
Activity Duration (Calendar Days) Subtask 5: SUE – QLB 45 (from execution date) Subtask 5A: SUE – QLA 45 (from execution date)
Subtask Subtask Fixed Price Cost Subtask Reimbursable Subtask 5: SUE – QLB $11,870.55 $ .00 Subtask 5A: SUE – QLA $ 4,764.15 $ .00
Total Fixed Price Cost: $16,634.70 Total Reimbursable Cost: $ .00
Overall Total Cost: $2 .70
File details come from the government source that posted it. Updated .